Registration validHRERA GurugramOC / CC on record

Ashiana Anmol Phase III & Plaza Ph II

by Ashiana Housing Limited · Vill. Dhunela Sec 33 Sohna

RERA registration
GGM/579/311/2022/54
Registered on
27 Jun 2022
Valid till
31 Dec 2028
Project ID
RERA-GRG-929-2021
Land area
6.788 acres
Apartments
468 in 1 tower
Completion (as filed)
31 Dec 2028
Estimated cost
₹ 231.19 Cr

RERA registration

Registration certificateGGM/579/311/2022/54, dated 27 Jun 2022
Registration valid till31 Dec 2028
Project IDRERA-GRG-929-2021
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameAshiana Anmol Phase III & Plaza Ph II
PromoterAshiana Housing Limited
Promoter’s registered office5F, Everest, 46/C, Chowringhee Road, Kolkata 70071 West Bengal
CINL70109WB1986PLC040864
Site addressVill. Dhunela Sec 33 Sohna
Tehsil / DistrictSohna / Gurugram
Layout plan approved5 Mar 2021
Building plans approved5 Mar 2021
Construction start (as filed)1 Feb 2023
Completion (as filed)31 Dec 2028
Application submitted10 Sep 2021

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutiny1st deficiency notice sent to the promoter
Next hearingNot Required
  1. Application submitted online
  2. Notice sent to the promoter 1st deficiency notice
  3. Hearing Examination By Authority
    Proceedings

    Proceedings dated: 12.10.2021 Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case. Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The promoter has submitted an application on 12.10.2021 requesting the authority for the adjournment of hearing because they need more time for the removal of deficiencies. Therefore, the authority considers the request of the promoter to grant two-week time for removal of deficiencies. The matter to come up on 26.10.2021.

  1. Hearing Adjournment
    Proceedings

    THE MATTER IS ADJOURNED FOR 28.10.2021

  2. Hearing Adjournment
    Proceedings

    Proceedings dated: 28.10.2021 Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case. No one present on behalf of the promoter. An email dated 28.10.2021 received from the promoter regarding adjournment of hearing for two weeks for the submission of deficit documents. The authority decided to grant two weeks’ time and matter adjourned for 16.11.2021

  3. Hearing Adjournment
    Proceedings

    Proceedings dated: 16.11.2021 Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case. No one appeared on behalf of the promoter. No reply submitted in reference to first deficiency notice. Earlier registration was granted for an area admeasuring 2.409 acres vide RC No. 50 of 2021 subject to the condition that the promoter shall apply for the registration of the remaining area.  Accordingly, the promoter has applied for the registration of an area admeasuring 6.7879 acres on 10.09.2021. The application was scrutinized, and the deficiencies were conveyed to the promoter, but no reply has been submitted by the promoter till date.  Last opportunity of hearing is offered to the promoter and matter to come up on 07.12.2021.

  1. Hearing Objection
    Proceedings

    The matter is adjourned for 13.12.2021

  2. Hearing Adjournment
    Proceedings

    No one appeared on behalf of the promoter. The promoter is directed to submit the reply of deficiencies conveyed vide notice dated 05.10.2021 along with online PDF of detailed project information. Matter adjourned for 27.12.2021.

  3. Hearing Objection
    Proceedings

    Matter adjourned for 31.01.2022.

  1. Hearing Adjournment
    Proceedings

    Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case through video conferencing. By the orders of the authority, the promoter is directed to submit the reply of remaining deficiencies which are conveyed to the promoter along with corrected online DPI and REP-I (A-H). Matter adjourned for 22.02.2022.

  2. Hearing Adjournment
    Proceedings

    Ms. Jyoti Yadav Coordinator Planning Branch briefed the facts of the case. No one appeared on behalf of the promoter. On the request of the promoter, 15 days time is granted for submission of deficit documents. Matter adjourned for 14.03.2022

  3. Hearing Objection
    Proceedings

    Sh. Aayush Gupta (Advocate) is present on behalf of the promoter. The AR of the promoter is filing the reply today which will be scrutinized by the concerned Planning Executive and to be put up for further consideration by the Authority on the in the next date of hearing.   The matter to come up on 28.03.2022.

  1. Hearing Objection
    Proceedings

    The matter is adjourned to 31.03.2022

  2. Hearing Adjournment
    Proceedings

    The matter is adjourned to 02.04.2022

  3. Hearing Adjournment
    Proceedings

    Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. Sh. Jatin (Legal Assistant) is resent on behalf of the promoter. The promoter requested for the adjournment of 2 weeks as the concerned person is not feeling well. The Authority decided to fix the matter for 18.04.2022.

  1. Hearing Objection
    Proceedings

    Proceedings dated: 25.04.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The reply was submitted today which needs to be scrutinized. The matter to come up on 25.04.2022. 

  2. Hearing Objection
    Proceedings

    Proceedings dated: 25.04.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. In the last hearing, the promoter had submitted the reply, which was scrutinized, and remaining deficiencies are conveyed to the promoter. The observations which need to be rectified by the promoter are mentioned in the agenda note. The AR of the promoter requested for one week’s time for rectifying the deficiencies. The Authority granted the same. Matter to come up on 09.05.2022.

