Land Area To Be Used For Construction Of Apartments
0.292
11.1%
Construction Of Roads
0.387
14.8%
Pavements
0.18
6.9%
Parks And Playgrounds
0.049
1.9%
Green Belts
1.182
45.1%
Vehicle Parkings
0.517
19.7%
Electricity Sub-Station
0.012
0.5%
External services
Service
Provided by
Approval taken
Roads
HUDA
Yes
Water Supply
HUDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
HUDA
Yes
Storm Water Drainage
HUDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 79 lakh
Submitted To HUDA
Water Supply System
₹ 4.68 Cr
Submitted To HUDA
Storm Water Drainage
₹ 5 lakh
Submitted To HUDA
Electricity Supply System
₹ 6.01 Cr
Submitted To HUDA
Street Lighting
₹ 13 lakh
Submitted To HUDA
Security And Fire Fighting
₹ 1.81 Cr
Submitted To HUDA
Playgrounds And Parks
₹ 18 lakh
Submitted To HUDA
Club House/Community Centre
₹ 88 lakh
Submitted To HUDA
Renewable Energy System
₹ 31 lakh
Submitted To HUDA
Any Other
₹ 1.62 Cr
Submitted To HUDA
Sewage System
₹ 62 lakh
Submitted To HUDA
Stp
₹ 15 lakh
Submitted To HUDA
Ugt
₹ 52 lakh
Submitted To HUDA
Electrification
₹ 50.43 lakh
Submitted To HUDA
Statutory approvals
Approval
Status
Date
Aai
Already Been Obtained
24 Jul 2019
Haryana State Pollution Board
Already Been Obtained
22 May 2022
Forest (Noc)
Already Been Obtained
27 Dec 2013
Building Plan Approval
Already Been Obtained
1 Jul 2022
Environment Clearance
Already Been Obtained
29 May 2014
Fire Scheme Approval Report
Already Been Obtained
7 Apr 2022
Fresh Water
Already Been Obtained
10 Mar 2022
Nbwl Clearance
Already Been Obtained
11 Mar 2014
Power Load
Already Been Obtained
23 Dec 2020
Release Of Sewage Treated Water For Construction
Already Been Obtained
17 Feb 2022
Request Letter For Hasta For Additional License
Already Been Obtained
8 Jul 2016
Stp Undertaking
Already Been Obtained
9 Sep 2013
Undertaking For DHBVN Power Load
Already Been Obtained
28 Dec 2020
Specifications (as filed)
Flooring Details Of Various Parts Of House
Vitrified Tiles Flooring In Living, Dining & Lobby Wooden/ Vitrified Tiles Flooring In Bedrooms Vitrified Tiles In Kitchen, Utility & Servant Room And Ceramic Tiles In Toilets. Balconies Will Be In Anti-Skid Ceramic Flooring
Wall Finishing Details
Glazed Tiles Of Required Height In Toilets & 600MM Height Above Kitchen Counter Slab In Appropriate Colour & Paint
Kitchen Details
All Kitchen Counters In Pre-Polished Granite/ Marble Stone, Electrical Points For Kitchen Chimney & Hob, Washing Machine & Fridge To Be Provided. Kitchen Will Be Provided With Modular Cabinets Of Appropriate Finish
Main Entrance Doors – Plywood Frames With Polished Veneer On Top. All Internal Doors-Laminated Plywood Frames .
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about ATS Grandstand Phase 1?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.