Registration validHRERA Gurugram

Dalcore The Falcon

by Ahir Infraspace Pvt Ltd · Plot No Gh-25, Sector 53, Gurugram II

RERA registration
GGM/913/645/2025/16
Registered on
13 Feb 2025
Valid till
31 Mar 2031
Project ID
RERA-GRG-1838-2024
Apartments
101 in 1 tower
Completion (as filed)
31 Mar 2031
Estimated cost
₹ 595.96 Cr

RERA registration

Registration certificateGGM/913/645/2025/16, dated 13 Feb 2025
Registration valid till31 Mar 2031
Project IDRERA-GRG-1838-2024
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameDalcore The Falcon
PromoterAhir Infraspace Pvt Ltd
Promoter’s registered office10A, 10TH Floor, Grand View Tower, Sector 58, Gurugram, Haryana 122002
CINU45309GJ2019PTC109121
Site addressPlot No Gh-25, Sector 53, Gurugram II
SectorSector 53
Tehsil / DistrictWazirabad St / Gurugram
Building plans approved5 Dec 2024
Construction start (as filed)1 Apr 2025
Completion (as filed)31 Mar 2031
Application submitted31 Dec 2024

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyFirst Hearing
Next hearingNot Required
  1. Application submitted online
  2. Notice sent to the promoter Hand Recieved By Ar And Uploaded Online
  3. Hearing Examination By Authority View order
    Proceedings

    The matter is adjourned and to come up on 05.02.2025. 

  1. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Ar. Neeraj Gautam, Associate Architectural Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Tarun Yadav, Sh. Harshvardhan Yadav and Sh. Manjeet Singh are present on behalf of the promoter. Approved as proposed. The certificate shall be issued after rectification of remaining deficiencies pointed out in para no. 21 above.

  2. Registration granted GGM/913/645/2025/16
  3. Certificate uploaded RC Uploaded
  1. Registration valid till

Land, licence & cost

LicenceZO002/EO018/UE029/GALOT/0000001441
FAR permissible / proposed3.15 / 3.136
Estimated project cost₹ 595.96 Cr
Cost of land₹ 125.09 Cr
Cost of construction₹ 298.26 Cr
Infrastructure and other structures₹ 29.69 Cr
EDC, taxes, levies and other costs₹ 142.92 Cr

How the land will be used

UseArea (as filed)Share
Land Area To Be Used For Construction Of Apartments2,834.46634.9%
Construction Of Roads3,308.87440.7%
Parks And Playgrounds1,220.21915%
Green Belts729.9619%
Electricity Sub-Station28.730.4%
Guardroom100.1%

Apartments 101 units · 1 tower

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings207.692,23658
Apartment/Shops/Other Buildings172.151,85328
Apartment/Shops/Other Buildings190.122,0464
Apartment/Shops/Other Buildings135.121,4543
Apartment/Shops/Other Buildings330.593,5582
Apartment/Shops/Other Buildings284.623,0641
Apartment/Shops/Other Buildings39.774281
Apartment/Shops/Other Buildings203.302,1882
Apartment/Shops/Other Buildings170.231,8322

Areas are as filed with HRERA.

External services

ServiceProvided byApproval taken
RoadsHSVPYes
Water SupplyGMDANo
ElectricityDHBVNNo
Sewage DisposalGMDANo
Storm Water DrainageGMDANo

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 1.27 CrAs Per Project Report
Water Supply System₹ 3 CrAs Per Project Report
Storm Water Drainage₹ 2.5 CrAs Per Project Report
Electricity Supply System₹ 2 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 60 lakhAs Per Project Report
Street Lighting₹ 25 lakhAs Per Project Report
Security And Fire Fighting₹ 4 CrAs Per Project Report
Playgrounds And Parks₹ 1.25 CrAs Per Project Report
Renewable Energy System₹ 80 lakhAs Per Project Report
Stp₹ 50 lakhAs Per Project Report
Electrical Sub Station₹ 5 CrAs Per Project Report
Underground Water Tank₹ 3.52 CrAs Per Project Report
Rainwater Harvesting₹ 2.5 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
Zoning PlanAlready Been Obtained11 Oct 2024
Assurance Of Water SupplyAlready Been Obtained25 Jun 2024
Noc For Use Of Treated Waste WaterAlready Been Obtained24 Apr 2024
Permission For Tree CuttingAlready Been Obtained5 Feb 2024
Assurance Of Sewerage ConnectionAlready Been Obtained25 Jun 2024
Assurance Certificate Of DHBVN For Power SupplyAlready Been Obtained12 Jun 2024
Noc For Aravali By Deputy CommissionerAlready Been Obtained18 Jun 2024
Building Plan ApprovalAlready Been Obtained5 Dec 2024
Noc For Height Clearance From AaiAlready Been Obtained16 Jul 2024
Environment ClearanceAlready Been Obtained14 Nov 2024
Fire Scheme ApprovalAlready Been Obtained21 Oct 2024
Service Plan ApprovalAlready Been Obtained24 Sep 2024

Specifications (as filed)

Flooring Details Of Various Parts Of HouseStone / Tiles In Common Areas
Wall Finishing DetailsAcrylic Emulsion Paint/ Oil Bound Distemper
Kitchen DetailsFloor: Vitrified Tiles, Wall: Ceramic Tiles 2FT Above Counter And Obd Paint On Remaining Area, Ceiling: Obd Paint
Bathroom FittingsAll Provided With Standard Company Make
Wood Work EtcEntrance Doors, Rooms & Toilet
Doors And Windos FramesWooden/ Upvc/ Aluminium /Ms Frame With Glass
Glass Work4MM And Above As Per Specifications
Electric FittingsAs Per The Nbc
Conducting And Wiring DetailsAs Per The Nbc
Water StorageUnderground Tank & Over Head Tank
Lift Details4 Nos Passenger Lift & 1NO Service Lift
Windows/GlazingsUpvc / Aluminum / Ms / Wooden Frames With Single / Double Glass Unit With Clear Glass In Shutters & Wire Mesh Shutters In Habitable Rooms. Upvc / Aluminium / Ms Frames With Frosted / Clear Glass In Toilet
DoorsPainted/Polished Frame With Painted / Laminated / Polished / Veneered Flush Door
Main DoorsPainted/Polished Frame With Painted / Laminated / Polished / Veneered Flush Door
Internal DoorsPainted/Polished Frame With Painted / Laminated / Polished / Veneered Flush Door
Air ConditioningAir-Conditioning Apartment With Energy Efficient Vrv/Vrf System Excluding Toilets & Common Area.
Electrical FittingsModular Touch Switches With Copper Wiring, Standard Ceiling Fans In All Rooms (Except Toilets) Exhaust Fan In Toilet & Kitchen & Ceiling Light Fixtures In Balconies. Home Automation For Selected Services As Per Design
External Finishing/Colour SchemeExternal Grade Paints/ As Per Nbc
Internal FinishingPainting On Plaster Surface/ As Per Nbc

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Dalcore The Falcon?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.