Ashiana Anmol Phase III & Plaza Ph II
by Ashiana Housing Limited · Vill. Dhunela Sec 33 Sohna
- RERA registration
- GGM/579/311/2022/54
- Registered on
- 27 Jun 2022
- Valid till
- 31 Dec 2028
- Project ID
- RERA-GRG-929-2021
- Land area
- 6.788 acres
- Apartments
- 468 in 1 tower
- Completion (as filed)
- 31 Dec 2028
- Estimated cost
- ₹ 231.19 Cr
RERA registration
| Registration certificate | GGM/579/311/2022/54, dated 27 Jun 2022 |
|---|---|
| Registration valid till | 31 Dec 2028 |
| Project ID | RERA-GRG-929-2021 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Ashiana Anmol Phase III & Plaza Ph II |
| Promoter | Ashiana Housing Limited |
| Promoter’s registered office | 5F, Everest, 46/C, Chowringhee Road, Kolkata 70071 West Bengal |
| CIN | L70109WB1986PLC040864 |
| Site address | Vill. Dhunela Sec 33 Sohna |
| Tehsil / District | Sohna / Gurugram |
| Layout plan approved | 5 Mar 2021 |
| Building plans approved | 5 Mar 2021 |
| Construction start (as filed) | 1 Feb 2023 |
| Completion (as filed) | 31 Dec 2028 |
| Application submitted | 10 Sep 2021 |
Authority, hearings & orders
- Application submitted online
- Notice sent to the promoter 1st deficiency notice
-
Hearing
Examination By Authority
Proceedings
Proceedings dated: 12.10.2021 Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case. Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The promoter has submitted an application on 12.10.2021 requesting the authority for the adjournment of hearing because they need more time for the removal of deficiencies. Therefore, the authority considers the request of the promoter to grant two-week time for removal of deficiencies. The matter to come up on 26.10.2021.
-
Hearing
Adjournment
Proceedings
THE MATTER IS ADJOURNED FOR 28.10.2021
-
Hearing
Adjournment
Proceedings
Proceedings dated: 28.10.2021 Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case. No one present on behalf of the promoter. An email dated 28.10.2021 received from the promoter regarding adjournment of hearing for two weeks for the submission of deficit documents. The authority decided to grant two weeks’ time and matter adjourned for 16.11.2021
-
Hearing
Adjournment
Proceedings
Proceedings dated: 16.11.2021 Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case. No one appeared on behalf of the promoter. No reply submitted in reference to first deficiency notice. Earlier registration was granted for an area admeasuring 2.409 acres vide RC No. 50 of 2021 subject to the condition that the promoter shall apply for the registration of the remaining area. Accordingly, the promoter has applied for the registration of an area admeasuring 6.7879 acres on 10.09.2021. The application was scrutinized, and the deficiencies were conveyed to the promoter, but no reply has been submitted by the promoter till date. Last opportunity of hearing is offered to the promoter and matter to come up on 07.12.2021.
-
Hearing
Objection
Proceedings
The matter is adjourned for 13.12.2021
-
Hearing
Adjournment
Proceedings
No one appeared on behalf of the promoter. The promoter is directed to submit the reply of deficiencies conveyed vide notice dated 05.10.2021 along with online PDF of detailed project information. Matter adjourned for 27.12.2021.
-
Hearing
Objection
Proceedings
Matter adjourned for 31.01.2022.
-
Hearing
Adjournment
Proceedings
Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case through video conferencing. By the orders of the authority, the promoter is directed to submit the reply of remaining deficiencies which are conveyed to the promoter along with corrected online DPI and REP-I (A-H). Matter adjourned for 22.02.2022.
-
Hearing
Adjournment
Proceedings
Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case. No one appeared on behalf of the promoter. On the request of the promoter, 15 days time is granted for submission of deficit documents. Matter adjourned for 14.03.2022
-
Hearing
Objection
Proceedings
Sh. Aayush Gupta (Advocate) is present on behalf of the promoter. The AR of the promoter is filing the reply today which will be scrutinized by the concerned Planning Executive and to be put up for further consideration by the Authority on the in the next date of hearing. The matter to come up on 28.03.2022.
