Registration period overHRERA GurugramOC / CC on record

Bella Vista - Central Park Resorts

by Sweta Estates Pvt. Ltd. · Sector 48, Sohna Road, Near Subhash Chowk, Gurgaon

RERA registration
GGM/379/111/2019/73
Registered on
23 Dec 2019
Valid till
28 Feb 2026
Project ID
RERA-GRG-330-2019
Land area
13.2 acres
Apartments
511 in 2 towers
Completion (as filed)
31 Aug 2024
Estimated cost
₹ 3,886.64 Cr

RERA registration

Registration certificateGGM/379/111/2019/73, dated 23 Dec 2019
Registration valid till28 Feb 2026
Project IDRERA-GRG-330-2019
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameBella Vista - Central Park Resorts
PromoterSweta Estates Pvt. Ltd.
Promoter’s registered officeAsset 5B, Hospitality District, Delhi Aerocity, Igi Airport, New Delhi- 110037
CINU74899DL1991PTC044871
Site addressSector 48, Sohna Road, Near Subhash Chowk, Gurgaon
SectorSector 48
Tehsil / DistrictBadshahpur St / Gurugram
Layout plan approved24 Oct 2019
Building plans approved24 Oct 2019
Construction start (as filed)1 Jul 2019
Completion (as filed)31 Aug 2024
Application submitted1 Nov 2019

Authority, hearings & orders

Current statusExtension Certificate Uploaded
Initial scrutinyDeficiencies conveyed. matter will be heard on 02.12.2019
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter dispatched
  1. Hearing Examination By Authority
    Proceedings

    Hearing adjourned on 09.12.2019

  2. Hearing Adjournment
    Proceedings

    Hearing adjourned on 10.12.2019

  3. Hearing Adjournment View order
    Proceedings

    Sh. Rakesh Malhotra, General Manager, M/s Sweta Estates Pvt Ltd for pursuing application for registration of group housing project “Bella Vista-Central Park Resorts” appeared before the authority yesterday (09.12.2019) and made a request to give a week’s time to remove deficiencies as conveyed vide 3rd deficiency notice sent on 6.12.2019. Accordingly, the matter is adjourned to 16.12.2019.

  1. Hearing Adjournment
    Proceedings

    matter adjourned to 18.12.2019

  2. Hearing Adjournment
    Proceedings

    matter adjourned to 24.12.2019

  3. Registration granted GGM/379/111/2019/73
  1. Hearing Approved And Ready For Certificate Issuing Process
    Proceedings

    Project approved for issuance of registration certificate

  2. Registration valid till

Land, licence & cost

Land area of the project13.2 acres
Total licensed area47.418 acres
Licence02 of 1995 dt. 10.03.1995
FAR permissible / proposed1.78 / 18
Estimated project cost₹ 3,886.64 Cr
Cost of land₹ 6.36 Cr
Cost of construction₹ 2,133.35 Cr
Infrastructure and other structures₹ 410.53 Cr
EDC, taxes, levies and other costs₹ 1,336.4 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments0.937%
Construction Of Roads2.2216.8%
Pavements0.352.7%
Parks And Playgrounds2.3317.7%
Green Belts0.191.4%
Vehicle Parkings0.584.4%
Club House215.2%
Any Other4.634.8%

Apartments 511 units · 2 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings40,139.65-511

Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.

