- Land area
- 10.81 acres
- Estimated cost
- ₹ 419.85 Cr
RERA registration
| Registration certificate | GGM/370/102/2019/64, dated 7 Nov 2019 |
|---|---|
| Registration valid till | 21 Jul 2021 |
| Project ID | RERA-GRG-240-2019 |
| Authority | HRERA Gurugram |
| Project type (as filed) | Ongoing |
| Project name | Canary Greens |
| Promoter | Today Homes & Infrastructure Pvt Ltd |
| Promoter’s registered office | Ugf-08-09, Pragati Tower, Rajendra Place, New Delhi-110008 |
| CIN | U45201DL1996PTC081609 |
| Site address | Village- Behrampur, Sector-73, Gurugram. Haryana |
| Sector | Sector 73 |
| Tehsil / District | Gurgaon / Gurugram |
| Layout plan approved | 13 May 2011 |
| Building plans approved | 13 May 2011 |
| Application submitted | 19 Apr 2019 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
-
Hearing
Examination By Authority
Proceedings
Show cause hearing notice was issued to the promoter along with the deficiencies which are still pending and not fulfilled by the promoter.
- Notice sent to the promoter dispatched
-
Hearing
Objection Compliance Done
Proceedings
Next date of hearing 27-08-2019
-
Hearing
Objection
Proceedings
Next date of hearing 2-9-2019
-
Hearing
Adjournment
Proceedings
Next date of hearing 18.09.2019
-
Hearing
Objection
Proceedings
Adjourned for dated 24.09.2019
-
Hearing
Adjournment
Proceedings
hearing for dated 09.10.2019
-
Hearing
Adjournment
Proceedings
Adjourned for dated 14.10.2019
-
Hearing
Approved And Ready For Certificate Issuing Process
Proceedings
Registration certificate to be prepared by the authority
- Registration granted GGM/370/102/2019/64
- Certificate uploaded RC Approved
- Registration valid till
Land, licence & cost
| Land area of the project | 10.81 acres |
|---|---|
| Total licensed area | 21.637 acres |
| Licence | 03 of 2009 |
| FAR permissible / proposed | 175 / 171 |
| Estimated project cost | ₹ 419.85 Cr |
| Cost of land | ₹ 120 Cr |
| Cost of construction | ₹ 209.3 Cr |
| Infrastructure and other structures | ₹ 16.96 Cr |
| EDC, taxes, levies and other costs | ₹ 73.59 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 4,991 | 11.4% |
| Construction Of Roads | 8,670 | 19.8% |
| Pavements | 2,535 | 5.8% |
| Parks And Playgrounds | 6,653.54 | 15.2% |
| Vehicle Parkings | 2,906 | 6.6% |
| Electricity Sub-Station | 921.72 | 2.1% |
| Club House | 496 | 1.1% |
| Sewage And Solid Waste Treatment Facility | 300 | 0.7% |
| Any Other | 11,261.48 | 25.7% |
| Shopping | 198 | 0.5% |
| Nursery | 800.29 | 1.8% |
| Primary | 4,046.48 | 9.2% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HUDA | No |
| Water Supply | HUDA | Yes |
| Electricity | DHVBN | Yes |
| Sewage Disposal | HUDA | No |
| Storm Water Drainage | HUDA | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 2.75 Cr | Yet To Be Prepared |
| Water Supply System | ₹ 34 lakh | Yet To Be Prepared |
| Storm Water Drainage | ₹ 56 lakh | Yet To Be Prepared |
| Electricity Supply System | ₹ 4 Cr | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 31.7 lakh | Yet To Be Prepared |
| Street Lighting | ₹ 12 lakh | Yet To Be Prepared |
| Security And Fire Fighting | ₹ 2.46 Cr | Yet To Be Prepared |
| Playgrounds And Parks | ₹ 32 lakh | Yet To Be Prepared |
| Club House/Community Centre | ₹ 1.75 Cr | Yet To Be Prepared |
| Shopping Area | ₹ 30 lakh | Yet To Be Prepared |
| Renewable Energy System | ₹ 50 lakh | Yet To Be Prepared |
| Any Other | ₹ 3.54 Cr | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Mining Permission Letter No. 1073 | Already Been Obtained | 17 Nov 2011 |
| Consent To Establish | Hspcb/Consent/2821213GUSOCTE258155 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Marble Flooring |
|---|---|
| Wall Finishing Details | Plastic Paint |
| Kitchen Details | Ceramic Tile/Obd |
| Bathroom Fittings | Jaquar Fittings |
| Doors And Windos Frames | Aluminium Door And Windows |
| Glass Work | Door & Windows |
| Electric Fittings | Anchor |
| Conducting And Wiring Details | Polycab |
| Water Storage | Anchor Polycab- Ugt/Oht |
| Lift Details | Not Required |
| External Glazings | Provided |
| Windows/Glazings | Provided |
| Doors | Aluminium Door |
| Main Doors | Aluminium Door |
| Internal Doors | Flush |
| Air Conditioning | Split |
| Electrical Fittings | Anchor |
| External Finishing/Colour Scheme | Texture Finish |
| Internal Finishing | Plastic Paint |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.