Registration validHRERA Panchkula

Ceremony Enthia

by Ceremonyhomes Private Limited · Hsiidc,Block-D,Export Complex

RERA registration
HRERA-PKL-PNP-510-2023
Valid till
19 Apr 2027
Project ID
RERA-PKL-1311-2023
Apartments
68
Completion (as filed)
30 Sep 2025
Estimated cost
₹ 41.4 Cr

RERA registration

Registration certificateHRERA-PKL-PNP-510-2023
Registration valid till19 Apr 2027
Project IDRERA-PKL-1311-2023
AuthorityHRERA Panchkula
Project type (as filed)New
Project nameCeremony Enthia
PromoterCeremonyhomes Private Limited
Promoter’s registered officeSCO-20, Eldeco Estate One Sec-40 Panipat Haryana-132103
CINU70101HR2020PTC088032
Site addressHsiidc,Block-D,Export Complex
Tehsil / DistrictPanipat / Panipat
Construction start (as filed)1 Oct 2023
Completion (as filed)30 Sep 2025
Application submitted1 Sep 2023

Authority, hearings & orders

Current statusExtension Certificate Uploaded
Initial scrutinyListed for hearing on 03-06-2026
Next hearingNot Required
  1. Application submitted online
  2. Hearing Examination By Authority View order
    Proceedings

    Adjourned to 04.12.2023

  3. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS.

  1. Application received by HRERA Panchkula
  2. Hearing Extension First Hearing View order
    Proceedings

    Listed for hearing on 24-06-2026

  3. Hearing Extension Approved View order
    Proceedings

    Disposed as of Extension Approved

  1. Registration valid till

Land, licence & cost

Licence00 of 2022 (HSIIDC 5452)
FAR permissible / proposed400 / 400
Estimated project cost₹ 41.4 Cr
Cost of land₹ 12.03 Cr
Cost of construction₹ 22.97 Cr
EDC, taxes, levies and other costs₹ 6.39 Cr

How the land will be used

UseArea (as filed)Share
Land Area To Be Used For Construction Of Apartments1,728100%

Apartments 68 units

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings100.701,0844
Apartment/Shops/Other Buildings88.2795012
Apartment/Shops/Other Buildings79.778592
Apartment/Shops/Other Buildings101.341,0912
Apartment/Shops/Other Buildings101.921,09710
Apartment/Shops/Other Buildings75.478122
Apartment/Shops/Other Buildings65.927102
Apartment/Shops/Other Buildings31.413382
Apartment/Shops/Other Buildings52.615664
Apartment/Shops/Other Buildings52.9157022
Apartment/Shops/Other Buildings52.215622
Apartment/Shops/Other Buildings77.018292
Apartment/Shops/Other Buildings25.242722

Areas are as filed with HRERA.

