Registration validHRERA PanchkulaInterim ReraOC / CC on record

Commercial Colony Area 4314.13 Sq. Mtrs.

by Robust Buildwell Pvt. Ltd. · Sector-79, Village Bhatola

RERA registration
315 OF 2017
Registered on
17 Oct 2017
Valid till
31 Dec 2027
Project ID
RERA-PKL-458-2019
Estimated cost
₹ 25.01 Cr

RERA registration

Registration certificate315 OF 2017, dated 17 Oct 2017
Registration valid till31 Dec 2027
Project IDRERA-PKL-458-2019
AuthorityHRERA Panchkula (Interim Rera)
Project type (as filed)Ongoing
Project nameCommercial Colony Area 4314.13 Sq. Mtrs.
PromoterRobust Buildwell Private Limited
Promoter’s registered officeOmaxe City Centre Sector 79 Faridabad 121004 Haryana
CINU74120HR2007PTC036993
Site addressVillage Bhatola, Sector-79, Faridabad
SectorSector 79
Tehsil / DistrictFaridabad / Faridabad
Application submitted15 Jun 2019

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Next hearingNot Required
  1. Registration granted 315 OF 2017
  2. Application submitted online
  3. Application received by HRERA Panchkula
  1. Registration valid till

Land, licence & cost

Licence51 and 52 of 2017
FAR permissible / proposed1.5 / 1.5
Estimated project cost₹ 25.01 Cr
Cost of land₹ 1.45 Cr
Cost of construction₹ 7.24 Cr
Infrastructure and other structures₹ 4.56 Cr
EDC, taxes, levies and other costs₹ 11.76 Cr

How the land will be used

UseArea (as filed)Share
Plots To Be Sold1,928.5644.7%
Construction Of Roads351.418.1%
Pavements893.7420.7%
Vehicle Parkings263.266.1%
Any Other877.1620.3%

External services

ServiceProvided byApproval taken
RoadsHARYANA PWD (B&R) DEPARTMENTYes
Water SupplyHARYANA URBAN DEVELOPMENT AUTHORITYYes
ElectricityDAKSHIN HARYANA BIJLI VITRAN NIGAMYes
Sewage DisposalNoSTORM WATER DRAINAGE
No4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:Sr. No.
Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS70.8
Yet To Be Prepared2WATER SUPPLY SYSTEM
2YET TO BE PREPARED3
Storm Water Drainage11.9YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM256
Yet To Be Prepared5SEWAGE TREATMENT & GARBAGE DISPOSAL
2YET TO BE PREPARED6
Street Lighting0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING6
Yet To Be Prepared8PLAYGROUNDS AND PARKS
5.8YET TO BE PREPARED9
Club House/Community Centre0YET TO BE PREPARED
10SHOPPING AREA0
Yet To Be Prepared11RENEWABLE ENERGY SYSTEM
0YET TO BE PREPARED12
School0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0
Yet To Be Prepared14ANY OTHER
0YET TO BE PREPARED15
Re Development And Beautication Of Existing Govt Road1.010YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.NA(date)
6. Date of approval of Building PlansNA(date)
(i) Details of the plots/apartments in the project:Sr. No.Plot/ apartment type
Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectTotal size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type SCO403.43
31210.293
012
APARTMENT/SHOPS/OTHER BUILDINGS Type SCO403.643
1210.9230
13APARTMENT/SHOPS/OTHER BUILDINGS Type SCO
406.55156098.25
1501
4APARTMENT/SHOPS/OTHER BUILDINGS Type SCO406.59
62439.546
015
APARTMENT/SHOPS/OTHER BUILDINGS Type SCO406.613
1219.8330
16APARTMENT/SHOPS/OTHER BUILDINGS Type SCO
406.8931220.67
301
7APARTMENT/SHOPS/OTHER BUILDINGS Type SCO406.95
31220.853
018
APARTMENT/SHOPS/OTHER BUILDINGS Type SCO406.983
1220.9430
19APARTMENT/SHOPS/OTHER BUILDINGS Type SCO
407.131221.3
301
10APARTMENT/SHOPS/OTHER BUILDINGS Type SCO407.6
31222.83
0111
APARTMENT/SHOPS/OTHER BUILDINGS Type SCO478.543
1435.6230
1Total48
19721.01480
11(ii) Apartments/Shops/Other Buildings:-(a) Status of construction activities in respect of sold/booked apartments.
TypeNumber of apartments booked/ soldWrite or Annex the stage of construction of the booked/ sold apartments in folder C
SCO48COMPLETE
(b) Time schedule of completion of already booked apartments:Start Date01-08-2016
Earlier date of completion31-12-2020Revised date of completion
30-06-2021(c) Time schedule for development of infrastructure:Start Date
01-08-2016Percentage completion Upto the   date of application
55Projected date of completion30-06-2021
(d) Provide further details in the proforma REP-I Part-C-X.(e) Plan of action for completing the Project along with requisite infrastructure.WORK WILL BE COMPLETED UPTO 30.06.2021
(iii) Status in respect of plotted colony:-(a)Plots
Booked/soldStage of handing over the possession (Write or Annex details)PLOT
00(b) Schedule for development of Infrastructure:
Start Date01-08-2016Percentage completion
55Projected date of completion30-06-2021
(c) Provide further details in the proforma REP-I Part-C-X.(d) Schedule of completing the project and handing over possession of the plots.(iv) Vehicle parkings details of the project-
a) Underground parking48b) Stilt parking
0c) Covered parking0
d) Open parking0e) Independent garages
0(v) Quarterly schedule of development of whole/remaining part of the project:(a) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)ParticularsExpenditure
Expenditure to be made in each quarter (In Lakhs)ParticularsYear-2021
Jan-MarApr-JuneJuly-Sep
Oct-DecApartments0
0Shops18
10Plots0
0(b) InfrastructureExpenditure incurred till the date of application (In Lakhs)
ParticularsExpenditureExpenditure to be made in each quarter (In Lakhs)
ParticularsYear-2020Jan-Mar
Apr-JuneJuly-SepOct-Dec
Roads & Pavements2.01.8
00Water Supply System
000
0Sewerage treatment & garbage disposal0
000
Electricity Supply System10.010.0
20.020.0Storm Water Drainage
000
0Parks and Playgrounds0
000
Clubhouse/community centres00
00Shopping area
000
0Other5.0
5.01.00
ParticularsYear-2021Jan-Mar
Apr-JuneJuly-SepOct-Dec
Roads & Pavements00
Water Supply System00
Sewerage treatment & garbage disposal00
Electricity Supply System26.05.0
Storm Water Drainage1.00.9
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.Signature of the Applicant / Authorised RepresentativeStamp _____________
Date _____________FORM REP-IPart - C-X
1.Financial information:ParticularsRemarks, if any
i. No. of Flats/Apartments constructed48ii. No. of Flats/ Apartments booked
48iii. Total amount sale value of booked Flats, on the date of application/end of last quarter2493 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter1486 Lakhsv. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
346 LakhsUndue Amountvi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
661 LakhsDue Amountvii. Amount invested in the project upto the date of application
0 LakhsLand cost (If any)145 Lakhs
Apartments415 LakhsInfrastructure
120 LakhsEDC/ Taxes Etc.701 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession1120 Lakhs(a) In respect of existing allottees
0 Lakhs(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the projectAnnex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)0 Lakhs2.Additional information:
ParticularsEstimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. Internal Roads And Pavements70.850
II. Water Supply System20
III. Storm Water Drainage11.95
IV. Electricity Supply System25626.5
V. Sewage Treatment & Garbage Disposal00
Vi. Club House/Community Centre00
Vii. School00
Viii. Any Other00
Ix. Solid Waste Collection & Mgmt System00
X. Clubhouse00
Xi. Neighbourhood Shopping00
Xii. Green Areas,Parks,Playgrounds Etc.5.80.5
Xiii. Covered Parking00
Xiv. Open Parking00
Xv. Garages00
Xvi. Security System61
Xvii. Other Facilities As Per Project Report10135
I hereby declare that the above information and particulars are based on record and are true to thebest of my knowledge and belief and nothing has been concealed.Signature of the Applicant / Authorised Representative
Stamp _____________Date _____________FORM REP-I
Part - DAccounts related information:1. Annex copy of the balance sheet of last 3 years
Yes2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
No3. Bank account to which the deposits received from apartment buyers will be creditedBank and Branch address
Yes Bank, South Ex. Part -2Bank Account number1666300000125
IFSC codeYESB0000016MICR code
110532006Branch code000016

