RERA registration
Registration certificateGGM/313/45/2019/07, dated 18 Feb 2019
Registration valid till31 Dec 2021
Project IDRERA-GRG-143-2018
AuthorityHRERA Gurugram
Project type (as filed)Ongoing
Project nameCrosswalk
PromoterJms Buildtech Pvt. Ltd./Ramaprastha Estate Pvt. Ltd.
Promoter’s registered office3RD Floor, Plot No. 10, Sector-44, Gurugram
CINU70109HR2013PTC048244
Site addressSector -93, Gurugram
SectorSector 93
Tehsil / DistrictGurgaon / Gurugram
Application submitted29 Jan 2019
Authority, hearings & orders
Current status Approved And Certificate Uploaded
Next hearing Not Required
29 Jan 2019
Application submitted online
8 Feb 2019
Application received by HRERA Gurugram
18 Feb 2019
Registration granted
GGM/313/45/2019/07
31 Dec 2021
Registration valid till
Land, licence & cost
Land area of the project2 acres
Total licensed area128.594 acres
Licence44 of 2010
FAR permissible / proposed150 / 150
Estimated project cost₹ 131.66 Cr
Cost of land₹ 18.9 Cr
Cost of construction₹ 68.04 Cr
Infrastructure and other structures₹ 7.4 Cr
EDC, taxes, levies and other costs₹ 2 Cr
How the land will be used
Use Area (as filed) Share
Plots To Be Sold8,093.7 46.4% Construction Of Roads6,250 35.8% Green Belts2,025.929 11.6% Vehicle Parkings253 1.4% Electricity Sub-Station488.16 2.8% Sewage And Solid Waste Treatment Facility339.66 1.9%
External services
Service Provided by Approval taken
RoadsNOT YET AWARDED No Water SupplyNOT YET AWARDED No ElectricityNOT YET AWARDED No Sewage DisposalNOT YET AWARDED No Storm Water DrainageNOT YET AWARDED No
Facilities in the service plan
Facility Estimated cost Status
Internal Roads And Pavements₹ 20 lakh Yet To Be Prepared Water Supply System₹ 20 lakh Yet To Be Prepared Storm Water Drainage₹ 10 lakh Yet To Be Prepared Electricity Supply System₹ 15 lakh Yet To Be Prepared Sewage Treatment & Garbage Disposal₹ 20 lakh Yet To Be Prepared Street Lighting₹ 10 lakh Yet To Be Prepared Security And Fire Fighting₹ 1 Cr Yet To Be Prepared Playgrounds And Parks₹ 5 lakh Yet To Be Prepared Renewable Energy System₹ 3 lakh Yet To Be Prepared
Statutory approvals
Approval Status Date
Forest NocAlready Been Obtained 24 Aug 2015
Airport HeightAlready Been Obtained 1 Sep 2015
HUDA ConstructionAlready Been Obtained 30 Jun 2015
Electricity LoadAlready Been Obtained 17 Jul 2015
Enviornment ClearanceAlready Been Obtained 1 May 2016
Consent To EstablishAlready Been Obtained 22 Feb 2014
Mining PermissionAlready Been Obtained 5 Aug 2016
Fire Scheme ApprovalYet To File For Approval
Source: HRERA Gurugram, Form REP-I , read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.