HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS
Registration valid till
Land, licence & cost
Land area of the project
25.894 acres
Total licensed area
25.894 acres
Licence
LICENSE NO. 146 OF 2025, GRANTED BY DTCP HARYANA ON 14-08-2025, IS VALID UP TO 13-08-2030
FAR permissible / proposed
1 / 1
Estimated project cost
₹ 27.34 Cr
Cost of land
₹ 8.09 Cr
Infrastructure and other structures
₹ 13.21 Cr
EDC, taxes, levies and other costs
₹ 6.05 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
12.9877
50.2%
Construction Of Roads
7.7726
30%
Parks And Playgrounds
1.9422
7.5%
Area To Be Left For Transferring To The Government For Community Services
2.6669
10.3%
Area Under Commercial
0.5243
2%
Plots 373 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
129.63
155
1,395
6
131.12
157
1,411
7
135.10
162
1,454
8
137.06
164
1,475
12
137.53
164
1,480
64
137.65
165
1,482
19
138.07
165
1,486
8
138.84
166
1,494
12
138.99
166
1,496
6
139.68
167
1,504
9
140.52
168
1,513
56
140.83
168
1,516
5
141.30
169
1,521
13
141.55
169
1,524
10
141.82
170
1,527
15
142.42
170
1,533
8
142.77
171
1,537
15
143.42
172
1,544
6
144.71
173
1,558
8
145.07
174
1,562
14
145.73
174
1,569
12
146.17
175
1,573
26
146.78
176
1,580
12
147.67
177
1,590
7
148.59
178
1,599
12
149.54
179
1,610
2
149.65
179
1,611
1
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
No
Electricity
DHBVN
No
Sewage Disposal
HSVP
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 3.61 Cr
As Per Project Report
Water Supply System
₹ 2.09 Cr
As Per Project Report
Storm Water Drainage
₹ 1.53 Cr
As Per Project Report
Electricity Supply System
₹ 1.77 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 2.01 Cr
As Per Project Report
Street Lighting
₹ 64.44 lakh
As Per Project Report
Playgrounds And Parks
₹ 56.91 lakh
As Per Project Report
Boundary Wall
₹ 99.3 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Approval Of Layout Plan
Already Been Obtained
14 Aug 2025
Demarcation Cum Zoning Plan
Already Been Obtained
1 Oct 2025
Standard Design Of Sco's
Already Been Obtained
1 Oct 2025
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Clean Earth Enclave?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.