Shop No 74-75 Divine City, Ratgal, Kurukshetra -136118, Haryana
CIN
U70103HR2021PTC098917
Site address
Village Darakhera & Narkatari, Sector 46 Kurukshetra
Sector
Sector 46
Tehsil / District
Thanesar / Kurukshetra
Layout plan approved
14 Nov 2022
Construction start (as filed)
26 Jan 2023
Completion (as filed)
25 Jan 2027
Application submitted
24 Dec 2022
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyListed for first hearing.
Next hearingNot Required
Application submitted online
Application received by HRERA Panchkula
HearingExamination By AuthorityView order Proceedings
Adjourned to 30.01.2023
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Approved for registration certificate
Registration valid till
Land, licence & cost
Land area of the project
36.231 acres
Total licensed area
36.231 acres
Licence
186 of 2022(14.11.2022)
Estimated project cost
₹ 122.93 Cr
Cost of land
₹ 17.64 Cr
Infrastructure and other structures
₹ 70.42 Cr
EDC, taxes, levies and other costs
₹ 34.87 Cr
How the land will be used
Use
Sq m
Share
Plots To Be Sold
74,275.6
50.7%
Construction Of Roads
42,019.66
28.7%
Parks And Playgrounds
11,055.43
7.5%
Electricity Sub-Station
125
0.1%
Area To Be Left For Transferring To The Government For Community Services
14,670.478
10%
Any Other
215.72
0.1%
Commercial
4,261.14
2.9%
Plots 539 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
4,261.14
5,096
45,866
15
74,275.60
88,833
799,495
524
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
No
Electricity
HVPNL
No
Sewage Disposal
HSVP
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 10.53 Cr
As Per Project Report
Water Supply System
₹ 11.71 Cr
As Per Project Report
Storm Water Drainage
₹ 6.93 Cr
As Per Project Report
Electricity Supply System
₹ 5.4 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 10.83 Cr
As Per Project Report
Street Lighting
₹ 1.56 Cr
As Per Project Report
Playgrounds And Parks
₹ 20.94 lakh
As Per Project Report
Stp
₹ 2.88 Cr
Yet To Be Prepared
Underground Water Tank
₹ 3.96 Cr
Yet To Be Prepared
Rainwater Harvesting
₹ 1.44 Cr
Yet To Be Prepared
Electric Sub Station
₹ 7.2 Cr
Yet To Be Prepared
Construction Of Twenty Four Mtr Road
₹ 1.51 Cr
Yet To Be Prepared
Commercial Development
₹ 1.8 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
14 Nov 2022
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Dd City ( The Dream Destination)?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.