LapsedHRERA Gurugram

Aster Court Premier

by Orris Infrastructure Pvt Ltd · Sector-85, Badha, Manesar

RERA registration
GGM/287/2018/19
Registered on
13 Oct 2018
Valid till
31 Dec 2025
Project ID
RERA-GRG-415-2019
Land area
5.906 acres
Estimated cost
₹ 305.16 Cr

RERA registration

Registration certificateGGM/287/2018/19, dated 13 Oct 2018
Registration valid till31 Dec 2025
Project IDRERA-GRG-415-2019
AuthorityHRERA Gurugram
Project type (as filed)Ongoing
Project nameAster Court Premier
PromoterOrris Infrastructure Private Limited
Promoter’s registered officeC-3/260, Janakpuri, New Delhi-110058
CINU70109DL2006PTC151295
Site addressSector - 85, Village- Badha , Tehsil-Manesar, Gurugram
SectorSector 85
Tehsil / DistrictManesar / Gurugram
Layout plan approved10 Apr 2012
Building plans approved10 Apr 2012
Application submitted28 Dec 2019

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Next hearingNot Required
  1. Registration granted GGM/287/2018/19
  2. Application submitted online
  3. Application received by HRERA Gurugram
  1. Registration valid till

Land, licence & cost

Land area of the project5.906 acres
Total licensed area29.068 acres
Licence39 OF 2009 (24.07.2009), 99 OF 2011
FAR permissible / proposed1.75 / 1.75
Estimated project cost₹ 305.16 Cr
Cost of land₹ 4.79 Cr
Cost of construction₹ 195.42 Cr
Infrastructure and other structures₹ 20.31 Cr
EDC, taxes, levies and other costs₹ 84.63 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments1.01617.2%
Construction Of Roads1.57926.7%
Pavements0.1753%
Parks And Playgrounds1.6127.3%
Club House0.2013.4%
Any Other1.32522.4%

External services

ServiceProvided byApproval taken
RoadsPWDYes
Water SupplyNoELECTRICITY
Dakshin Haryana Bijli NigamYesSEWAGE DISPOSAL
NoSTORM WATER DRAINAGENo

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 4.73 CrYet To Be Prepared
Water Supply System₹ 60.92 lakhYet To Be Prepared
Storm Water Drainage₹ 50.02 lakhYet To Be Prepared
Electricity Supply System₹ 5.79 CrYet To Be Prepared
Security And Fire Fighting₹ 82.53 lakhYet To Be Prepared
Playgrounds And Parks₹ 12.36 lakhYet To Be Prepared
Club House/Community Centre₹ 3.5 CrYet To Be Prepared
Any Other₹ 4.23 CrYet To Be Prepared

Statutory approvals

ApprovalStatusDate
Airport Height CleranceAlready Been Obtained20 Sep 2010
Wet ConstructionAlready Been Obtained24 Sep 2012
Electrical Load AvailabilityAlready Been Obtained22 Jul 2012
Tree CuttingAlready Been Obtained27 Oct 2010
Environmental ClearanceAlready Been Obtained15 Oct 2013
Consent To EstablishAlready Been Obtained15 Apr 2011
Fire Scheme ApprovalAlready Been Obtained29 Jul 2013
Approval Of Service Plan EstimateAlready Been Obtained21 Mar 2014
Road Access With In PwdAlready Been Obtained27 Jan 2011
AravalliAlready Been Obtained30 Jan 2013

Specifications (as filed)

Flooring Details Of Various Parts Of HouseVitrified Tile In Drawing Hall

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Aster Court Premier?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.