by Ansal Housing & Construction Limited · Sector 104 Gurgaon
RERA registration
Applied, not granted yet
Applied on
4 Feb 2019
Application status
In process
Project ID
RERA-GRG-174-2019
Land area
2.1 acres
Estimated cost
₹ 173.52 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
Registration certificate
Not issued yet: the application is being processed by HRERA Gurugram
Project ID
RERA-GRG-174-2019
Authority
HRERA Gurugram
Project type (as filed)
Ongoing
Project name
Ansals Townwalk
Promoter
Ansal Housing & Construction Limited
Promoter’s registered office
606, 6TH Floor, Indra Prakash 21, Barakhamba Road, New Delhi
CIN
L45201DL1983PLC016821
Site address
Sector 104 Gurgaon
Sector
Sector 104
Tehsil / District
Kadipur St / Gurugram
Application submitted
4 Feb 2019
Authority, hearings & orders
Current statusStatus not given
Next hearingNot Required
Application submitted online
Land, licence & cost
Land area of the project
2.1 acres
Total licensed area
2.1 acres
Licence
103 of 2012
Estimated project cost
₹ 173.52 Cr
Cost of land
₹ 53.5 Cr
Cost of construction
₹ 39.8 Cr
Infrastructure and other structures
₹ 4.34 Cr
EDC, taxes, levies and other costs
₹ 75.88 Cr
How the land will be used
Use
Sq m
Share
Land Area To Be Used For Construction Of Apartments
3,352.687
39.5%
Construction Of Roads
3,998.09
47%
Parks And Playgrounds
585.108
6.9%
Vehicle Parkings
562
6.6%
External services
Service
Provided by
Approval taken
Roads
No
WATER SUPPLY
HUDA, Memo No. 99 Dated 8-1-2013
Yes
ELECTRICITY
No
SEWAGE DISPOSAL
No
Storm Water Drainage
No
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
43.54
YET TO BE PREPARED
2
Water Supply System
46.63
YET TO BE PREPARED
3
STORM WATER DRAINAGE
13.97
Yet To Be Prepared
4
ELECTRICITY SUPPLY SYSTEM
178.79
YET TO BE PREPARED
5
Sewage Treatment & Garbage Disposal
26.53
YET TO BE PREPARED
6
STREET LIGHTING
5.44
Yet To Be Prepared
7
SECURITY AND FIRE FIGHTING
119.19
YET TO BE PREPARED
8
Playgrounds And Parks
0
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
Yet To Be Prepared
10
SHOPPING AREA
0
YET TO BE PREPARED
11
Renewable Energy System
0
YET TO BE PREPARED
12
SCHOOL
0
Yet To Be Prepared
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
Any Other
0
YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
NA
(date)
6. Date of approval of Building Plans
NA
(date)
(i) Details of the plots/apartments in the project:
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP
0
152
0
103
49
0
2
APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP
0
84
0
37
47
0
3
APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP
0
1
0
1
0
0
4
APARTMENT/SHOPS/OTHER BUILDINGS Type OFFICE
0
32
0
19
13
0
5
APARTMENT/SHOPS/OTHER BUILDINGS Type OFFICE
0
117
0
72
45
0
6
APARTMENT/SHOPS/OTHER BUILDINGS Type OFFICE
0
1
0
0
1
0
7
APARTMENT/SHOPS/OTHER BUILDINGS Type RESTAURANT
0
4
0
0
4
0
Total
391
0
232
159
0
(ii) Apartments/Shops/Other Buildings:-
(a) Status of construction activities in respect of sold/booked apartments.
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
SHOP
141
Structure Work Is Complete And Balance Finishing Work Is Ongoing
OFFICE
191
Structure Work Is Complete And Balance Finishing Work Is Ongoing
(b) Time schedule of completion of already booked apartments:
Start Date
25-09-2013
Earlier date of completion
30-09-2017
Revised date of completion
31-03-2020
(c) Time schedule for development of infrastructure:
Start Date
25-09-2013
Percentage completion Upto the
date of application
2
Projected date of completion
31-03-2020
(d) Provide further details in the proforma REP-I Part-C-X.
