Aspen One
by Whiteland Corporation Pvt Ltd · Darbaripur Road Sector-76
- RERA registration
- GGM/827/559/2024/54
- Registered on
- 27 May 2024
- Valid till
- 30 Jun 2031
- Project ID
- RERA-GRG-1442-2023
- Land area
- 2.316 acres
- Apartments
- 300 in 2 towers
- Completion (as filed)
- 30 Jun 2031
- Estimated cost
- ₹ 606.52 Cr
RERA registration
| Registration certificate | GGM/827/559/2024/54, dated 27 May 2024 |
|---|---|
| Registration valid till | 30 Jun 2031 |
| Project ID | RERA-GRG-1442-2023 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Aspen One |
| Promoter | Whiteland Corporation Pvt Ltd |
| Promoter’s registered office | Worldmark 10TH Floor, Sector-65, Gurugram |
| CIN | U70109HR2021PTC092905 |
| Site address | Darbaripur Road Sector-76 |
| Sector | Sector 76 |
| Tehsil / District | Manesar / Gurugram |
| Building plans approved | 16 May 2024 |
| Construction start (as filed) | 1 Jul 2024 |
| Completion (as filed) | 30 Jun 2031 |
| Application submitted | 21 Dec 2023 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter By Hand
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive and Sh. M.L. Sardana, Accountant briefed about the facts of the case. No reply has been submitted by the promoter company against the deficiencies conveyed by the authority through deficiency notice dated 04.01.2024. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 week’s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016.
-
Hearing
Adjournment View order
Proceedings
Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Atul Kumar Modi (AR) is present on behalf of the promoter. The AR seeks six weeks’ time for submission of approved building plans from DTCP for which in principle approval has already been granted. The AR states that there are no revisions/changes in the existing licensed/registered project beyond the permissible limits prescribed in the ACS, TCP circular vide memo no. Misc-862/2023/7/1/2023-2TCP/11689-91 dated 24.04.2023 and if otherwise, a detailed list of such changes shall be submitted alongwith consent of the 2/3rd allottees. The matter to come up on 20.05.2024.
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Suruchi Pandey, Chartered Accountant briefed about the facts of the project. Shri Navdeep Sardana, Director and Shri Deepak Pant, General Manager are present on behalf of the promoter. Approved in principle as the promoter has submitted requisite consent of 2/3rd allottees in respect of earlier registered project for minor changes in the earlier approved plan. The deficit fees has already been deposited and application to the concerned authority for Fire NOC and approval of Service plans estimates which have already been submitted and final approval shall be submitted within four months and in lieu of same BG/DD of Rs. 25 lakh each shall be submitted and a public notice w.r.t changes in building plan for inspection/objection within one week, if any in respect of the documents/plans submitted by the promoter be published in two newspapers one English and One Hindi. The Environment Clearance has been approved by SEIAA with platinum rating and final approval shall be submitted within two months. The matter to come up on 27.05.2024.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Suruchi Pandey, Chartered Accountant briefed about the facts of the project. Sh. Deepak Pant (GM Coordination) is present on behalf of the promoter. The promoter has submitted two BG of Rs 25 lakhs each for submission of Approved service plans and estimates and Fire Scheme approval within four months from the grant of registration. No objection in respect of the public notice issued by the office has been received till date. The final approval of Environment Clearance shall be submitted within four months from the grant of registration, which has been approved by SEIAA under Platinum category. The promoter shall submit the Mining permission before start of construction. In view of the same, approved as proposed and office to ensure necessary correction in form A to H and DPI.
- Registration granted GGM/827/559/2024/54
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 2.316 acres |
|---|---|
| Total licensed area | 2.316 acres |
| Licence | 172 of 2023(25-08-2023) |
| FAR permissible / proposed | 2.59 / 2.583 |
| Estimated project cost | ₹ 606.52 Cr |
| Cost of land | ₹ 27.7 Cr |
| Cost of construction | ₹ 354.48 Cr |
| Infrastructure and other structures | ₹ 24.1 Cr |
| EDC, taxes, levies and other costs | ₹ 200.24 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 0.298 | 12.9% |
| Construction Of Roads | 0.191 | 8.2% |
| Pavements | 0.515 | 22.2% |
| Parks And Playgrounds | 0.732 | 31.6% |
| Any Other | 0.5799 | 25% |
Apartments 300 units · 2 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 127.19 | 1,369 | 42 |
| Apartment/Shops/Other Buildings | 116.79 | 1,257 | 119 |
| Apartment/Shops/Other Buildings | 116.68 | 1,256 | 8 |
| Apartment/Shops/Other Buildings | 132.84 | 1,430 | 83 |
| Apartment/Shops/Other Buildings | 18.20 | 196 | 48 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 3.8 Cr | As Per Project Report |
| Water Supply System | ₹ 2.6 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 1.3 Cr | As Per Project Report |
| Electricity Supply System | ₹ 1.6 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 1.9 Cr | As Per Project Report |
| Street Lighting | ₹ 65 lakh | As Per Project Report |
| Security And Fire Fighting | ₹ 80 lakh | As Per Project Report |
| Playgrounds And Parks | ₹ 2 Cr | As Per Project Report |
| Renewable Energy System | ₹ 60 lakh | As Per Project Report |
| Any Other | ₹ 8.85 Cr | As Per Project Report |
| Stp | ₹ 35 lakh | As Per Project Report |
| Underground Water Tank | ₹ 60 lakh | As Per Project Report |
| Rain Water Harvesting | ₹ 80 lakh | As Per Project Report |
| Electrical Sub Station | ₹ 4.25 Cr | As Per Project Report |
| Construction Of Circulation Road | ₹ 85 lakh | As Per Project Report |
| Electrification Cost | ₹ 2 Cr | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License | Already Been Obtained | 25 Aug 2023 |
| Loi | Already Been Obtained | 3 Aug 2023 |
| Building Plan | Already Been Obtained | 16 May 2024 |
| Aai | Already Been Obtained | 19 Mar 2024 |
| Powerload Assurance | Already Been Obtained | 22 Feb 2024 |
| Sewage Assurance | Already Been Obtained | 11 Dec 2023 |
| Storm Assurance | Already Been Obtained | 12 Dec 2023 |
| Water Assurance | Already Been Obtained | 15 Dec 2023 |
| Zoning | Already Been Obtained | 25 Aug 2023 |
| Forest Noc | Already Been Obtained | 7 Sep 2022 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Yes |
|---|---|
| Wall Finishing Details | Obd, Emulsion |
| Kitchen Details | Sink & Counter |
| Bathroom Fittings | Yes |
| Wood Work Etc | Doors, Kitchen |
| Doors And Windos Frames | Yes |
| Glass Work | Yes |
| Electric Fittings | Yes |
| Conducting And Wiring Details | Yes |
| Water Storage | Yes |
| Lift Details | Yes |
| External Glazings | Yes |
| Windows/Glazings | Yes |
| Doors | Yes |
| Main Doors | Yes |
| Internal Doors | Yes |
| Air Conditioning | Yes |
| Electrical Fittings | Yes |
| External Finishing/Colour Scheme | Yes |
| Internal Finishing | Yes |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Aspen One?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.