RERA applied, not grantedHRERA Gurugram

Azalia

by Dsc Estate Developers Pvt Ltd · Sector-68, Badshahpur

RERA registration
Applied, not granted yet
Applied on
31 Dec 2019
Application status
Withdrawn/Rejected
Project ID
RERA-GRG-515-2019
Land area
15.1 acres
Estimated cost
₹ 416.48 Cr

This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.

RERA registration

Registration certificateNot issued yet: the application is being processed by HRERA Gurugram
Project IDRERA-GRG-515-2019
AuthorityHRERA Gurugram
Project type (as filed)Ongoing
Project nameAzalia
PromoterDsc Estate Developers Pvt Ltd
Promoter’s registered office1114, Hemkunt Chambers, 89 Nehru Place, New Delhi-110019
CINU70200DL2010PTC210988
Site addressSector-68, Badshahpur
SectorSector 68
Tehsil / DistrictBadshahpur St / Gurugram
Layout plan approved20 May 2015
Building plans approved2 Sep 2015
Application submitted31 Dec 2019

Authority, hearings & orders

Current statusWithdrawn/Rejected
Initial scrutiny1st deficiency notice sent to the promoter
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter 1st deficiency notice sent to the promoter
  1. Hearing Examination By Authority
    Proceedings

    No one appeared on behalf of the promoter namely M/s DSC Estate Developers Pvt Ltd. Only an application has been received dated 10.02.2020 for adjournment of the project hearing. The promoter requested for 15 days’ time for removal of the deficiencies in the application. Accordingly, the matter is adjourned to 02.03.2020. Also, the matter be linked up with the suo-motu inquiry going on against Supertech.

  2. Hearing Adjournment
    Proceedings

    next date of hearing on 09.06.2020

  3. Hearing Adjournment
    Proceedings

    next date of hearing on 29.06.2020

  1. Hearing Adjournment
    Proceedings

    next date of hearing on 20.07.2020

  2. Hearing Objection View order
    Proceedings

    Next date of Hearing 24.08.2020

  3. Hearing Objection
    Proceedings

    Next date of hearing on 05.10.2020

  1. Hearing Objection
    Proceedings

    During the hearing proceedings, concerned PE explained the deficiencies which have not been removed by the promoter. It was further intimated that copy of deficiencies stand only email dated 01.10.2020. But so far the promoter has not removed and also has not deposited ₹20,99,515/-. The authority has viewed non-serious attitude of the promoter, and has decided that incase, the promoter did not remove the deficiencies and fee by 26.10.2020. Then, the action towards rejection of their registration of the project will be initiated. In view of show cause no. HARERA/GGM/RPIN/226 dated 14.08.020 already issued to them. After rejection of their application further necessary action to take over of the project under section 8 of the Haryana Real Estate (Regulation and Development) Act, 2016. The matter is adjourned to 29.10.2020.

  2. Hearing Objection
    Proceedings

    Due to administrative work of the authority, the matter is adjourned to 09.11.2020 at 3:00 p.m.

  3. Hearing Adjournment
    Proceedings

    Matter adjourned for dated 19.12.2020

  1. Hearing Adjournment
    Proceedings

    Matter adjourned for dated 01.12.2020

  2. Hearing Adjournment
    Proceedings

    Matter adjourned for dated 01.12.2020

  3. Hearing Adjournment
    Proceedings

    The Matter adjourned for 10.12.2020

  1. Hearing Adjournment
    Proceedings

    The Matter adjourned for 10.12.2020

  2. Hearing Objection
    Proceedings

    The Matter adjourned for 22.02.2021

  3. Hearing Adjournment
    Proceedings

    Hearing adjourned and fixed for 22.02.2021

  1. Hearing Adjournment
    Proceedings

    Next date of hearing on 26.04.2021

  2. Hearing Withdrawn/Rejected
    Proceedings

    Proceedings Dated: 26.04.2021Ms. Jyoti Yadav, Coordinator Planning Branch briefed about the facts of this case. AR (Sh. Yagna Brahmam) is  present on behalf of the promoter through video conferencing.Deficiencies were already conveyed to the promoter. But so far the promoter has not submitted the approved service estimates and plans and renewal of license No. 134 of 2014 dated 26.08.20214 valid upto 25.08.2019,License no. 89 of 2014 dated 08.08.2014 valid upto 07.08.2019 along with other deficit documents. The promoter has already been issued show cause notice dated 14.08.2020 as why application for grant of registration shall not be rejected on account of deficiencies and so far deficiencies have not been removed. The promoter has already been given eleven hearings but still the deficiencies have not been removed by the promoter. The Authority decided to reject the application for grant of registration on account of following deficiencies:1. License is not renewed and is valid up to 25.08.20192. Approved service plans and estimates not submitted. As mentioned by the AR ( Sh. Yagna Brahmam) the promoter  has so far not applied for approval of service plans and estimates to the competent authority although licenses were issued in the year 2013 and 2014.3. Annual statement of project audited accounts have not been received for financial year 2018-19 and 2019-20 in compliance of section 4(2)(l)(D).Processing fee shall be forfeited. Detailed order will follow. Dr. K.K.Khandelwal (Chairman)Samir Kumar (Member) Vijay Kumar Goyal (Member) through video conferencing                                                                                                                                                                                                                                                                                                                               

Land, licence & cost

Land area of the project15.1 acres
Total licensed area15.1 acres
Licence89 of 2013 and 134 of 2014
FAR permissible / proposed1.75 / 1.75
Estimated project cost₹ 416.48 Cr
Cost of land₹ 83.05 Cr
Cost of construction₹ 167.67 Cr
Infrastructure and other structures₹ 21.03 Cr
EDC, taxes, levies and other costs₹ 144.73 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments5.4235.9%
Construction Of Roads6.1740.9%
Parks And Playgrounds2.3115.3%
Area To Be Left For Transferring To The Government For Community Services0.171.1%
Any Other1.036.8%

External services

ServiceProvided byApproval taken
RoadsGMDANo
Water SupplyGMDANo
ElectricityDHBVNNo
Sewage DisposalGMDANo
Storm Water DrainageGMDANo

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 2.55 CrYet To Be Prepared
Water Supply System₹ 1.36 CrYet To Be Prepared
Storm Water Drainage₹ 51 lakhYet To Be Prepared
Electricity Supply System₹ 4.25 CrYet To Be Prepared
Sewage Treatment & Garbage Disposal₹ 4.25 CrYet To Be Prepared
Street Lighting₹ 34 lakhYet To Be Prepared
Security And Fire Fighting₹ 85 lakhYet To Be Prepared
Playgrounds And Parks₹ 51 lakhYet To Be Prepared
School₹ 4.03 CrYet To Be Prepared
Any Other₹ 2.38 CrYet To Be Prepared

Statutory approvals

ApprovalStatusDate
License No 89 Of 2014Already Been Obtained8 Aug 2014
License No 134 Of 2014Already Been Obtained26 Aug 2014
Br IIIAlready Been Obtained2 Sep 2015
Environment ClearanceAlready Been Obtained9 Mar 2017
Fire NocAlready Been Obtained19 Apr 2017
Forest NocAlready Been Obtained19 May 2017

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Azalia?

This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.