Land Area To Be Used For Construction Of Apartments
10,649.603
17.4%
Construction Of Roads
8,980.472
14.7%
Pavements
2,245.118
3.7%
Parks And Playgrounds
12,596.279
20.6%
Green Belts
2,531.13
4.1%
Vehicle Parkings
2,323
3.8%
Electricity Sub-Station
773.879
1.3%
Club House
1,234.2
2%
Sewage And Solid Waste Treatment Facility
332.99
0.5%
Any Other
19,410.468
31.8%
External services
Service
Provided by
Approval taken
Roads
HUDA DIV III
Yes
Water Supply
HUDA DIV III
Yes
Electricity
DHBVN
Yes
Sewage Disposal
HUDA DIV III
Yes
Storm Water Drainage
HUDA DIV III
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 5.35 Cr
Yet To Be Prepared
Water Supply System
₹ 3.09 Cr
Yet To Be Prepared
Storm Water Drainage
₹ 3.47 Cr
Yet To Be Prepared
Electricity Supply System
₹ 22.93 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 1.33 Cr
Yet To Be Prepared
Street Lighting
₹ 30 lakh
Yet To Be Prepared
Security And Fire Fighting
₹ 15.17 Cr
Yet To Be Prepared
Playgrounds And Parks
₹ 1.75 Cr
Yet To Be Prepared
Club House/Community Centre
₹ 10.2 Cr
Yet To Be Prepared
Shopping Area
₹ 25 lakh
Yet To Be Prepared
Renewable Energy System
₹ 30 lakh
Yet To Be Prepared
School
₹ 1 Cr
Yet To Be Prepared
Any Other
₹ 1.89 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
16 May 2012
Electrical Load Availability
Already Been Obtained
Environmental Clearance
Already Been Obtained
Consent To Establish
Already Been Obtained
Mining Permission
Already Been Obtained
Fire Scheme Approval
Already Been Obtained
Services Estimates And Plans
Already Been Obtained
Forest Noc
Already Been Obtained
24 Oct 2013
Airport Height Clearance
Already Been Obtained
HUDA Construction Water Noc
Already Been Obtained
Renewal License
Applied For But Yet To Receive
GMDA/ HUDA/ Mcg Services Connection Permission
Yet To File For Approval
Electrical Load Connection/ Energization
Yet To File For Approval
Hsd Storage Noc
Yet To File For Approval
Consent To Operate Noc
Yet To File For Approval
Occupation Permission Including Fire Noc, HSVP Internal And External Services Noc, Lift Noc, Chief Electrical Engineer Noc And Any Other Required Approval
Yet To File For Approval
Specifications (as filed)
Flooring Details Of Various Parts Of House
Flooring Done With Italian / Spanish / Turkish Marble Of Dyna / Perlato Sislia / Botticino / Crema Marfil Or Equivalent Quality With Designer Patterns
Wall Finishing Details
Painting With Plastic Emulsion
Kitchen Details
Modular Kitchen With Chimney, Hob & R.o.
Bathroom Fittings
Single Lever C.p. Fitting Hans Grohe/Jaguar Or Equivalent.
Doors And Windos Frames
Upvc Window Frames & Flush Doors With Veneer.
Electric Fittings
Modular Range Switch/Sockets/Mcb
Conducting And Wiring Details
Fire Proof Conduiting And Wire
Cupboard Details
Modular Wardrobes.
Water Storage
Underground & Overhead Tanks
Lift Details
High Speed Elevators
Windows/Glazings
Upvs Window With 8MM Thick Glass
Main Doors
Elegantly Designed Flush Doors
Internal Doors
Flush Doors With Veneer
Air Conditioning
Ductable Split A.c.
Electrical Fittings
Modular Range Switch/Sockets/Mcb
Cng Pipe Line
No
Provision Of Wifi And Broadband Facility
Wireless Internet Facilities For All Units
External Finishing/Colour Scheme
External Walls In Texture Paint
Internal Finishing
Painting With Plastic Emulsion
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Ambience Creacions?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.