Bestceh 92 Market Place
by Bestech India Pvt Ltd · Sector 92, Village Wazirpur, Gurugram
- RERA registration
- GGM/380/112/2019/74
- Registered on
- 9 Dec 2019
- Valid till
- 31 Mar 2025
- Project ID
- RERA-GRG-304-2019
- Land area
- 5.713 acres
- Apartments
- 432 in 2 towers
- Plots
- 432
- Completion (as filed)
- 31 Mar 2025
- Estimated cost
- ₹ 176.94 Cr
RERA registration
| Registration certificate | GGM/380/112/2019/74, dated 9 Dec 2019 |
|---|---|
| Registration valid till | 31 Mar 2025 |
| Project ID | RERA-GRG-304-2019 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Bestceh 92 Market Place |
| Promoter | Bestech India Pvt Ltd |
| Promoter’s registered office | Bestech House, Plot No 51, Sector 44, Gurugram - 122002 |
| CIN | U99999DL2001PTC110996 |
| Site address | Sector 92, Village Wazirpur, Gurugram |
| Sector | Sector 92 |
| Tehsil / District | Harsaru St / Gurugram |
| Layout plan approved | 4 Jul 2019 |
| Building plans approved | 4 Jul 2019 |
| Construction start (as filed) | 1 Oct 2019 |
| Completion (as filed) | 31 Mar 2025 |
| Application submitted | 16 Sep 2019 |
Authority, hearings & orders
- Application submitted online
-
Hearing
Examination By Authority
Proceedings
Personal hearing to be held
-
Hearing
Adjournment
Proceedings
Personal hearing to be held on 22.10.2019. (Sejal)
-
Hearing
Objection
Proceedings
2nd deficiency notice sent on 22.10.2019. Personal hearing to be held on 29.10.2019. (Sejal)
-
Hearing
Objection
Proceedings
matter will be heard on 25.11.2019
-
Hearing
Objection
Proceedings
Deficiencies which were conveyed earlier have not been completed and the promoter is asked to do the needful within two day.
-
Hearing
Objection
Proceedings
Hearing adjourned on 09.12.2019
-
Hearing
Adjournment
Proceedings
Hearing adjourned on 10.12.2019
- Registration granted GGM/380/112/2019/74
- Hearing Approved And Ready For Certificate Issuing Process View order
- Certificate uploaded RC Approved and Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 5.713 acres |
|---|---|
| Total licensed area | 5.713 acres |
| Licence | Licence no 31 of 2011 dated 08.04.2011 |
| FAR permissible / proposed | 1.78 / 1.78 |
| Estimated project cost | ₹ 176.94 Cr |
| Cost of land | ₹ 0 Cr |
| Cost of construction | ₹ 77.42 Cr |
| Infrastructure and other structures | ₹ 30.86 Cr |
| EDC, taxes, levies and other costs | ₹ 68.65 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 17,015.4 | 73.6% |
| Construction Of Roads | 6,102 | 26.4% |
Apartments 432 units · 2 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 31,462.78 | - | 432 |
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
Plots 432 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 6,922.79 | 8,280 | 74,516 | 111 |
| 24,540.63 | 29,350 | 264,153 | 321 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HSVP | No |
| Water Supply | HSVP | No |
| Electricity | DHBVN | Yes |
| Sewage Disposal | HSPCB | No |
| Storm Water Drainage | HSVP | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 105,036 Cr | Yet To Be Prepared |
| Water Supply System | ₹ 698,000 Cr | Yet To Be Prepared |
| Storm Water Drainage | ₹ 20,000 Cr | Yet To Be Prepared |
| Electricity Supply System | ₹ 1,533,803 Cr | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 78,990 Cr | Yet To Be Prepared |
| Street Lighting | ₹ 15,000 Cr | Yet To Be Prepared |
| Security And Fire Fighting | ₹ 535,000 Cr | Yet To Be Prepared |
| Renewable Energy System | ₹ 100,000 Cr | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Airport Authority Of India Noc | Already Been Obtained | 1 Mar 2019 |
| Licence No 31 Of 2011 | Already Been Obtained | 10 Jun 2019 |
| Licence No 42 Of 2011 | Already Been Obtained | 10 Jun 2019 |
| License No 57 Of 2012 | Already Been Obtained | 25 Jan 2019 |
| Environment Clearance | Already Been Obtained | 12 Dec 2013 |
| Consent To Establish | Already Been Obtained | 11 Feb 2014 |
| Aravalli Clearance | Already Been Obtained | 18 Sep 2013 |
| Forest Clearance | Already Been Obtained | 3 Sep 2013 |
| Wild Life Clearance | Already Been Obtained | 16 Aug 2013 |
| Building Plan Approval | Already Been Obtained | 4 Jul 2019 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Granite, Marble, Vitrified Tiles In Common Areas Only. Tenant Areas Shall Be Bare Finish |
|---|---|
| Wall Finishing Details | Plastered And Painted In Common Areas And Bare Finish In Tenant Areas |
| Bathroom Fittings | Standard Bath Room Fitting In Common Area Toilets |
| Doors And Windos Frames | Aluminium/Wood |
| Electric Fittings | Electrical And Telecom Cable With Isolator Shall Be Arranged By |
| Conducting And Wiring Details | No Electrical Conduit/Wiring Shall Be Provided In Slab |
| Water Storage | Ug &Oh; Water Storage Tanks As Per Norms |
| Lift Details | High Speed Elevators |
| External Glazings | Toughened Glass In Facade |
| Air Conditioning | Provision For Ac |
| Electrical Fittings | Electrical And Telecom Cable With Isolator Shall Be Arranged By The Respective Owner User |
| External Finishing/Colour Scheme | Long Lasting Exterior Paint |
| Internal Finishing | Plastered And Painted With Pleasing Shades Of Obd In Common |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.