Brahma City Phase-V
by Brahma City Pvt Ltd · Sector 60, 61,62, 63 Gurugram
- RERA registration
- GGM/640/372/2022/115
- Registered on
- 5 Dec 2022
- Valid till
- 19 Aug 2026
- Project ID
- RERA-GRG-867-2021
- Land area
- 53.584 acres
- Estimated cost
- ₹ 407.52 Cr
RERA registration
| Registration certificate | GGM/640/372/2022/115, dated 5 Dec 2022 |
|---|---|
| Registration valid till | 19 Aug 2026 |
| Project ID | RERA-GRG-867-2021 |
| Authority | HRERA Gurugram |
| Project type (as filed) | Ongoing |
| Project name | Brahma City Phase-V |
| Promoter | Brahma City Pvt Ltd |
| Promoter’s registered office | Epitome 10TH Floor Building No 5 A, DLF Cybercity, Phase 3, Gurugram |
| CIN | U45400DL2008PTC175331 |
| Site address | Sector 60, 61,62, 63 Gurugram |
| Sector | Sector 60 |
| Tehsil / District | Wazirabad St / Gurugram |
| Layout plan approved | 2 Nov 2016 |
| Application submitted | 24 May 2021 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter 1st deficiency notice
-
Hearing
Examination By Authority View order
Proceedings
Hearing is fixed for 08.06.2021.
-
Hearing
Adjournment View order
Proceedings
Ms. Jyoti Yadav, Coordinator Planning Branch briefed the facts of the project. Sh. Mukund Jha is present on behalf of the promoter. The AR submitted that they have not yet received the copy of notice dated 21.05.2021 and hence as a matter of additional precaution, copies of the notice dated 21.05.2021 were handed over. The promoter was asked to remove the deficiencies and submit the deficit document and also apply for registration of the balance area of 55.63 acres unregistered. The matter is to come up on 06.07.2021 at 3.00 PM. Dr. K.K. Khandelwal (Chairman) Samir Kumar (Member) Vijay Kumar Goyal (Member)
-
Hearing
Objection View order
Proceedings
Matter adjourned for 07.07.2021
-
Hearing
Adjournment View order
Proceedings
Ms. Jyoti Yadav, Coordinator Planning Branch briefed about the project. No one is present on behalf of the promoter. An e-mail request has been received for adjournment in the matter due to some unavoidable urgent prior commitments. Matter to come up on 27.07.2021. The promoter is advised to rectify the deficiencies and submit deficit documents.
-
Hearing
Objection View order
Proceedings
Proceedings dated: 27.07.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed the facts about the project. Sh. Venkat Rao, Advocate and Sh. Nikhil Srivastava (AVP Legal) are present on behalf of the promoter. The project could not be discussed in detail as the basic premises to register is validity of the license. As informed by the promoter they have applied for renewal and is pending with DTCP. When specifically asked whether EDC dues have been cleared the AR and LR informed that the concerned person is not available today and the position regarding non-renewal of the license will be explained in the next meeting where the project details will be discussed. Further the AR was asked to submit the bank account details wherein 70% amount received in lieu of sale of plots is to be deposited for development works along with details of total sold/unsold plots. The matter to come up on 02.08.2021.Dr. K.K. Khandelwal (Chairman) Samir Kumar (Member) Vijay Kumar Goyal (Member)
-
Hearing
Objection View order
Proceedings
Proceedings dated: 02.08.2021 Sh. Atul Vaid (AR), Sh. Nikhil Srivastava (AR) and Sh. Venkat Rao (Advocate) are present on behalf of the promoter. 1. There is a variation in the area to be registered for which a detailed explanation was given by the LR along with a data sheet. The LR was requested to give supporting documents along with parts of the project already registered and remaining part of the project to be registered. 2. The promoter was asked to fill up online DPI within 10 days. In case prerequisites are not met with the Authority shall be constrained to issue a press advertisement causing public not to indulge in the sale purchase of this project. 3. The promoter is asked to submit an affidavit regarding details of bank account where the amount received after selling 87 plots to M/s Adani Brahma Synergy Pvt. Ltd. has been kept. 4. The promoter is also asked to give an affidavit that withdrawals, if any, have been as per provisions of the Act. 5. The promoter is directed not to make any further sale in the part of the project under registration vide Temp ID RERA GRG 867/2021of any plot or flat till completion of the registration process of unregistered part of the project. 6. Further details of EDC dues to be paid to the T&CP; Department be submitted and all dues till date be cleared and details of payments of EDC further to be made to the department be submitted. 7. Site inspection be done by the Engineering Executive regarding status of development works in this part of the project and also for other parts which are registered separately duly marked on a copy of lay out plan. The matter to come up on 16.08.2021. Dr. K.K. Khandelwal (Chairman) Samir Kumar (Member) Vijay Kumar Goyal (Member)
-
Hearing
Objection View order
Proceedings
The matter adjourned for dated 23.08.2021
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 23.08.2021 Sh. Atul Vaid (AR) and Sh. Nikhil Srivastava (AR) are present on the behalf of the promoter. The promoter has made submissions that the promoter has applied for the registration and the file is under process. In the last hearing dated 02.08.2021 the promoter was directed to submit an affidavit regarding details of the bank account where the amount received after selling of 87 plots to M/s Adani Brahma Synergy Pvt. Ltd. has kept and details of the EDC dues to be paid to DTCP, Haryana be submitted whereas the promoter has not submitted the same in the authority. The promoter is directed to submit the above information till the next date of hearing meanwhile site inspection be done by the engineering executives of the authority regarding status of the development works in the project and place the report on the record in the next date of hearing. Hence the matter is adjourned to 13.09.2021 at 02:00 PM for personal hearing. Dr. K.K. Khandelwal (Chairman) Samir Kumar (Member) Vijay Kumar Goyal (Member)
-
Hearing
Objection View order
Proceedings
Proceedings dated: 13.09.2021 Sh. Venkat Rao (Advocate), Sh. Atul Vaid (AR), Ms. Priyanshi Madan (AR) and Sh. Nikhil Srivastava (AR) are present on behalf of the promoter. The promoter has made submissions that the promoter has applied for the registration and the file is under process. Further the promoter is directed to submit the plan demarcating their area till the next date of hearing. Hence the matter is adjourned to 18.10.2021 at 02:00 PM for personal hearing.
