Basant Vihar
by Sahiba Constructions Pvt Ltd · Sector 19
- RERA registration
- HRERA-PKL-JND-242-2021 Lapsed Project
- Valid till
- 30 Jun 2022
- Project ID
- RERA-PKL-826-2020
- Land area
- 36.779 acres
- Estimated cost
- ₹ 23.47 Cr
RERA registration
| Registration certificate | HRERA-PKL-JND-242-2021 Lapsed Project |
|---|---|
| Registration valid till | 30 Jun 2022 |
| Project ID | RERA-PKL-826-2020 |
| Authority | HRERA Panchkula |
| Project type (as filed) | Ongoing |
| Project name | Basant Vihar |
| Promoter | Sahiba Constructions Pvt Ltd |
| Promoter’s registered office | A-62, Barsati , Hauz Khas, New Delhi -110016 |
| CIN | U74899DL1992PTC051451 |
| Site address | Sector 19 |
| Sector | Sector 19 |
| Tehsil / District | Narwana / Jind |
| Layout plan approved | 6 Mar 2017 |
| Application submitted | 14 Feb 2020 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Panchkula
-
Hearing
Examination By Authority View order
Proceedings
Adjourned to 13.04.2020.
-
Hearing
Objection View order
Proceedings
Adjourned to 04.05.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 01.06.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 22.06.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 17.08.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 28.09.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 16.11.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 14.12.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 18.01.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 22.02.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 05.04.2021.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Registration certificate to be issued.
- Registration valid till
Land, licence & cost
| Land area of the project | 36.779 acres |
|---|---|
| Total licensed area | 45 acres |
| Licence | LICENSE NO 243 OF 2007, 57 OF 2011, 65 OF 2011 |
| FAR permissible / proposed | 54 / 51 |
| Estimated project cost | ₹ 23.47 Cr |
| Cost of land | ₹ 3.24 Cr |
| Infrastructure and other structures | ₹ 10.18 Cr |
| EDC, taxes, levies and other costs | ₹ 10.05 Cr |
How the land will be used
| Use | Area (as filed) | Share |
|---|---|---|
| Plots To Be Sold | 19.0049 | 33.3% |
| Land Area To Be Used For Construction Of Apartments | 19.0049 | 33.3% |
| Construction Of Roads | 14.4 | 25.2% |
| Parks And Playgrounds | 2.75 | 4.8% |
| Green Belts | 0.45 | 0.8% |
| Any Other | 0.5 | 0.9% |
| Commercial | 1.01 | 1.8% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | SELF | Yes |
| Water Supply | PWD | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | PWD | Yes |
| Storm Water Drainage | PWD | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 4.82 Cr | As Per Project Report |
| Water Supply System | ₹ 1.04 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 1.45 Cr | As Per Project Report |
| Electricity Supply System | ₹ 66 lakh | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 1.2 Cr | As Per Project Report |
| Security And Fire Fighting | ₹ 21 lakh | As Per Project Report |
| Playgrounds And Parks | ₹ 24.76 lakh | As Per Project Report |
| Shopping Area | ₹ 19.12 lakh | As Per Project Report |
| School | ₹ 35 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Completion Of The Project | Yet To File For Approval |
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Basant Vihar?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.