  3. Hearing Objection
    Proceedings

    Proceedings dated: 09.05.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The promoter has submitted the reply on 02.05.2022 which was scrutinized, and the remaining deficiencies have been conveyed to the promoter which area mentioned in the agenda note. Regarding late fee, the promoter has not submitted the phasing plan which needs to be done by the competent authority. Since phasing was not done by the competent authority, therefore, the project was to be registered as a single standalone project. Since the authority earlier registered projects in phases but at the same time late fees was also imposed for delay in applying for registration of the project after coming into force of RERA Act, 2016. Therefore, the promoter is directed to submit the late fees along with other deficit documents before next date of hearing. On the request of the promoter one week time is granted, and last opportunity of hearing is given. Matter to come up on 16.05.2022.

  1. Hearing Objection
    Proceedings

    Proceedings dated: 16.05.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. In the last hearing, the promoter was directed to submit the deficit documents along with submission of late fee. As on today, the promoter has not submitted the reply of deficiencies which were already conveyed in the last hearing. The promoter has submitted the reply today in the hearing which needs to be scrutinized by the concerned office. The matter to come up on 30.05.2022.

  2. Hearing Objection
    Proceedings

    Proceedings dated: 30.05.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The promoter has submitted the reply on 17.05.2022 which was scrutinized, and it was found that all the deficiencies have been fulfilled by the promoter except deficit fees of Rs. 17,97,229/, corrections in REP-I (Part A-H) and detailed project information. Apart from rectification of the above deficiencies the promoter is advised to submit a certificate from the concerned branch regarding submission of the annual audit report of project accounts in respect of projects registered till 31.03.2021 and QPRs of the projects of the promoter till last quarter is to be submitted. The matter to come up on 13.06.2022.

  3. Hearing Objection
    Proceedings

    Proceedings dated: 13.06.2022 Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter.The coram is incomplete. The matter is adjourned for 27.06.2022.

  1. Hearing Approved And Ready For Certificate Issuing Process
    Proceedings

    Proceedings dated: 27.06.2022  Sh. Ayush Gupta (Legal Officer) is present on behalf of the promoter. The authority decided to grant registration and the promoter is directed to submit the detailed project information within one week.  

  2. Registration granted GGM/579/311/2022/54
  3. Certificate uploaded RC Uploaded
  1. Registration valid till

Land, licence & cost

Land area of the project6.788 acres
Total licensed area13.338 acres
Licence20 0f 2014 dt 11.06.2014 valid upto 10.06.2026
FAR permissible / proposed1.75 / 0.43
Estimated project cost₹ 231.19 Cr
Cost of land₹ 55.64 Cr
Cost of construction₹ 73.72 Cr
Infrastructure and other structures₹ 9.61 Cr
EDC, taxes, levies and other costs₹ 92.29 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments0.713510.5%
Construction Of Roads0.94113.9%
Parks And Playgrounds0.54698.1%
Vehicle Parkings0.42316.2%
Any Other1.255518.5%
Service2.906642.8%

Apartments 468 units · 1 tower

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings92.54996180
Apartment/Shops/Other Buildings72.4578090
Apartment/Shops/Other Buildings117.271,26230
Apartment/Shops/Other Buildings109.591,18030
Apartment/Shops/Other Buildings16.15174138

Areas are as filed with HRERA.

External services

ServiceProvided byApproval taken
RoadsHUDA -ALREADY CONNECTEDYes
Water SupplyHUDAYes
ElectricityDHBVNYes
Sewage DisposalHUDAYes
Storm Water DrainageHUDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 2.17 CrSubmitted To Town & Country Planning
Water Supply System₹ 1.03 CrSubmitted To Town & Country Planning
Storm Water Drainage₹ 17.86 lakhSubmitted To Town & Country Planning
Electricity Supply System₹ 1.63 CrSubmitted To Town & Country Planning
Street Lighting₹ 13.54 lakhSubmitted To Town & Country Planning
Security And Fire Fighting₹ 2.05 CrSubmitted To Town & Country Planning
Playgrounds And Parks₹ 3.28 lakhSubmitted To Town & Country Planning
Renewable Energy System₹ 12.43 lakhSubmitted To Town & Country Planning
Electric Sub Station₹ 30.91 lakhAs Per Project Report
Underground Water Tank₹ 11.41 lakhAs Per Project Report
Rain Water Harvesting₹ 17.86 lakhAs Per Project Report
Parking₹ 92.79 lakhAs Per Project Report
Sewage System₹ 73.84 lakhAs Per Project Report

Statutory approvals

ApprovalStatusDate
Environment ClearanceAlready Been Obtained28 Dec 2015
Forest NocAlready Been Obtained12 Aug 2014
Consent To EstablishAlready Been Obtained16 Feb 2021
Aai Height NocAlready Been Obtained29 Aug 2019
Building Plan ApprovalAlready Been Obtained5 Mar 2021
Fire Fighting Scheme ApprovalAlready Been Obtained22 Dec 2021
Service Plan Estimate ApprovalAlready Been Obtained17 Dec 2021

Specifications (as filed)

Flooring Details Of Various Parts Of HouseLiving/ Dining / Lobby : Double Charged Vitrified Tiles

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Ashiana Anmol Phase III & Plaza Ph II?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.