Azalia
by Dsc Estate Developers Pvt Ltd · Sector-68, Badshahpur
- RERA registration
- Applied, not granted yet
- Applied on
- 31 Dec 2019
- Application status
- Withdrawn/Rejected
- Project ID
- RERA-GRG-515-2019
- Land area
- 15.1 acres
- Estimated cost
- ₹ 416.48 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Gurugram |
|---|---|
| Project ID | RERA-GRG-515-2019 |
| Authority | HRERA Gurugram |
| Project type (as filed) | Ongoing |
| Project name | Azalia |
| Promoter | Dsc Estate Developers Pvt Ltd |
| Promoter’s registered office | 1114, Hemkunt Chambers, 89 Nehru Place, New Delhi-110019 |
| CIN | U70200DL2010PTC210988 |
| Site address | Sector-68, Badshahpur |
| Sector | Sector 68 |
| Tehsil / District | Badshahpur St / Gurugram |
| Layout plan approved | 20 May 2015 |
| Building plans approved | 2 Sep 2015 |
| Application submitted | 31 Dec 2019 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter 1st deficiency notice sent to the promoter
-
Hearing
Examination By Authority
Proceedings
No one appeared on behalf of the promoter namely M/s DSC Estate Developers Pvt Ltd. Only an application has been received dated 10.02.2020 for adjournment of the project hearing. The promoter requested for 15 days’ time for removal of the deficiencies in the application. Accordingly, the matter is adjourned to 02.03.2020. Also, the matter be linked up with the suo-motu inquiry going on against Supertech.
-
Hearing
Adjournment
Proceedings
next date of hearing on 09.06.2020
-
Hearing
Adjournment
Proceedings
next date of hearing on 29.06.2020
-
Hearing
Adjournment
Proceedings
next date of hearing on 20.07.2020
-
Hearing
Objection View order
Proceedings
Next date of Hearing 24.08.2020
-
Hearing
Objection
Proceedings
Next date of hearing on 05.10.2020
-
Hearing
Objection
Proceedings
During the hearing proceedings, concerned PE explained the deficiencies which have not been removed by the promoter. It was further intimated that copy of deficiencies stand only email dated 01.10.2020. But so far the promoter has not removed and also has not deposited ₹20,99,515/-. The authority has viewed non-serious attitude of the promoter, and has decided that incase, the promoter did not remove the deficiencies and fee by 26.10.2020. Then, the action towards rejection of their registration of the project will be initiated. In view of show cause no. HARERA/GGM/RPIN/226 dated 14.08.020 already issued to them. After rejection of their application further necessary action to take over of the project under section 8 of the Haryana Real Estate (Regulation and Development) Act, 2016. The matter is adjourned to 29.10.2020.
-
Hearing
Objection
Proceedings
Due to administrative work of the authority, the matter is adjourned to 09.11.2020 at 3:00 p.m.
-
Hearing
Adjournment
Proceedings
Matter adjourned for dated 19.12.2020
-
Hearing
Adjournment
Proceedings
Matter adjourned for dated 01.12.2020
-
Hearing
Adjournment
Proceedings
Matter adjourned for dated 01.12.2020
-
Hearing
Adjournment
Proceedings
The Matter adjourned for 10.12.2020
-
Hearing
Adjournment
Proceedings
The Matter adjourned for 10.12.2020
-
Hearing
Objection
Proceedings
The Matter adjourned for 22.02.2021
-
Hearing
Adjournment
Proceedings
Hearing adjourned and fixed for 22.02.2021
-
Hearing
Adjournment
Proceedings
Next date of hearing on 26.04.2021
-
Hearing
Withdrawn/Rejected
Proceedings
Proceedings Dated: 26.04.2021Ms. Jyoti Yadav, Coordinator Planning Branch briefed about the facts of this case. AR (Sh. Yagna Brahmam) is present on behalf of the promoter through video conferencing.Deficiencies were already conveyed to the promoter. But so far the promoter has not submitted the approved service estimates and plans and renewal of license No. 134 of 2014 dated 26.08.20214 valid upto 25.08.2019,License no. 89 of 2014 dated 08.08.2014 valid upto 07.08.2019 along with other deficit documents. The promoter has already been issued show cause notice dated 14.08.2020 as why application for grant of registration shall not be rejected on account of deficiencies and so far deficiencies have not been removed. The promoter has already been given eleven hearings but still the deficiencies have not been removed by the promoter. The Authority decided to reject the application for grant of registration on account of following deficiencies:1. License is not renewed and is valid up to 25.08.20192. Approved service plans and estimates not submitted. As mentioned by the AR ( Sh. Yagna Brahmam) the promoter has so far not applied for approval of service plans and estimates to the competent authority although licenses were issued in the year 2013 and 2014.3. Annual statement of project audited accounts have not been received for financial year 2018-19 and 2019-20 in compliance of section 4(2)(l)(D).Processing fee shall be forfeited. Detailed order will follow. Dr. K.K.Khandelwal (Chairman)Samir Kumar (Member) Vijay Kumar Goyal (Member) through video conferencing
Land, licence & cost
| Land area of the project | 15.1 acres |
|---|---|
| Total licensed area | 15.1 acres |
| Licence | 89 of 2013 and 134 of 2014 |
| FAR permissible / proposed | 1.75 / 1.75 |
| Estimated project cost | ₹ 416.48 Cr |
| Cost of land | ₹ 83.05 Cr |
| Cost of construction | ₹ 167.67 Cr |
| Infrastructure and other structures | ₹ 21.03 Cr |
| EDC, taxes, levies and other costs | ₹ 144.73 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 5.42 | 35.9% |
| Construction Of Roads | 6.17 | 40.9% |
| Parks And Playgrounds | 2.31 | 15.3% |
| Area To Be Left For Transferring To The Government For Community Services | 0.17 | 1.1% |
| Any Other | 1.03 | 6.8% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | No |
| Water Supply | GMDA | No |
| Electricity | DHBVN | No |
| Sewage Disposal | GMDA | No |
| Storm Water Drainage | GMDA | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 2.55 Cr | Yet To Be Prepared |
| Water Supply System | ₹ 1.36 Cr | Yet To Be Prepared |
| Storm Water Drainage | ₹ 51 lakh | Yet To Be Prepared |
| Electricity Supply System | ₹ 4.25 Cr | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 4.25 Cr | Yet To Be Prepared |
| Street Lighting | ₹ 34 lakh | Yet To Be Prepared |
| Security And Fire Fighting | ₹ 85 lakh | Yet To Be Prepared |
| Playgrounds And Parks | ₹ 51 lakh | Yet To Be Prepared |
| School | ₹ 4.03 Cr | Yet To Be Prepared |
| Any Other | ₹ 2.38 Cr | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License No 89 Of 2014 | Already Been Obtained | 8 Aug 2014 |
| License No 134 Of 2014 | Already Been Obtained | 26 Aug 2014 |
| Br III | Already Been Obtained | 2 Sep 2015 |
| Environment Clearance | Already Been Obtained | 9 Mar 2017 |
| Fire Noc | Already Been Obtained | 19 Apr 2017 |
| Forest Noc | Already Been Obtained | 19 May 2017 |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.