External services

ServiceProvided byApproval taken
RoadsNoWATER SUPPLY
HUDA Div - III GurgaonYesELECTRICITY
DHBVNYesSEWAGE DISPOSAL
HUDA Div - II GurgaonYesSTORM WATER DRAINAGE
HUDA Div - Vi GurgaonYes4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)1INTERNAL ROADS AND PAVEMENTS
463AS PER PROJECT REPORT2
Water Supply System118AS PER PROJECT REPORT
3STORM WATER DRAINAGE288
As Per Project Report4ELECTRICITY SUPPLY SYSTEM
7302AS PER PROJECT REPORT5
Sewage Treatment & Garbage Disposal1395AS PER PROJECT REPORT
6STREET LIGHTING384
As Per Project Report7SECURITY AND FIRE FIGHTING
939AS PER PROJECT REPORT8
Playgrounds And Parks1562AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE7971
As Per Project Report10SHOPPING AREA
0AS PER PROJECT REPORT11
Renewable Energy System0AS PER PROJECT REPORT
12SCHOOL11344
As Per Project Report13HOSPITAL/DISPENSARY
3287AS PER PROJECT REPORT14
Any Other6000AS PER PROJECT REPORT
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.24-10-2019(date)
6. Date of approval of Building Plans24-10-2019(date)
7. New projects:i) Likely date of starting the construction work01-07-2019
ii) Likely date of completing the project31-08-2024iii) Sizes of the plots to be offered in the project
Sr. NoPlot Area(In Square Meter)Number of plots in the project
100
Total0iv. Type of apartments to be constructed in the project:
TypeCarpet area(In Square Meter)Number of apartments
Number of towersApartment/Shops/Other Buildings40139.65
5112(vi) Quarterly schedule of development of whole/remaining part of the project:
(c) Apartments/Shops/Other BuildingsExpenditure incurred till the date of application (In Lakhs)Particulars
ExpenditureApartments164942
Shops0Plots
0Expenditure to be made in each quarter (In Lakhs)Particulars
Year-2019Jan-MarApr-June
July-SepOct-DecApartments
14581242Shops
00Plots
00Particulars
Year-2020Jan-MarApr-June
July-SepOct-DecApartments
9238521082
1482Shops0
000
Plots00
00Particulars
Year-2021Jan-MarApr-June
July-SepOct-DecApartments
185525763003
3104Shops0
000
Plots00
00Particulars
Year-2022Jan-MarApr-June
July-SepOct-DecApartments
364045714514
4416Shops0
000
Plots00
00Particulars
Year-2023Jan-MarApr-June
July-SepOct-DecApartments
410641492801
2346Shops0
000
Plots00
00Particulars
Year-2024Jan-MarApr-June
July-SepOct-DecApartments
196000
0Shops0
000
Plots00
00(d) Infrastructure
Expenditure incurred till the date of application (In Lakhs)ParticularsExpenditure
Roads & Pavements382Water Supply System
92Sewerage treatment & garbage disposal1350
Electricity Supply System7033Storm Water Drainage
220Parks and Playgrounds1188
Clubhouse/community centres0Shopping area
0Other843
Parking1918Security and Fire Fighting
714Street Lighting292
Expenditure to be made in each quarter (In Lakhs)ParticularsYear-2021
Jan-MarApr-JuneJuly-Sep
Oct-DecRoads & Pavements0
Water Supply System0Sewerage treatment & garbage disposal
0Electricity Supply System0
Storm Water Drainage0Parks and Playgrounds
0Clubhouse/community centres664
Shopping area0Other
219Dispensary274
Security and Fire Fighting18School
945Parking43
ParticularsYear-2022Jan-Mar
Apr-JuneJuly-SepOct-Dec
Roads & Pavements00
00Water Supply System
000
0Sewerage treatment & garbage disposal0
000
Electricity Supply System00
1225Storm Water Drainage
000
0Parks and Playgrounds0
02958
Clubhouse/community centres664664
664664Shopping area
000
0Other219
219219219
Security and Fire Fighting1818
1919Parking
434343
43Dispensary274
274274274
School945945
945945Particulars
Year-2023Jan-MarApr-June
July-SepOct-DecRoads & Pavements
131313
14Water Supply System3
665
Sewerage treatment & garbage disposal77
1211Electricity Supply System
484843
30Storm Water Drainage10
141518
Parks and Playgrounds5858
5751Clubhouse/community centres
664664664
664Shopping area0
000
Other220220
220220Parking
434343
43Street Lighting10
101010
Security and Fire Fighting1919
1919School
945945945
945Dispensary274
274274274
ParticularsYear-2024Jan-Mar
Apr-JuneJuly-SepOct-Dec
Roads & Pavements185
50Water Supply System
411
0Sewerage treatment & garbage disposal6
110
Electricity Supply System2420
200Storm Water Drainage
632
0Parks and Playgrounds29
20150
Clubhouse/community centres665665
6650Shopping area
000
0Other220
2202200
School945945
949Parking43
8688Dispensary
274274273
Street Lighting1020
22Security and Fire Fighting19
1919IDW and Const Community Facility
1977It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.Signature of the Applicant / Authorised Representative
Stamp _____________Date _____________FORM REP-I
Part - DAccounts related information:1. Annex copy of the balance sheet of last 3 years
Yes2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
No3. Bank account to which the deposits received from apartment buyers will be creditedBank and Branch address
Icici BankBank Account number002105022418
IFSC codeICICI0000021MICR code
110229003Branch code000021

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 4.63 CrAs Per Project Report
Water Supply System₹ 1.18 CrAs Per Project Report
Storm Water Drainage₹ 2.88 CrAs Per Project Report
Electricity Supply System₹ 73.02 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 13.95 CrAs Per Project Report
Street Lighting₹ 3.84 CrAs Per Project Report
Security And Fire Fighting₹ 9.39 CrAs Per Project Report
Playgrounds And Parks₹ 15.62 CrAs Per Project Report
Club House/Community Centre₹ 79.71 CrAs Per Project Report
School₹ 113.44 CrAs Per Project Report
Hospital/Dispensary₹ 32.87 CrAs Per Project Report
Any Other₹ 60 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
Service Estimate ApprovalAlready Been Obtained27 Aug 2014
Aravali ClearanceAlready Been Obtained2 Feb 2016
Electrical Load SanctionAlready Been Obtained29 Apr 2014
Environmental ClearanceAlready Been Obtained29 Aug 2017
Fire Scheme ApprovalAlready Been Obtained24 Jul 2014
Forest ClearanceAlready Been Obtained21 Jan 2016
Sewer Connection PermissionAlready Been Obtained22 Jan 2015
Water Connection PermissionAlready Been Obtained2 Jan 2015
Storm Water Connection PermissionAlready Been Obtained6 May 2015
Water Noc From AdministratorAlready Been Obtained19 Sep 2012

Specifications (as filed)

Flooring Details Of Various Parts Of HouseAnnexure - 3 Attached
Wall Finishing DetailsAnnexure - 3 Attached
Kitchen DetailsAnnexure - 3 Attached
Bathroom FittingsAnnexure - 3 Attached
Wood Work EtcAnnexure - 3 Attached
Doors And Windos FramesAnnexure - 3 Attached
Glass WorkAnnexure - 3 Attached
Electric FittingsAnnexure - 3 Attached
Conducting And Wiring DetailsAnnexure - 3 Attached
Cupboard DetailsAnnexure - 3 Attached
Water StorageAnnexure - 3 Attached
Lift DetailsAnnexure - 3 Attached
External GlazingsAnnexure - 3 Attached
Windows/GlazingsAnnexure - 3 Attached
DoorsAnnexure - 3 Attached
Main DoorsAnnexure - 3 Attached
Internal DoorsAnnexure - 3 Attached
Air ConditioningAnnexure - 3 Attached
Electrical FittingsAnnexure - 3 Attached
Cng Pipe LineAnnexure - 3 Attached
Provision Of Wifi And Broadband FacilityAnnexure - 3 Attached
External Finishing/Colour SchemeAnnexure - 3 Attached
Internal FinishingAnnexure - 3 Attached

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Bella Vista - Central Park Resorts?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.