Site address
Village- Kheri Kalan, Sector-84, Faridabad
Sector
Sector 84
Tehsil / District
Faridabad / Faridabad
Layout plan approved
30 Jul 2019
Construction start (as filed)
1 Aug 2019
Completion (as filed)
29 Jul 2024
Application submitted
12 Aug 2019
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyListed for hearing.
Next hearingNot Required
Application submitted online
Application received by HRERA Panchkula
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
REGISTRATION CERTIFICATE ISSUED
Registration valid till
Land, licence & cost
Land area of the project
11.184 acres
Total licensed area
11.65 acres
Licence
82 of 2019
FAR permissible / proposed
1 / 1
Estimated project cost
₹ 58.32 Cr
Cost of land
₹ 19.37 Cr
Infrastructure and other structures
₹ 16.16 Cr
EDC, taxes, levies and other costs
₹ 22.79 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
6.46
57.8%
Construction Of Roads
1.611
14.4%
Pavements
0.988
8.8%
Parks And Playgrounds
0.874
7.8%
Electricity Sub-Station
0.03
0.3%
Sewage And Solid Waste Treatment Facility
0.025
0.2%
Area To Be Left For Transferring To The Government For Community Services
1.165
10.4%
Any Other
0.032
0.3%
Plots 234 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
91.00
109
980
7
98.90
118
1,065
38
98.90
118
1,065
41
98.90
118
1,065
21
112.60
135
1,212
4
113.20
135
1,218
6
121.80
146
1,311
59
125.10
150
1,347
17
125.10
150
1,347
36
126.20
151
1,358
1
133.00
159
1,432
2
138.60
166
1,492
2
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
No
Electricity
DHBVN
No
Sewage Disposal
HSVP
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 3.6 Cr
Yet To Be Prepared
Water Supply System
₹ 2.25 Cr
Yet To Be Prepared
Storm Water Drainage
₹ 88 lakh
Yet To Be Prepared
Electricity Supply System
₹ 2.74 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 2.35 Cr
Yet To Be Prepared
Street Lighting
₹ 35 lakh
Yet To Be Prepared
Security And Fire Fighting
₹ 2 lakh
Yet To Be Prepared
Playgrounds And Parks
₹ 1.73 Cr
Yet To Be Prepared
Renewable Energy System
₹ 14 lakh
Yet To Be Prepared
Any Other
₹ 2.08 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
License No 82 Of 2019
Already Been Obtained
30 Jul 2019
Layout Approval
Already Been Obtained
30 Jul 2019
Specifications (as filed)
Flooring Details Of Various Parts Of House
Not Applicable
Wall Finishing Details
Not Applicable
Kitchen Details
Not Applicable
Bathroom Fittings
Not Applicable
Wood Work Etc
Not Applicable
Doors And Windos Frames
Not Applicable
Glass Work
Not Applicable
Electric Fittings
Not Applicable
Conducting And Wiring Details
Not Applicable
Cupboard Details
Not Applicable
Water Storage
Not Applicable
Lift Details
Not Applicable
External Glazings
Not Applicable
Windows/Glazings
Not Applicable
Doors
Not Applicable
Main Doors
Not Applicable
Internal Doors
Not Applicable
Air Conditioning
Not Applicable
Electrical Fittings
Not Applicable
Cng Pipe Line
Not Applicable
Provision Of Wifi And Broadband Facility
Not Applicable
External Finishing/Colour Scheme
Not Applicable
Internal Finishing
Not Applicable
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about BPTP Nest 84B?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.