External services

ServiceProvided byApproval taken
RoadsNoWATER SUPPLY
NoELECTRICITYNo
Sewage DisposalNoSTORM WATER DRAINAGE
No4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:Sr. No.
Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS819890
As Per Project Report2WATER SUPPLY SYSTEM
1377313AS PER PROJECT REPORT3
Storm Water Drainage395799AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM15179529
As Per Project Report5SEWAGE TREATMENT & GARBAGE DISPOSAL
657275AS PER PROJECT REPORT6
Street Lighting320029AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING5000000
As Per Project Report8PLAYGROUNDS AND PARKS
0AS PER PROJECT REPORT9
Club House/Community Centre0AS PER PROJECT REPORT
10SHOPPING AREA0
As Per Project Report11RENEWABLE ENERGY SYSTEM
800000AS PER PROJECT REPORT12
School0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0
As Per Project Report14ANY OTHER
0AS PER PROJECT REPORT15
Rain Water Pipes434515AS PER PROJECT REPORT
16RAIN WATER HARVESTING700000
As Per Project Report5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.NA
(date)6. Date of approval of Building PlansNA
(date)7. New projects:i) Likely date of starting the construction work
01-10-2023ii) Likely date of completing the project30-09-2025
iii) Sizes of the plots to be offered in the projectSr. NoPlot Area(In Square Meter)
Number of plots in the project10
0Total0
iv. Type of apartments to be constructed in the project:TypeCarpet area(In Square Meter)
Number of apartmentsNumber of towersApartment/Shops/Other Buildings
100.70040
Apartment/Shops/Other Buildings88.26712
0Apartment/Shops/Other Buildings79.768
20Apartment/Shops/Other Buildings
101.34220
Apartment/Shops/Other Buildings101.92210
0Apartment/Shops/Other Buildings75.466
20Apartment/Shops/Other Buildings
65.92320
Apartment/Shops/Other Buildings31.4082
0Apartment/Shops/Other Buildings52.610
40Apartment/Shops/Other Buildings
52.911220
Apartment/Shops/Other Buildings52.2082
0Apartment/Shops/Other Buildings77.007
20Apartment/Shops/Other Buildings
25.24320
(vi) Quarterly schedule of development of whole/remaining part of the project:(c) Apartments/Shops/Other BuildingsExpenditure incurred till the date of application (In Lakhs)
ParticularsExpenditureApartments
0Shops0
Plots0Expenditure to be made in each quarter (In Lakhs)
ParticularsYear-2023Jan-Mar
Apr-JuneJuly-SepOct-Dec
Apartments0Shops
250Plots0
ParticularsYear-2024Jan-Mar
Apr-JuneJuly-SepOct-Dec
Apartments00
00Shops
250195210
260Plots0
000
ParticularsYear-2025Jan-Mar
Apr-JuneJuly-SepOct-Dec
Apartments00
0Shops360
354418Plots
000
(d) InfrastructureExpenditure incurred till the date of application (In Lakhs)Particulars
ExpenditureRoads & Pavements0
Water Supply System0Sewerage treatment & garbage disposal
0Electricity Supply System0
Storm Water Drainage0Parks and Playgrounds
0Clubhouse/community centres0
Shopping area0Other
0Expenditure to be made in each quarter (In Lakhs)Particulars
Year-2023Jan-MarApr-June
July-SepOct-DecRoads & Pavements
00Water Supply System
00Sewerage treatment & garbage disposal
00Electricity Supply System
00Storm Water Drainage
00Parks and Playgrounds
00Clubhouse/community centres
00Shopping area
00Other
00FOUNDATION AND CASTING OF BASEMENT ONE AND TWO
200EXCAVATION WORK50
ParticularsYear-2024Jan-Mar
Apr-JuneJuly-SepOct-Dec
Roads & Pavements00
00Water Supply System
028
8Sewerage treatment & garbage disposal0
000
Electricity Supply System03
22Storm Water Drainage
000
0Parks and Playgrounds0
000
Clubhouse/community centres00
00Shopping area
000
0Other0
000
Casting Of Ground Floor150BRICK WORK
404040
Plaster Work1030
Casting Of First Floor150CASTING OF SECOND FLOOR
150FINISHING WORK OF COMMON AREA AND STAIRCASE AND LIFTS30
Foundation And Casting Of Basement One And Two250Particulars
Year-2025Jan-MarApr-June
July-SepOct-DecRoads & Pavements
000
0Water Supply System8
770
Sewerage treatment & garbage disposal00
00Electricity Supply System
233
0Storm Water Drainage0
000
Parks and Playgrounds00
00Clubhouse/community centres
000
0Shopping area0
000
Other00
00FINISHING WORK OF COMMON AREA AND STAIRCASE AND LIFTS
60BRICK WORK40
5070PLASTER WORK
304230
Rain Water Harvesting System7FIRE FIGHTING SCHEME
2525OPEN AREA FINISHINGS
408085
External Finishing Work3080
90RENEWABLE SOLAR ENERGY SYSTEM8
Finishing Work Of Common Area And Staircase And Lift100FINISHING WORK OF COMMON AREAS AND STAIRCASE AND LIFTS
60CASTING OF THIRD FLOOR150
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.Signature of the Applicant / Authorised RepresentativeStamp _____________
Date _____________FORM REP-IPart - D
Accounts related information:1. Annex copy of the balance sheet of last 3 yearsYes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.Yes
3. Bank account to which the deposits received from apartment buyers will be creditedBank and Branch addressHDFC BANK, HARMONY TOWERS, GT ROAD, PANIPAT-132103, HARYANA
Bank Account number50200065851034IFSC code
HDFC0000171MICR code132240002
Branch code1714. Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)
MUKESH GULATI,H. No-464 Ward-4 Panchwati Colony near water tank, Samalkha Panipat, Haryana-132101 andMamta Gulati, H. No-464 Ward-4 Panchwati Colony near water tank, Samalkha Panipat, Haryana-1321015. Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)
Certificate AnnexedI hereby declare that the above information and particulars are based on record and are true to thebest of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised RepresentativeStamp _____________Date _____________
Form Rep-IPart - EDetails of the statutory approvals:
1. Annex copies of the following in Folder E:i. Lay out PlanYes
ii. Demarcation PlanYesiii. Zoning Plan
Yesiv. Building PlanYes
Site PlanYesFloor Plan
YesApartment PlansNo
Elevation SectionYesDetail of Permissible FAR
YesDetail of covered area achieved FARYes
