LapsedHRERA Gurugram

Avenue 81

by M/S Gls Infracon Pvt. Ltd. · Sector 81,Gurugram, Situated In The Revenue Estate Of Village Nawada Fatehpur, District Gurugram, Haryana

RERA registration
GGM/442/174/2021/10
Registered on
1 Mar 2021
Valid till
31 Dec 2025
Project ID
RERA-GRG-808-2021
Land area
5.663 acres
Apartments
820 in 5 towers
Completion (as filed)
29 Oct 2025
Estimated cost
₹ 188.75 Cr

RERA registration

Registration certificateGGM/442/174/2021/10, dated 1 Mar 2021
Registration valid till31 Dec 2025
Project IDRERA-GRG-808-2021
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameAvenue 81
PromoterM/S Gls Infracon Pvt. Ltd.
Promoter’s registered office707, 7TH Floor, Jmd Pacific Square, Sector-15, Part-II, Gurugram-122001
CINU70102HR2013PTC051299
Site addressSector 81,Gurugram, Situated In The Revenue Estate Of Village Nawada Fatehpur, District Gurugram, Haryana
SectorSector 81
Tehsil / DistrictManesar / Gurugram
Layout plan approved8 Feb 2021
Building plans approved8 Feb 2021
Construction start (as filed)1 May 2021
Completion (as filed)29 Oct 2025
Application submitted8 Feb 2021

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyHearing is fixed for 01.03.2021.
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter By Hand
  1. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Approved.

  2. Registration granted GGM/442/174/2021/10
  3. Certificate uploaded RC Approved and Certificate Uploaded
  1. Registration valid till

Land, licence & cost

Land area of the project5.663 acres
Total licensed area5.663 acres
Licence34 of 2020 dated 30.10.2020 (29.10.2025)
Estimated project cost₹ 188.75 Cr
Cost of land₹ 43.4 Cr
Cost of construction₹ 108.86 Cr
Infrastructure and other structures₹ 2.73 Cr
EDC, taxes, levies and other costs₹ 33.76 Cr

How the land will be used

UseSq mShare
Land Area To Be Used For Construction Of Apartments7,564.39233%
Construction Of Roads1,376.1246%
Parks And Playgrounds1,132.4614.9%
Green Belts1,088.3444.7%
Vehicle Parkings10,917.84347.6%
Electricity Sub-Station361.1291.6%
Any Other44.6620.2%
Meter Room11.9720.1%
Electric Switch Yard418.3621.8%

Apartments 820 units · 5 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings58.51630406
Apartment/Shops/Other Buildings52.965706
Apartment/Shops/Other Buildings56.78611124
Apartment/Shops/Other Buildings56.4060782
Apartment/Shops/Other Buildings54.02581202

Areas are as filed with HRERA.

External services

ServiceProvided byApproval taken
RoadsHSVP/ CONNECTED WITH EXISTING REVENUE RASTANo
Water SupplyHSVPYes
ElectricityDHBVNYes
Sewage DisposalHSVPYes
Storm Water DrainageHSVPNo

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 65 lakhYet To Be Prepared
Water Supply System₹ 90 lakhYet To Be Prepared
Storm Water Drainage₹ 7.5 lakhYet To Be Prepared
Electricity Supply System₹ 1.32 CrYet To Be Prepared
Sewage Treatment & Garbage Disposal₹ 67 lakhYet To Be Prepared
Street Lighting₹ 16 lakhYet To Be Prepared
Security And Fire Fighting₹ 68 lakhYet To Be Prepared
Playgrounds And Parks₹ 20.5 lakhYet To Be Prepared
Renewable Energy System₹ 11.5 lakhYet To Be Prepared
Parking₹ 12.65 lakhYet To Be Prepared
Stp₹ 33 lakhYet To Be Prepared
Underground Water Tank₹ 33 lakhYet To Be Prepared
Rain Water Harvesting₹ 5 lakhYet To Be Prepared
Electrical Sub Station₹ 54.5 lakhYet To Be Prepared

Statutory approvals

ApprovalStatusDate
Building Plan Approval Br-IIIAlready Been Obtained8 Feb 2021
Loi Issued Vide Memo No. Lc-3774/Asstt(Ak)/2020/16240 Dated 14.09.2020Already Been Obtained14 Sep 2020
Forest Noc Issued Vide Memo No. YK1-3RE-DB9K Dated 06.10.2020Already Been Obtained6 Oct 2020
Electric Load Assurance Vide Memo No. Ch-80-Drg.-PlcAlready Been Obtained28 Dec 2020
Water Assurance Vide Memo No. 450Already Been Obtained31 Dec 2020
Sewerage AssuranceAlready Been Obtained30 Dec 2020
Arawali NocAlready Been Obtained27 Jan 2021
License No. 34 Of 2020 Dated 30.10.2020Already Been Obtained30 Oct 2020
Environment ClearanceApplied For But Yet To Receive28 Dec 2020

Specifications (as filed)

Flooring Details Of Various Parts Of HouseTiles
Wall Finishing DetailsOil Bound Distemper
Kitchen DetailsTiles
Bathroom FittingsIsi Marked
Doors And Windos FramesDoor With Wooden Frame.

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Avenue 81?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.