ATTACHED
(e) Plan of action for completing the Project along with requisite infrastructure.
ATTACHED
(iii) Status in respect of plotted colony:-
(a)
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
(b) Schedule for development of Infrastructure:
Start Date
25-09-2013
Percentage completion
0
Projected date of completion
31-03-2020
(c) Provide further details in the proforma REP-I Part-C-X.
(d) Schedule of completing the project and handing over possession of the plots.
(iv) Vehicle parkings details of the project-
a) Underground parking
252
b) Stilt parking
0
c) Covered parking
0
d) Open parking
45
e) Independent garages
0
(v) Quarterly schedule of development of whole/remaining part of the project:
(a) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
5457.95
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
(b) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
24.90
Sewerage treatment & garbage disposal
5.40
Electricity Supply System
20
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - C-X
1.Financial information:
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
232
Structure work is complete and balance finishing work is ongoing
ii. No. of Flats/ Apartments booked
232
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
8124.44 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
5042.90 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
3081.54 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
3081.54 Lakhs
vii. Amount invested in the project upto the date of application
5457.80 Lakhs
Land cost (If any)
1358 Lakhs
Apartments
2784.82 Lakhs
Infrastructure
51.15 Lakhs
EDC/ Taxes Etc.
2914.98 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
6544.29 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
30 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
2.Additional information:
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. Internal Roads And Pavements
43.54
0
II. Water Supply System
46.63
24.90
III. Storm Water Drainage
0
0
IV. Electricity Supply System
304
20
V. Sewage Treatment & Garbage Disposal
26.53
5.40
Vi. Club House/Community Centre
0
0
Vii. School
0
0
Viii. Any Other
0
0
Ix. Solid Waste Collection & Mgmt System
0
0
X. Clubhouse
0
0
Xi. Neighbourhood Shopping
0
0
Xii. Green Areas,Parks,Playgrounds Etc.
0
0
Xiii. Covered Parking
0
0
Xiv. Open Parking
0
0
Xv. Garages
0
0
Xvi. Security System
0
0
Xvii. Other Facilities As Per Project Report
0
0
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
Yes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
Yes
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
Hdfc Bank Vaishali Ghaziabad
Bank Account number
57500000232023
IFSC code
HDFC0000422
MICR code
110240064
Branch code
0422
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 43.54 lakh
Yet To Be Prepared
Water Supply System
₹ 46.63 lakh
Yet To Be Prepared
Storm Water Drainage
₹ 13.97 lakh
Yet To Be Prepared
Electricity Supply System
₹ 1.79 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 26.53 lakh
Yet To Be Prepared
Street Lighting
₹ 5.44 lakh
Yet To Be Prepared
Security And Fire Fighting
₹ 1.19 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
1 Oct 2012
Forest Noc
Already Been Obtained
2 Apr 2013
Airport Height Clearance Noc
Already Been Obtained
21 Jan 2013
HUDA Construction Water Noc
Already Been Obtained
8 Jan 2013
Environmental Clearance
Already Been Obtained
28 Apr 2014
Consent To Establishment
Already Been Obtained
28 Jul 2014
Mining Permission
Already Been Obtained
20 Nov 2013
Fire Scheme Approval
Already Been Obtained
31 Mar 2014
Commencement Certificate
Already Been Obtained
27 Jun 2013
Service Estimate
Applied For But Yet To Receive
Electrical Load
Yet To File For Approval
Specifications (as filed)
Flooring Details Of Various Parts Of House
Raw Rcc Slab
Wall Finishing Details
Plaster
Doors And Windos Frames
Wooden Doors In Offices And Glass Door In Shops
Electric Fittings
Led Fitting In Common Area
Conducting And Wiring Details
Pvc Conduit And Frls Copper Wiring In Common Area
Water Storage
Rcc Ugt And Oht
Lift Details
Stainless Steel Finish Elevators
External Glazings
Structural Glazing
Windows/Glazings
Structural Glazing
Main Doors
Wooden Door For Offices And Glass Door For Shops
Electrical Fittings
Led Fittings In Common Area
External Finishing/Colour Scheme
Whether Proof Texture Paint
Internal Finishing
Plaster
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Ansals Townwalk?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.