Bmg Elegant City (Additional)
by B. M. Gupta Developers Pvt. Ltd. · Sector-26, Garhi Bolni Road, Rewari-123401, Haryana
- RERA registration
- HRERA-PKL-RWR-551-2024
- Valid till
- 25 Jun 2028
- Project ID
- RERA-PKL-1309-2023
- Land area
- 4.812 acres
- Plots
- 44
- Completion (as filed)
- 25 Jun 2028
- Estimated cost
- ₹ 35.22 Cr
RERA registration
| Registration certificate | HRERA-PKL-RWR-551-2024 |
|---|---|
| Registration valid till | 25 Jun 2028 |
| Project ID | RERA-PKL-1309-2023 |
| Authority | HRERA Panchkula |
| Project type (as filed) | New |
| Project name | Bmg Elegant City (Additional) |
| Promoter | B. M. Gupta Developers Pvt. Ltd. |
| Promoter’s registered office | 5TH Floor, Bmg City Centre, Elegant City, Sector-26, Garhi Bolni Road, Rewari, Haryana-123401 |
| CIN | U45400HR2008PTC103627 |
| Site address | Sector-26, Garhi Bolni Road, Rewari-123401, Haryana |
| Sector | Sector 26 |
| Tehsil / District | Rewari / Rewari |
| Construction start (as filed) | 26 Jun 2023 |
| Completion (as filed) | 25 Jun 2028 |
| Application submitted | 31 Jul 2023 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Panchkula
-
Hearing
Examination By Authority View order
Proceedings
Adjourned to 25.09.2023
-
Hearing
Adjournment View order
Proceedings
Adjourned to 16.10.2023
-
Hearing
Adjournment View order
Proceedings
Adjourned to 18.12.2023
-
Hearing
Adjournment View order
Proceedings
Adjourned to 12.02.2024
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS.
- Registration valid till
Land, licence & cost
| Land area of the project | 4.812 acres |
|---|---|
| Total licensed area | 5.963 acres |
| Licence | 135 of 2023 dated 26-06-2023 |
| Estimated project cost | ₹ 35.22 Cr |
| Cost of land | ₹ 21.1 Cr |
| Infrastructure and other structures | ₹ 4.19 Cr |
| EDC, taxes, levies and other costs | ₹ 9.94 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 2.6638 | 55.4% |
| Construction Of Roads | 1.235 | 25.7% |
| Parks And Playgrounds | 0.6557 | 13.6% |
| Ud | 0.058 | 1.2% |
| Nursery | 0.2 | 4.2% |
Plots 44 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 50.00 | 60 | 538 | 10 |
| 224.40 | 268 | 2,415 | 11 |
| 313.01 | 374 | 3,369 | 16 |
| 467.25 | 559 | 5,029 | 6 |
| 809.41 | 968 | 8,712 | 1 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HSVP | No |
| Water Supply | HSVP | No |
| Electricity | DHBVN | No |
| Sewage Disposal | HSVP | No |
| Storm Water Drainage | HSVP | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 55,000 Cr | As Per Project Report |
| Water Supply System | ₹ 74,531.25 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 25,340.63 Cr | As Per Project Report |
| Electricity Supply System | ₹ 87,648.75 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 65,587.5 Cr | As Per Project Report |
| Street Lighting | ₹ 11,925 Cr | As Per Project Report |
| Security And Fire Fighting | ₹ 1,788.75 Cr | As Per Project Report |
| Playgrounds And Parks | ₹ 8,943.75 Cr | As Per Project Report |
| Any Other | ₹ 53,662.5 Cr | As Per Project Report |
| Toe Wall | ₹ 32,500 Cr | As Per Project Report |
| Signages | ₹ 1,788.75 Cr | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License No 135 Of 2023 | Already Been Obtained | 26 Jun 2023 |
| Lay Out Plan Dwg No Dtcp 9361 | Already Been Obtained | 30 Jun 2023 |
| Demarcation Plan | Applied For But Yet To Receive | 5 Jul 2023 |
| Zoning Plan | Yet To File For Approval | |
| Service Plan Estimats | Yet To File For Approval |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Not Applicable |
|---|---|
| Wall Finishing Details | Not Applicable |
| Kitchen Details | Not Applicable |
| Bathroom Fittings | Not Applicable |
| Wood Work Etc | Not Applicable |
| Doors And Windos Frames | Not Applicable |
| Glass Work | Not Applicable |
| Electric Fittings | Not Applicable |
| Conducting And Wiring Details | Not Applicable |
| Cupboard Details | Not Applicable |
| Water Storage | Not Applicable |
| Lift Details | Not Applicable |
| External Glazings | Not Applicable |
| Windows/Glazings | Not Applicable |
| Doors | Not Applicable |
| Main Doors | Not Applicable |
| Internal Doors | Not Applicable |
| Air Conditioning | Not Applicable |
| Electrical Fittings | Not Applicable |
| Cng Pipe Line | Not Applicable |
| Provision Of Wifi And Broadband Facility | Not Applicable |
| External Finishing/Colour Scheme | Not Applicable |
| Internal Finishing | Not Applicable |
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.