-
Hearing
Objection
Proceedings
The matter is adjourned to 31.03.2022
-
Hearing
Adjournment
Proceedings
The matter is adjourned to 02.04.2022
-
Hearing
Adjournment
Proceedings
Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. Sh. Jatin (Legal Assistant) is resent on behalf of the promoter. The promoter requested for the adjournment of 2 weeks as the concerned person is not feeling well. The Authority decided to fix the matter for 18.04.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 25.04.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The reply was submitted today which needs to be scrutinized. The matter to come up on 25.04.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 25.04.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. In the last hearing, the promoter had submitted the reply, which was scrutinized, and remaining deficiencies are conveyed to the promoter. The observations which need to be rectified by the promoter are mentioned in the agenda note. The AR of the promoter requested for one week’s time for rectifying the deficiencies. The Authority granted the same. Matter to come up on 09.05.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 09.05.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The promoter has submitted the reply on 02.05.2022 which was scrutinized, and the remaining deficiencies have been conveyed to the promoter which area mentioned in the agenda note. Regarding late fee, the promoter has not submitted the phasing plan which needs to be done by the competent authority. Since phasing was not done by the competent authority, therefore, the project was to be registered as a single standalone project. Since the authority earlier registered projects in phases but at the same time late fees was also imposed for delay in applying for registration of the project after coming into force of RERA Act, 2016. Therefore, the promoter is directed to submit the late fees along with other deficit documents before next date of hearing. On the request of the promoter one week time is granted, and last opportunity of hearing is given. Matter to come up on 16.05.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 16.05.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. In the last hearing, the promoter was directed to submit the deficit documents along with submission of late fee. As on today, the promoter has not submitted the reply of deficiencies which were already conveyed in the last hearing. The promoter has submitted the reply today in the hearing which needs to be scrutinized by the concerned office. The matter to come up on 30.05.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 30.05.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The promoter has submitted the reply on 17.05.2022 which was scrutinized, and it was found that all the deficiencies have been fulfilled by the promoter except deficit fees of Rs. 17,97,229/, corrections in REP-I (Part A-H) and detailed project information. Apart from rectification of the above deficiencies the promoter is advised to submit a certificate from the concerned branch regarding submission of the annual audit report of project accounts in respect of projects registered till 31.03.2021 and QPRs of the projects of the promoter till last quarter is to be submitted. The matter to come up on 13.06.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 13.06.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter.The coram is incomplete. The matter is adjourned for 27.06.2022.
-
Hearing
Approved And Ready For Certificate Issuing Process
Proceedings
Proceedings dated: 27.06.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The authority decided to grant registration and the promoter is directed to submit the detailed project information within one week.
- Registration granted GGM/579/311/2022/54
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 6.788 acres |
|---|---|
| Total licensed area | 13.338 acres |
| Licence | 20 0f 2014 dt 11.06.2014 valid upto 10.06.2026 |
| FAR permissible / proposed | 1.75 / 0.43 |
| Estimated project cost | ₹ 231.19 Cr |
| Cost of land | ₹ 55.64 Cr |
| Cost of construction | ₹ 73.72 Cr |
| Infrastructure and other structures | ₹ 9.61 Cr |
| EDC, taxes, levies and other costs | ₹ 92.29 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 0.7135 | 10.5% |
| Construction Of Roads | 0.941 | 13.9% |
| Parks And Playgrounds | 0.5469 | 8.1% |
| Vehicle Parkings | 0.4231 | 6.2% |
| Any Other | 1.2555 | 18.5% |
| Service | 2.9066 | 42.8% |
Apartments 468 units · 1 tower
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 92.54 | 996 | 180 |
| Apartment/Shops/Other Buildings | 72.45 | 780 | 90 |
| Apartment/Shops/Other Buildings | 117.27 | 1,262 | 30 |
| Apartment/Shops/Other Buildings | 109.59 | 1,180 | 30 |
| Apartment/Shops/Other Buildings | 16.15 | 174 | 138 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HUDA -ALREADY CONNECTED | Yes |
| Water Supply | HUDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | HUDA | Yes |
| Storm Water Drainage | HUDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 2.17 Cr | Submitted To Town & Country Planning |
| Water Supply System | ₹ 1.03 Cr | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 17.86 lakh | Submitted To Town & Country Planning |
| Electricity Supply System | ₹ 1.63 Cr | Submitted To Town & Country Planning |
| Street Lighting | ₹ 13.54 lakh | Submitted To Town & Country Planning |
| Security And Fire Fighting | ₹ 2.05 Cr | Submitted To Town & Country Planning |
| Playgrounds And Parks | ₹ 3.28 lakh | Submitted To Town & Country Planning |
| Renewable Energy System | ₹ 12.43 lakh | Submitted To Town & Country Planning |
| Electric Sub Station | ₹ 30.91 lakh | As Per Project Report |
| Underground Water Tank | ₹ 11.41 lakh | As Per Project Report |
| Rain Water Harvesting | ₹ 17.86 lakh | As Per Project Report |
| Parking | ₹ 92.79 lakh | As Per Project Report |
| Sewage System | ₹ 73.84 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Environment Clearance | Already Been Obtained | 28 Dec 2015 |
| Forest Noc | Already Been Obtained | 12 Aug 2014 |
| Consent To Establish | Already Been Obtained | 16 Feb 2021 |
| Aai Height Noc | Already Been Obtained | 29 Aug 2019 |
| Building Plan Approval | Already Been Obtained | 5 Mar 2021 |
| Fire Fighting Scheme Approval | Already Been Obtained | 22 Dec 2021 |
| Service Plan Estimate Approval | Already Been Obtained | 17 Dec 2021 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Living/ Dining / Lobby : Double Charged Vitrified Tiles |
|---|
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.