-
Hearing
Objection View order
Proceedings
Proceedings dated: 18.10.2021 Sh. Venkat Rao (Advocate), Sh. Atul Vaid (AR), Ms. Priyanshi Madan (AR) and Sh. Nikhil Srivastava (AR) are present on behalf of the promoter. The promoter has filed application for registration which is under examination. After decision is taken about registration of the project and all necessary details are filed in the registry, the issue regarding penal proceedings for non-registration of the project will be finalized. The matter to come up after fifteen days. The matter is adjourned to 02.11.2021.
-
Hearing
Objection View order
Proceedings
The matter will be heard 09.11.2021.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 09.11.2021 Ms. Neeraj Gautam, Architectural Executive briefed the facts about the project. Sh. Venket Rao (Advocate), Sh. Atul Vaid (AR), Ms. Priyanshi Madan (AR) and Sh. Nikhil Srivastava (AR) are present on behalf of the promoter. The details submitted by the promoter in online DPI are not matching with the details of license. The case is to be examined. Matter to come up on 23.11.2021.
-
Hearing
Objection View order
Proceedings
The authority decided to adjourn the matter. Next date of hearing will be 20.12.2021.
-
Hearing
Objection View order
Proceedings
Proceedings dated: 20.12.2021 Sh. Venkat Rao (Advocate), Sh. Atul Vaid (AR), Ms. Priyanshi Madan (AR) and Sh. Nikhil Srivastava (AR) are present on behalf of the promoter. This matter is linked with the penal proceeding for non-registration of the project. The promoter has sold plots of the unregistered area to M/s Adani Brahma Synergy Pvt Ltd. Therefore, two show cause notices vide no. RERA-GRG-2273-2021 and RERA-GRG-2273-2021/1 dated 21.05.2021 were issued to the promoter for violation of provisions of section 3 of the Real Estate (Regulation and Development) Act, 2016. Out of the total licensed area admeasuring 141.668 acres, 55.64 acres is unregistered, but the promoter has applied for registration of only 53.61 acres. The remaining unregistered area which still needs to be applied for registration is 2.03 acres which consists of electric substation. The promoter is directed to apply for the registration of 55.64 acres and submit the information online for the same along with details of sold and unsold inventory. Details of the bank account of Brahma City Pvt. Ltd. where the amount of consideration was transferred by ABSPL. The list of bank account of M/s ABSPL shall also be submitted on the next date of hearing. Details of plots overall purchased from M/s Brahma City Pvt. Ltd. and details of the plots sold out of these plots shall also be submitted giving details of registration of the project where the plot is located. Matter to come up on 24.12.2021.
-
Hearing
Objection View order
Proceedings
Matter adjourned for 14.03.2022.
-
Hearing
Objection View order
Proceedings
Sh. Gulshan Kumar (Sr. Officer Liaison) and Ms. Priyanshi Kapoor (Company Secretary) are present on behalf of the promoter. The matter is adjourned for 15.03.2022.
-
Hearing
Adjournment
Proceedings
The matter will be heard dated 10.10.2022.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned for 12.10.2022.
-
Hearing
Adjournment View order
Proceedings
The matter was considered and it was decided to adjourned the same for 14.11.2022. Matter to come up on 14.11.2022.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned for 15.11.2022.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 15.11.2022 Ms. Deepika, Planning Executive briefed about the facts of the project. None is present on behalf of the promoter. The matter to come up on 21.11.2022. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Vijay Kumar Goyal) Member, HARERA, Gurugram
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Approved a proposed
- Registration granted GGM/640/372/2022/115
- Registration valid till
Land, licence & cost
| Land area of the project | 53.584 acres |
|---|---|
| Total licensed area | 141.669 acres |
| Licence | 64 of 2010 |
| FAR permissible / proposed | 0 / 0 |
| Estimated project cost | ₹ 407.52 Cr |
| Cost of land | ₹ 209.17 Cr |
| Infrastructure and other structures | ₹ 50.91 Cr |
| EDC, taxes, levies and other costs | ₹ 147.45 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 17.5333 | 32.7% |
| Construction Of Roads | 10.4252 | 19.5% |
| Parks And Playgrounds | 6.3581 | 11.9% |
| Any Other | 19.2674 | 36% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | ALREADY CONNECTED | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 16.16 Cr | Yet To Be Prepared |
| Water Supply System | ₹ 2.59 Cr | Yet To Be Prepared |
| Storm Water Drainage | ₹ 1.01 Cr | Yet To Be Prepared |
| Electricity Supply System | ₹ 1.46 Cr | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 1.13 Cr | Yet To Be Prepared |
| Street Lighting | ₹ 1.37 Cr | Yet To Be Prepared |
| Playgrounds And Parks | ₹ 6.42 Cr | Yet To Be Prepared |
| Any Other | ₹ 20.77 Cr | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Occupation Certificate | Yet To File For Approval |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.