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 70.8 lakhYet To Be Prepared
Water Supply System₹ 2 lakhYet To Be Prepared
Storm Water Drainage₹ 11.9 lakhYet To Be Prepared
Electricity Supply System₹ 2.56 CrYet To Be Prepared
Sewage Treatment & Garbage Disposal₹ 2 lakhYet To Be Prepared
Security And Fire Fighting₹ 6 lakhYet To Be Prepared
Playgrounds And Parks₹ 5.8 lakhYet To Be Prepared
Re Development And Beautication Of Existing Govt Road₹ 1.01 lakhYet To Be Prepared

Statutory approvals

ApprovalStatusDate
License No. 51 Of 2017 Dated 22.02.2017 & 52 Of 2017 Dated 22.02.2017Already Been Obtained
Demarcation PlanAlready Been Obtained
Zoning Plan Drg No. Dgtcp 6010 Dt. 24.07.2017Already Been Obtained
Noc For Height Clearance No. Aai/Rhq/Nr/Atm/Noc/2014/475/9085-88Already Been Obtained
Consent To Establish From Pollution Angle No.-Hspcb/Consent/:329962316FDBDCTE3450348Already Been Obtained
Environment Clearance No. Seiaa/Hr/2016/904Already Been Obtained

Specifications (as filed)

Flooring Details Of Various Parts Of HouseNo Flooring
Wall Finishing DetailsOnly Plaster
Kitchen DetailsN/A
Bathroom FittingsN/A
Wood Work EtcN/A
Doors And Windos FramesFlush Door
Glass WorkN/A
Electric FittingsIn Shops Upto Db Only, In Common Area Complete Provision
Conducting And Wiring DetailsOnly Wall And Ceiling Condution And M.s. Box In Walls
Water StoragePvc Tank At Terrace
Windows/GlazingsUpvc Door Window
Main DoorsFlush Door
External Finishing/Colour SchemeExternal Wheather Shield Paint

Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Commercial Colony Area 4314.13 Sq. Mtrs.?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.