RERA applied, not grantedHRERA Gurugram

Arden 45 Phase 2

by Uday Buildwell Private Limited · Village Kanhai, Sector-45

RERA registration
Applied, not granted yet
Applied on
29 Nov 2023
Application status
Withdrawn
Project ID
RERA-GRG-1497-2023
Land area
0.375 acres
Apartments
118 in 1 tower
Completion (as filed)
27 Sep 2026
Estimated cost
₹ 92.22 Cr

This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.

RERA registration

Registration certificateNot issued yet: the application is being processed by HRERA Gurugram
Project IDRERA-GRG-1497-2023
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameArden 45 Phase 2
PromoterUday Buildwell Private Limited
Promoter’s registered office310, Palm Spring Plaza, 3RD Floor, Commercial Complex, Golf Course Road, Sector-54, Gurugram-122001
CINU45400DL2008PTC175635
Site addressVillage Kanhai, Sector-45
SectorSector 45
Tehsil / DistrictGurgaon / Gurugram
Construction start (as filed)1 Jan 2024
Completion (as filed)27 Sep 2026
Application submitted29 Nov 2023

Authority, hearings & orders

Current statusWithdrawn
Initial scrutinyFirst hearing
Next hearingNot Required
  1. Application submitted online
  2. Hearing Examination By Authority View order
    Proceedings

    Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Yudhveer Singh (AR) and Sh. Ashwani Kumar (AR) are present on behalf of the promoter. The AR states that no sale or advertisement in respect of earlier registered project measuring 0.65 acres vide RC No. 76 of 2023 has been made till date and an affidavit to this effect duly signed by the director of the company shall be submitted within one week. Further the approval of plans have been obtained by clubbing the earlier license/registered area and there is no distinct phasing and hence a fresh RC in respect of total area admeasuring 1.025 acres shall be applied with a request to supersede the earlier RC. The concerned official of the authority to check the site and submit report after local verification within two weeks to ascertain the veracity of claim of having no sale affected. The fees paid in respect of the above additional area applied for fresh RC shall be adjusted while applying for the total area including earlier registered area and no discount in respect of fees paid towards earlier area registered. The matter to come up on 08.01.2024. 

  3. Hearing Withdrawn View order
    Proceedings

    Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Ashwani Kumar (AR) is present on behalf of the promoter. The promoter has submitted an application for inclusion of earlier licensed/registered area along with the area applied now for registration due to grant of additional license by DGTCP for an area measuring 0.375 acres. In view of the same the above application is allowed to be withdrawn and the processing fee paid for the above application stand forfeited and registration fee be adjusted in the revised application. 

Land, licence & cost

Land area of the project0.375 acres
Total licensed area0.375 acres
Licence189 OF 2023
FAR permissible / proposed1.87 / 1.869
Estimated project cost₹ 92.22 Cr
Cost of land₹ 44.21 Cr
Cost of construction₹ 23.7 Cr
Infrastructure and other structures₹ 4.23 Cr
EDC, taxes, levies and other costs₹ 20.07 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments0.22560%
Construction Of Roads0.1540%

Apartments 118 units · 1 tower

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings2,612.90-118

Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.

External services

ServiceProvided byApproval taken
RoadsYesWATER SUPPLY
GMDAYesELECTRICITY
NoSEWAGE DISPOSALGMDA
YesSTORM WATER DRAINAGEGMDA
Yes4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:Sr. No.
Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS24.68
Yet To Be Prepared2WATER SUPPLY SYSTEM
17.53YET TO BE PREPARED3
Storm Water Drainage17.53YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM92.81
Yet To Be Prepared5SEWAGE TREATMENT & GARBAGE DISPOSAL
43.48YET TO BE PREPARED6
Street Lighting4.85YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING74.95
Yet To Be Prepared8PLAYGROUNDS AND PARKS

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 24.68 lakhYet To Be Prepared
Water Supply System₹ 17.53 lakhYet To Be Prepared
Storm Water Drainage₹ 17.53 lakhYet To Be Prepared
Electricity Supply System₹ 92.81 lakhYet To Be Prepared
Sewage Treatment & Garbage Disposal₹ 43.48 lakhYet To Be Prepared
Street Lighting₹ 4.85 lakhYet To Be Prepared
Security And Fire Fighting₹ 74.95 lakhYet To Be Prepared
Playgrounds And Parks₹ 4.21 lakhYet To Be Prepared
Underground Water Tank₹ 16.25 lakhYet To Be Prepared
Electrical Sub Station₹ 99.88 lakhYet To Be Prepared
Sewerage System₹ 27 lakhYet To Be Prepared

Statutory approvals

ApprovalStatusDate
Obtained In Principal Approval For Br-IIIApplied For But Yet To Receive10 Nov 2023

Specifications (as filed)

Doors And Windos FramesAlpro, Nayur Door King, Bhutantuff, Jyoti Or Equivalent
Glass WorkSaint Gobain, Ashahi, Modiguard, Gold Plus Or Equivalent
Electric FittingsPolypack, Apter, Atul Or Equivalent Anchor, Abb Or Equivalent
Conducting And Wiring DetailsProcon, Anchor, Paradise Or Equivalent
Lift DetailsOtis/Kone/ Ece/Fuji Tech/Equivalent
DoorsAlpro, Nayur Door King, Bhutantuff, Jyoti Or Equivalent
Main DoorsAlpro, Nayur Door King, Bhutantuff, Jyoti Or Equivalent
Internal DoorsAlpro, Nayur Door King, Bhutantuff, Jyoti Or Equivalent
Air ConditioningVrv System/Centralized Chilled Water System Or As Per Consultant
Electrical FittingsPolypack, Apter, Atul Or Equivalent

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Arden 45 Phase 2?

This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.