2. Annex copies of the following in Folder E:I. ROADS AND PAVEMENT PLANNo
II. Electricity Supply PlanNoIII. WATER SUPPLY PLAN
NoIV. SEWERAGE AND GARBAGE DISPOSAL PLANNo
V. Strom Water DrainageNoVI. 10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITY
NoVII. STREET LIGHTING PLANNo
Viii. Parking PlanNo3. Statutory Approvals Status
Statutory ApprovalsStatutory Approvals StatusDate
I. Demarcation PlanALREADY BEEN OBTAINED27-12-2013
II. Zoning PlanALREADY BEEN OBTAINED27-12-2013
It is undertaken that the project shall be completed within the time schedule given in Part C and the same will not be delayed on account of non- receipt of any of the statutory approval. The liability for the non-receipt of any of the statutory approval shall be that of the promoter and in case of delay, compensation as per law may be given to the allottees.Signature _____________Seal _____________
Date _____________FORM REP-IPart - F
1. A copy of the draft allotment letter by which the apartment shall be allotted/ booked in favour of the apartment buyers.(Annex a copy in Folder F)Yes
2. A copy of the Draft Agreement which shall be made before seeking any deposit exceeding 10% of the cost of the apartment. (Based on the model agreement prescribed in the Rules)(Annex a copy in Folder F)Yes
3. Gist of the important provisions of the Draft Agreement(Annex a copy in Folder F)ENCLOSED
I hereby declare that the above information and particulars are based on record and are true to thebest of my knowledge and belief and nothing has been concealed.Signature of the Applicant / Authorised Representative
Stamp _____________Date _____________FORM REP-I
Part - GProjects launched by the promoter in last five years: (No Projects)I hereby declare that the above information and particulars are based on record and are true to the best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised RepresentativeStamp _____________Date _____________
Form Rep-IPart - HSPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:1FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
Na2WALL FINISHING DETAILS
Oil Bound Distemper (Obd)3KITCHEN DETAILS
Water Supply4BATHROOM FITTINGS
Water And Sewerage Supply5WOOD WORK ETC
Na6DOORS AND WINDOS FRAMES
Na7GLASS WORK
Na8ELECTRIC FITTINGS
Connectivity Upto Distribution Board (Db)9CONDUCTING AND WIRING DETAILS
Na10CUPBOARD DETAILS
Na11WATER STORAGE
Overheads Tank12LIFT DETAILS
As Per Approved Building Plan13EXTERNAL GLAZINGS
As Per Architect13.1WINDOWS/GLAZINGS
As Per Architect14DOORS
Na14.1MAIN DOORS
Glass Door14.2INTERNAL DOORS
Na15AIR CONDITIONING
Na16ELECTRICAL FITTINGS
Na17CNG PIPE LINE
Na18PROVISION OF WIFI AND BROADBAND FACILITY
Na19EXTERNAL FINISHING/COLOUR SCHEME
As Per Architect20INTERNAL FINISHING
Finished Common Corridor,Lift,Lobbies,Staircase,Common Toilets.SPECIFICATION UNIT WISE1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1FLOORNA
1 . 2WALLSNA
1 . 3CEILINGNA
2 . Master Bedroom/Dressroom2 . 1FLOOR
Na2 . 2WALLS
Na2 . 3CEILING
Na2 . 4MODULAR WARDROBES
Na3 . MASTER TOILET3 . 1
FloorNA3 . 2
WallsNA3 . 3
CeilingNA3 . 4
CountersNA3 . 5
Sanitary Ware/Cp FittingsNA3 . 6
Fitting/FixturesNA4 . BED ROOMS
4 . 1FLOORNA
4 . 2WALLSNA
4 . 3CEILINGNA
4 . 4WARDROBESNA
5 . Toilet5 . 1FLOOR
Na5 . 2WALLS
Na5 . 3CEILING
Na5 . 4COUNTERS
Na5 . 5SANITARY WARE/CP FITTINGS
Na5 . 6FIXTURES
Na6 . KITCHEN6 . 1
FloorNA6 . 2
WallsNA6 . 3
CeilingNA6 . 4
CountersNA6 . 5
FixturesNA6 . 6
Kitchen AppliancesNA7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1FLOORNA
7 . 2WALLS & CEILINGNA
7 . 3TOILETNA
7 . 4BALCONYNA
8 . Sit-Outs8 . 1FLOOR
Na8 . 2WALLS & CEILING
Na8 . 3RAILINGS
Na8 . 4FIXTURES
NaI hereby declare that the above information and particulars are based on record and are true to thebest of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised RepresentativeStamp _____________Date _____________
List of Uploaded DocumentsSr. No.Document Description
Date of Document UploadView Document1
Demarcation Plan19-08-2023View Document
2IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN19-08-2023
View Document3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN
01-09-2023View Document4
Declaration Supported By Affidavit Duly Signed By The Promoter To Be Enclosed.21-08-2023View Document
5BALANCE SHEET OF LAST YEARS01-09-2023
View Document6A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS
29-08-2023View Document7
Zoning Plan19-08-2023View Document
8NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT21-08-2023
View Document9DRAFT ALLOTMENT LETTER
30-08-2023View Document10
Copy Of License Along With Schedule Of Land01-09-2023View Document
11CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT29-08-2023
View Document12MOA AND AOA
30-08-2023View Document13
Draft Agreement For Sale01-09-2023View Document
14CASH FLOW STATEMENT OF THE PROPOSED PROJECT01-09-2023
View Document15SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN
01-09-2023View Document16
Cin And Pan30-08-2023View Document
17PROJECT REPORT30-08-2023
View Document18GIST OF PROVISIONS OF DRAFT AGREEMENT
30-08-2023View Document19
Documents Relating To The Entry Of License And Collaboration Agreement In The Revenue Record01-09-2023View Document
I hereby declare that the above information and particulars are based on record and are true to thebest of my knowledge and belief and nothing has been concealed.Signature of the Applicant / Authorised Representative
Stamp _____________Date _____________Documents Uploaded After Registration
Sr. No.Document DescriptionDate of Document Upload
View Document1RC APPROVED
11-09-2025View Document2
Corrigendum Uploaded30-03-2026View Document
3Extension Approved07-08-2026
View DocumentI hereby declare that the above information and particulars are based on record and are true to thebest of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised RepresentativeStamp _____________Date _____________

