Sec-7 Village Thanakalan Tehsil Kharkhoda,Sonipat, Haryana
Tehsil / District
Kharkhoda / Sonipat
Layout plan approved
19 Sep 2025
Construction start (as filed)
1 Dec 2025
Completion (as filed)
17 Sep 2030
Application submitted
4 Nov 2025
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyListed for hearing on 26-11-2025
Next hearingNot Required
Application submitted online
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS
Registration valid till
Land, licence & cost
Land area of the project
8.344 acres
Total licensed area
8.344 acres
Licence
LICENSE NO. 180 OF 2025 DATED 18.09.2025 VALID UPTO 17.09.2030 ISSUED BY TOWN AND COUNTRY PLANNING DEPARTMENT HARYANA
Estimated project cost
₹ 11.51 Cr
Cost of land
₹ 2.91 Cr
Infrastructure and other structures
₹ 3.1 Cr
EDC, taxes, levies and other costs
₹ 5.5 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
4.467
53.5%
Construction Of Roads
2.104
25.2%
Green Belts
0.627
7.5%
Area To Be Left For Transferring To The Government For Community Services
0.835
10%
Commercial Area
0.215
2.6%
Area Under Road
0.095
1.1%
Plots 145 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
108.82
130
1,171
12
108.89
130
1,172
6
109.45
131
1,178
1
109.45
131
1,178
1
109.52
131
1,179
1
118.13
141
1,272
12
118.13
141
1,272
16
118.98
142
1,281
1
118.98
142
1,281
1
124.61
149
1,341
28
130.50
156
1,405
22
132.68
159
1,428
22
134.85
161
1,452
22
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
No
Electricity
UHBVN
No
Sewage Disposal
HSVP
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 50 lakh
As Per Project Report
Water Supply System
₹ 35 lakh
As Per Project Report
Storm Water Drainage
₹ 20 lakh
As Per Project Report
Electricity Supply System
₹ 1.05 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 45 lakh
As Per Project Report
Street Lighting
₹ 20 lakh
As Per Project Report
Security And Fire Fighting
₹ 15 lakh
As Per Project Report
Renewable Energy System
₹ 10 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
License No 180 Of 2025
Already Been Obtained
18 Sep 2025
Zoning Plan
Already Been Obtained
3 Nov 2025
Specifications (as filed)
Flooring Details Of Various Parts Of House
Not Applicable
Wall Finishing Details
Not Applicable
Kitchen Details
Not Applicable
Bathroom Fittings
Not Applicable
Wood Work Etc
Not Applicable
Doors And Windos Frames
Not Applicable
Glass Work
Not Applicable
Electric Fittings
Not Applicable
Conducting And Wiring Details
Not Applicable
Cupboard Details
Not Applicable
Water Storage
Not Applicable
Lift Details
Not Applicable
External Glazings
Not Applicable
Windows/Glazings
Not Applicable
Doors
Not Applicable
Main Doors
Not Applicable
Internal Doors
Not Applicable
Air Conditioning
Not Applicable
Electrical Fittings
Not Applicable
Cng Pipe Line
Not Applicable
Provision Of Wifi And Broadband Facility
Not Applicable
External Finishing/Colour Scheme
Not Applicable
Internal Finishing
Not Applicable
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Alan City?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.