Layout plan approved
16 Mar 2016
Building plans approved
16 Mar 2016
Application submitted
22 Jan 2020
Authority, hearings & orders
Current statusExtension Certificate Uploaded
Next hearingNot Required
Registration granted80 OF 2017
Application submitted online
Application received by HRERA Gurugram
Registration valid till
Land, licence & cost
Land area of the project
3.175 acres
Total licensed area
3.175 acres
Licence
10 of 2015 Dated 18.09.2015
FAR permissible / proposed
22482.569 / 1.75
Estimated project cost
₹ 187.71 Cr
Cost of land
₹ 17.82 Cr
Cost of construction
₹ 53.97 Cr
Infrastructure and other structures
₹ 41.03 Cr
EDC, taxes, levies and other costs
₹ 74.89 Cr
How the land will be used
Use
Acres
Share
Construction Of Roads
0.895
28.2%
Pavements
0.356
11.2%
Vehicle Parkings
0.0201
0.6%
Area
1.045
32.9%
Corridor
0.85
26.8%
Rain Water Harvesting
0.0089
0.3%
External services
Service
Provided by
Approval taken
Roads
HSVP / GMDA
No
Water Supply
HSVP / GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
DHBVN
No
Storm Water Drainage
HSVP / GMDA
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 1.25 Cr
As Per Project Report
Water Supply System
₹ 8 Cr
As Per Project Report
Storm Water Drainage
₹ 7.5 Cr
As Per Project Report
Electricity Supply System
₹ 9.53 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 2.5 Cr
As Per Project Report
Street Lighting
₹ 3.5 Cr
As Per Project Report
Security And Fire Fighting
₹ 4 Cr
As Per Project Report
Renewable Energy System
₹ 1.5 Cr
As Per Project Report
Parking
₹ 75 lakh
As Per Project Report
Underground Water Tank
₹ 75 lakh
As Per Project Report
Rain Water Harvesting
₹ 75 lakh
As Per Project Report
Electrical Sub Station
₹ 1 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Licence
Already Been Obtained
18 Sep 2015
Environment Clearance
Already Been Obtained
10 Jul 2017
Noc For Water (Construction)
Already Been Obtained
9 Dec 2015
Noc For Drinking Water
Already Been Obtained
5 Apr 2016
Forest Noc
Already Been Obtained
25 Feb 2016
Aravali Noc
Already Been Obtained
2 Mar 2016
Height Clearance
Already Been Obtained
23 Dec 2015
Building Plan Approval
Already Been Obtained
16 Mar 2016
Electrical Load
Already Been Obtained
10 Dec 2015
Harera Registration
Already Been Obtained
23 Aug 2017
Specifications (as filed)
Flooring Details Of Various Parts Of House
Vitreous Tiles
Wall Finishing Details
Pop & Paint
Kitchen Details
Anti Skid Tiles
Bathroom Fittings
Cp & Chinaware
Doors And Windos Frames
Aluminium
Glass Work
St. Gobain
Electric Fittings
Havells
Conducting And Wiring Details
Havells
Water Storage
Pvc Syntex
Lift Details
Otis
External Glazings
St. Gobain
Windows/Glazings
St. Gobain
Doors
Aluminium
Main Doors
Aluminium
Internal Doors
Aluminium
Air Conditioning
Central Air Conditioning
Electrical Fittings
Havells Or Equivalent
Provision Of Wifi And Broadband Facility
Airtel / Ril/Voda Or Equivalent
External Finishing/Colour Scheme
19. External Finishing / Colour Scheme Texture
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Amb Selfie Street?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.