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 8,198.9 CrAs Per Project Report
Water Supply System₹ 13,773.13 CrAs Per Project Report
Storm Water Drainage₹ 3,957.99 CrAs Per Project Report
Electricity Supply System₹ 151,795.29 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 6,572.75 CrAs Per Project Report
Street Lighting₹ 3,200.29 CrAs Per Project Report
Security And Fire Fighting₹ 50,000 CrAs Per Project Report
Renewable Energy System₹ 8,000 CrAs Per Project Report
Rain Water Pipes₹ 4,345.15 CrAs Per Project Report
Rain Water Harvesting₹ 7,000 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
Demarcation PlanAlready Been Obtained27 Dec 2013
Zoning PlanAlready Been Obtained27 Dec 2013

Specifications (as filed)

Wall Finishing DetailsOil Bound Distemper (Obd)
Kitchen DetailsWater Supply
Bathroom FittingsWater And Sewerage Supply
Electric FittingsConnectivity Upto Distribution Board (Db)
Water StorageOverheads Tank
Lift DetailsAs Per Approved Building Plan
External GlazingsAs Per Architect
Windows/GlazingsAs Per Architect
Main DoorsGlass Door
External Finishing/Colour SchemeAs Per Architect
Internal FinishingFinished Common Corridor,Lift,Lobbies,Staircase,Common Toilets.

Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Ceremony Enthia?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.