RERA applied, not grantedHRERA Gurugram

Destination 43

by Craft Infrastructure Pvt. Ltd. · Sector 43

RERA registration
Applied, not granted yet
Applied on
31 Jan 2022
Application status
Rejected
Project ID
RERA-GRG-1003-2022
Land area
2 acres
Plots
32
Completion (as filed)
2 Nov 2026
Estimated cost
₹ 47.72 Cr

This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.

RERA registration

Registration certificateNot issued yet: the application is being processed by HRERA Gurugram
Project IDRERA-GRG-1003-2022
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameDestination 43
PromoterCraft Infrastructure Pvt. Ltd.
Promoter’s registered office158,Bank Enclave,Laxmi Nagar,New Delhi,110092
Site addressSector 43
SectorSector 43
Tehsil / DistrictWazirabad St / Gurugram
Layout plan approved3 Nov 2021
Construction start (as filed)1 Mar 2022
Completion (as filed)2 Nov 2026
Application submitted31 Jan 2022

Authority, hearings & orders

Current statusRejected
Initial scrutinyThe hearing is fixed for 07.03.2022.
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter By Hand
  1. Hearing Examination By Authority
    Proceedings

    Proceedings dated: 07.03.2022. Sh. Ashish Kush, Planning Executive briefed about the facts of the case. An e-mail request dated 07.03.2022 has been received from the promoter requesting 2-3 weeks’ time for rectification of the deficiencies already conveyed vide notice no. HARERA/GGM/RPIN/436 dated 23.02.2022. In view of the request the matter is adjourned to 04.04.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)

  2. Hearing Adjournment
    Proceedings

    Proceedings dated: 04.04.2022. Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Dipendra Pal Jaiswal (AR) is present on behalf of the promoter. The promoter requested the authority for two weeks’ time for the rectification of the deficiencies. The Authority grants the same and the matter to come up on 18.04.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)

  3. Hearing Adjournment
    Proceedings

    Proceedings dated: 18.04.2022. Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Dipendra Jaiswal (Accounts Deptt.) is present on behalf of the promoter. The promoter has not yet rectified the deficiencies conveyed and rather is seeking 2-3 weeks’ time for rectification of the deficiencies. A two weeks’ time is granted as the last opportunity for rectification of all the deficiencies failing which the application shall be considered for rejection/return. The matter to come up on 02.05.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)

  1. Hearing Adjournment
    Proceedings

    Proceedings dated: 02.05.2022. Sh. Ashish Kush, Planning Executive briefed about the facts of the case.Sh. Dipendra Pal Jaiswal (Accounts) is present on behalf of the promoter. The AR of the promoter stated that they have submitted the reply today itself. The reply to be scrutinized by the concerned planning executive. The matter to come up on 09.05.2022..Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)

  2. Hearing Adjournment
    Proceedings

    Proceedings dated: 09.05.2022. Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Sh. Dipendra Prasad Jaiswal (Accountant) is present on behalf of the promoter. The AR of the promoter requested for the adjournment of two weeks for the submission of deficit fee and documents. The Authority directed to submit the deficit fee alongwith the deficit documents mentioned below: 1.        Deficit Fee- Rs 1,21,404/- 2.       The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. 3.       Online DPI needs to be revised. 4.       Demarcation plan and architectural control sheet needs to be submitted. 5.       Approved Service Plan and Estimates needs to be submitted. 6.       Mutation, Jamabandi and aks-shajra duly certified by revenue officer six months prior to date of application needs to be submitted. 7.       Approvals / NOC’s from various agencies for connecting external services like roads, water supply, sewage disposal and storm water drainage needs to be submitted. 8.       Land title search report needs to be revised. 9.       Draft Allotment letter is not as per the prescribed format. 10.   Draft Builder Buyer Agreement needs to be revised.   M/s Skyscrapper Infraprojects Pvt. Ltd. submitted a complaint regarding the objection with respect to the application for registration. .M/s Skyscrapper Infraprojects Pvt. Ltd. filed a suit before the Court of Sh. Sunil Kumar, Ld. Civil Judge, Sr. Division, district Court, Gurugram, bearing No. CS/784/2022, seeking declaration to the effect that the sale deed and subsequent revenue entries in favour of Craft Infrastructure Pvt. Ltd. be declared as illegal null and void being prepared by impersonation and without consideration. The promoter is directed to submit his reply in this regard before the application for grant of registration. Copy of reply be also sent to M/s Skyscrapper Infraprojects Pvt. Ltd. The authority directed the planning executive to supply the copy of complaint to the promoter which was received in the authority. M/s Skyscrapper Infraprojects Pvt. Ltd. may also appear on the next date of hearing if they have to say anything in the matter. The matter to come up on 30.05.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)

