Registration validHRERA Gurugram

Courtyard 37D

by Eternal Housing Infra LLP · Revenue Estate Of Vill- Harsaru, Sector - 37D, Gururgam

RERA registration
GGM/727/459/2023/71
Registered on
19 Jun 2023
Valid till
29 Feb 2028
Project ID
RERA-GRG-1360-2023
Land area
2.2 acres
Plots
27
Completion (as filed)
29 Feb 2028
Estimated cost
₹ 50.48 Cr

(SUPERSEDED BY GGM/798/530/2024/25 DATED 15.03.2024)

RERA registration

Registration certificateGGM/727/459/2023/71, dated 19 Jun 2023
Registration valid till29 Feb 2028
Project IDRERA-GRG-1360-2023
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameCourtyard 37D
Site addressRevenue Estate Of Vill- Harsaru, Sector - 37D, Gururgam
SectorSector 37D
Tehsil / DistrictHarsaru St / Gurugram
Layout plan approved7 Mar 2023
Building plans approved18 May 2023
Construction start (as filed)1 Jun 2023
Completion (as filed)29 Feb 2028
Application submitted7 May 2023

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter 1st deficiency notice
  1. Hearing Adjournment View order
    Proceedings

    Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Balram Jha is present on behalf of the promoter. The reply of a few observations has been submitted today including standard design of SCOs approved by DGTCP on 18.05.2023 in the registry and regarding details of payment of  license fee and EDC/IDC is also being submitted today. Office to check the status of compliances in view of above reply and matter to come up on 29.05.2023.

  2. Hearing Adjournment View order
    Proceedings

    Proceedings dated: 29.05.2023. Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Balram Jha is present on behalf of the promoter. The AR of the promoter is directed to rectify the deficiencies. Matter to come up on 05.06.2023 for further proceedings. 

  3. Hearing Adjournment View order
    Proceedings

    Coram is not complete. The matter is placed before the authority and as per the directions of authority the matter is adjourned to 07.06.2023.

  1. Hearing Adjournment View order
    Proceedings

    Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Balram Jha (AR) is present on behalf of the promoter. On the request of the AR of the promoter the matter is adjourned to 19.06.2023 and he is further directed to rectify the deficiencies by 14.06.2023. 

  2. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Balram Jha (AR) is present on behalf of the promoter. Approved as proposed. The registration certificate shall be issued only after submission of requisite undertakings and pending corrections in A to H and DPI. 

  3. Registration granted GGM/727/459/2023/71
  1. Certificate uploaded RC Uploaded
  2. Registration valid till

Land, licence & cost

Land area of the project2.2 acres
Total licensed area2.2 acres
LicenceLicence No. 47 of 2023 dated 02.03.2023 and valid upto 01.03.2028
FAR permissible / proposed150 / 149.91
Estimated project cost₹ 50.48 Cr
Cost of land₹ 31.99 Cr
Infrastructure and other structures₹ 3.04 Cr
EDC, taxes, levies and other costs₹ 15.45 Cr

How the land will be used

UseAcresShare
Plots To Be Sold0.646829.4%
Parkingandservices0.981244.6%
Serviceroadandgreenbeltandsectorroad0.57226%

Plots 27 plots

Plot size (sq m)Sq ydSq ftPlots
96.921161,04314
96.961161,04413

External services

ServiceProvided byApproval taken
RoadsCONNECTEDYes
Water SupplyHSVPYes
ElectricityDHBVNYes
Sewage DisposalHSVPYes
Storm Water DrainageHSVPYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 64.97 lakhAs Per Project Report
Storm Water Drainage₹ 11.01 lakhAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 9.75 lakhAs Per Project Report
Street Lighting₹ 3 lakhAs Per Project Report
Plantation And Road Side Trees₹ 5.22 lakhAs Per Project Report
Mtc Charges₹ 98 lakhAs Per Project Report
Water Supply And Fire Fighting Scheme₹ 62 lakhAs Per Project Report
Toilet₹ 5 lakhAs Per Project Report
Utility₹ 30 lakhAs Per Project Report
Parking₹ 15 lakhAs Per Project Report

Statutory approvals

ApprovalStatusDate
License: 1Already Been Obtained2 Mar 2023
Architectural Control SheetsAlready Been Obtained18 May 2023
Service Plan Estimates ApprovalApplied For But Yet To Receive28 Apr 2023

Specifications (as filed)

Flooring Details Of Various Parts Of HouseN/A
Wall Finishing DetailsN/A
Kitchen DetailsN/A
Bathroom FittingsN/A
Wood Work EtcN/A
Doors And Windos FramesN/A
Glass WorkN/A
Electric FittingsN/A
Conducting And Wiring DetailsN/A
Cupboard DetailsN/A
Water StorageN/A
Lift DetailsN/A
External GlazingsN/A
Windows/GlazingsN/A
DoorsN/A
Main DoorsN/A
Internal DoorsN/A
Air ConditioningN/A
Electrical FittingsN/A
Cng Pipe LineN/A
Provision Of Wifi And Broadband FacilityN/A
External Finishing/Colour SchemeN/A
Internal FinishingN/A

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Courtyard 37D?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.