  3. Hearing Adjournment
    Proceedings

    Proceedings dated: 30.05.2022. Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Vineet Maheshwari (Legal Head Advocate) is present on behalf of M/s Skyscrapper Infraprojects Pvt. Ltd. Sh. Vishnu Anand, advocate along with Sh. Dipendra Jaiswal (Accountant) are present on behalf of M/s Craft Infrastructure Pvt. Ltd. Apart from rectifying the above deficiencies the promoter is advised to submit that there is no project registered with the Authority of the promoter and as such there is no pending QPRs/ARs. Regarding objection on the land title raised by M/s Skyscrapper Infraprojects Pvt. Ltd., matter is referred to Local Commissioner/Inquiry Officer Sh. S.C. Goyal, Sessions Judge (Retd.) and Sh. Dharam Pal, DRO(Retd.) to examine the documents submitted/to be submitted by both the parties and give their  findings about legal and clear title of the project land.  They will be paid an honorarium of Rs. 25,000/- and Rs. 20,000/- respectively. Both the parties agreed to share the above cost on equal basis. The above honorarium shall include cost of their local visits, engaging any other specialist, documentation and etc. and that the work shall be undertaken beyond official duty hours and no use of official machinery or stationery shall be allowed. The payee party may deduct TDS as per applicable rates.   The deficiencies already conveyed vide proceedings dated 09.05.2022 are not yet rectified and the AR is advised for their rectification. The matter to come up on 04.07.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)

  1. Hearing Adjournment
    Proceedings

    Proceedings dated 04.07.2022.Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Vishnu Anand (Advocate), Sh. Naman Dutt (Advocate), Sh. Dipendra Prasad Jaiswal (Accountant) and Sh. Kapil Chhabra (Sr. Manager) are present on behalf of M/s Craft Infrastructure Pvt. Ltd. Sh. Puneet Sain (Manager Legal) is present on behalf of M/s Skyscrapper Infraprojects Pvt. Ltd. The matter regarding objections about some part of the land of the project was referred to Local Commissioner/Inquiry Officer Sh. S.C. Goyal, Sessions Judge (Retd.) and Sh. Dharam Pal, DRO(Retd.) to examine the documents submitted/to be submitted by both the parties and give their findings about legal and clear title of the project land. Copy of the findings be given to objector and applicant along with copy of the documents filed by the applicant to the objector for submission of the rejoinder if any. Meanwhile the deficiencies as pointed out above be rectified. The matter to come up on 25.07.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)

  2. Hearing Adjournment
    Proceedings

    Proceedings dated: 25.07.2022Sh. Sumeet, Engineer Executive briefed about the facts of the case.Due to administrative work of the Authority, the matter is adjourned to 27.07.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)

  3. Hearing Rejected
    Proceedings

    Sh. Sumeet, Engineer Executive briefed about the facts of the case. Sh. Dipendra Prasad Jaiswal (Accountant), Sh. Vishnu Anand (Advocate) and are present on behalf of the promoter. Sh. Vineet Maheshwari(Legal Head) is present on behalf of the M/s Skyscraper Infraprojects Pvt. Ltd. Inspite of 9 hearings the promoter failed to rectify the deficiencies and submit deficit documents. Regarding land title no response has been received from the promoter as well the objector. The Authority decided to reject the application with a liberty to file afresh after requisite documents are submitted and approvals are obtained. Only processing fee i.e., Rs. 1,21,406/- will be forfeited.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)

Land, licence & cost

Land area of the project2 acres
Total licensed area2 acres
LicenceLICENSE NUMBER 88 OF 2021 DATED 3-11-2021 DIRECTOR TOWN AND COUNTRY PLANNING
FAR permissible / proposed1.5 / 1.38
Estimated project cost₹ 47.72 Cr
Cost of land₹ 7.51 Cr
Infrastructure and other structures₹ 2.07 Cr
EDC, taxes, levies and other costs₹ 38.13 Cr

How the land will be used

UseSq mShare
Plots To Be Sold2,80034.6%
Public Utilities200.2%
Roads5,273.7265.2%

Plots 32 plots

Plot size (sq m)Sq ydSq ftPlots
87.5010594232

External services

ServiceProvided byApproval taken
RoadsHSVPYes
Water SupplyHSVPYes
ElectricityDHBVNLYes
Sewage DisposalHSVPYes
Storm Water DrainageHSVPYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 82.7 lakhYet To Be Prepared
Water Supply System₹ 68.23 lakhYet To Be Prepared
Storm Water Drainage₹ 24.91 lakhYet To Be Prepared
Sewage Treatment & Garbage Disposal₹ 21.26 lakhYet To Be Prepared
Street Lighting₹ 7.68 lakhYet To Be Prepared
Horticulture Plantation And Road Side Trees₹ 2.31 lakhYet To Be Prepared

Statutory approvals

ApprovalStatusDate
Ce-I/Ace(Hq)/(Hdm)(G)/2021/217436Already Been Obtained24 Dec 2021

Specifications (as filed)

Water StorageNa`

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Destination 43?