Affodable Group Housing Colony-Zara Rossa

by Deluris Buildtech India Pvt Lts · Sector 112, Bajghra, Gurugram

RERA registration
82 OF 2017
Registered on
23 Aug 2017
Valid till
30 Jun 2024
Project ID
RERA-GRG-1077-2022
Land area
5.006 acres
Apartments
756
Completion (as filed)
1 Apr 2023
Estimated cost
₹ 165.61 Cr

RERA registration

Registration certificate82 OF 2017, dated 23 Aug 2017
Registration valid till30 Jun 2024
Project IDRERA-GRG-1077-2022
AuthorityHRERA Gurugram (Interim Rera)
Project type (as filed)New
Project nameAffodable Group Housing Colony-Zara Rossa
PromoterDeluris Buildtech India Private Limited
Promoter’s registered officeSector-112, Gurgaon, Bajghera, Gurgaon, Haryana, 122017
CINU70102DL2013PTC257689
Site addressSector-112, Gurgaon, Bajghera, Gurgaon, Haryana, 122017
SectorSector 112
Tehsil / DistrictGurgaon / Gurugram
Layout plan approved3 May 2017
Building plans approved16 Oct 2017
Construction start (as filed)30 Nov 2017
Completion (as filed)1 Apr 2023
Application submitted14 Jun 2022

Authority, hearings & orders

Current statusExtension Certificate Uploaded
Next hearingNot Required
  1. Registration granted 82 OF 2017
  2. Application submitted online
  3. Application received by HRERA Gurugram
  1. Registration valid till

Land, licence & cost

Land area of the project5.006 acres
Total licensed area5.006 acres
Licence7 of 2016 (28-06-2016)
FAR permissible / proposed228 / 228
Estimated project cost₹ 165.61 Cr
Cost of land₹ 35.62 Cr
Cost of construction₹ 85.25 Cr
Infrastructure and other structures₹ 38.17 Cr
EDC, taxes, levies and other costs₹ 6.57 Cr

How the land will be used

UseSq mShare
Land Area To Be Used For Construction Of Apartments3,468.76217.1%
Construction Of Roads3,142.80915.5%
Parks And Playgrounds3,645.71118%
Vehicle Parkings10,002.2649.4%

Apartments 756 units

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings513.905,532346
Apartment/Shops/Other Buildings539.305,805338
Apartment/Shops/Other Buildings645.446,94723
Apartment/Shops/Other Buildings645.476,94826
Apartment/Shops/Other Buildings645.576,94923

Areas are as filed with HRERA.

External services

ServiceProvided byApproval taken
RoadsNoWATER SUPPLY
HUDA(Memo No-159240 Dated 25.08.2017)YesELECTRICITY
DHBVN(Memo No-99 Dated 21.09.2016)YesSEWAGE DISPOSAL
HUDA(Memo No-159239 Dated 25.08.2017)YesSTORM WATER DRAINAGE
GMDA(Memo No-GMDA/Drainage/2021/129 Dated 24.02.2021)YesFOREST NOC
Forest Department(No-2110-G Dated 07.10.2016)YesHEIGHT CLEARANCE
Airport Authority Of India(Dated 29.07.2017)YesARAVALI NOC
Dc(NO.22 Dated 16.11.2016)YesENVIRONMENT CLEARANCE
Seiaa (No. Seiaa/Hr/2017/810 Dated 30.11.2017)YesFIRE NOC
Fire Service(Memo No. Fs/2020/76 Dated 02.03.2020)Yes4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)1INTERNAL ROADS AND PAVEMENTS
290AS PER PROJECT REPORT2
Water Supply System56AS PER PROJECT REPORT
3STORM WATER DRAINAGE280
As Per Project Report4ELECTRICITY SUPPLY SYSTEM
400AS PER PROJECT REPORT5
Sewage Treatment & Garbage Disposal111AS PER PROJECT REPORT
6STREET LIGHTING20
As Per Project Report7SECURITY AND FIRE FIGHTING
300AS PER PROJECT REPORT8
Playgrounds And Parks30AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0
As Per Project Report10SHOPPING AREA
0AS PER PROJECT REPORT11
Renewable Energy System28AS PER PROJECT REPORT
12SCHOOL0
As Per Project Report13HOSPITAL/DISPENSARY
0AS PER PROJECT REPORT14
Any Other445YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.03-05-2017(date)
6. Date of approval of Building Plans16-10-2017(date)
7. New projects:i) Likely date of starting the construction work30-11-2017
ii) Likely date of completing the project01-04-2023iii) Sizes of the plots to be offered in the project
Sr. NoPlot Area(In Square Meter)Number of plots in the project
100
Total0iv. Type of apartments to be constructed in the project:
TypeCarpet area(In Square Meter)Number of apartments
Number of towersApartment/Shops/Other Buildings513.90
3460Apartment/Shops/Other Buildings
539.303380
Apartment/Shops/Other Buildings645.4423
0Apartment/Shops/Other Buildings645.47
260Apartment/Shops/Other Buildings
645.57230
(vi) Quarterly schedule of development of whole/remaining part of the project:(c) Apartments/Shops/Other BuildingsExpenditure incurred till the date of application (In Lakhs)
ParticularsExpenditureApartments
6385.91Shops212.76
Plots0Expenditure to be made in each quarter (In Lakhs)
ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-Dec
Jan-Mar(d) InfrastructureExpenditure incurred till the date of application (In Lakhs)
ParticularsExpenditureRoads & Pavements
0Water Supply System0
Sewerage treatment & garbage disposal55.32Electricity Supply System
177.36Storm Water Drainage8.50
Parks and Playgrounds0Clubhouse/community centres
0Shopping area0
Other167.00Expenditure to be made in each quarter (In Lakhs)
ParticularsYear-2022Jan-Mar
Apr-JuneJuly-SepOct-Dec
Roads & Pavements0190.00
0Water Supply System2.89
13.110Sewerage treatment & garbage disposal

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 2.9 CrAs Per Project Report
Water Supply System₹ 56 lakhAs Per Project Report
Storm Water Drainage₹ 2.8 CrAs Per Project Report
Electricity Supply System₹ 4 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 1.11 CrAs Per Project Report
Street Lighting₹ 20 lakhAs Per Project Report
Security And Fire Fighting₹ 3 CrAs Per Project Report
Playgrounds And Parks₹ 30 lakhAs Per Project Report
Renewable Energy System₹ 28 lakhAs Per Project Report
Any Other₹ 4.45 CrYet To Be Prepared

Statutory approvals

ApprovalStatusDate
Airport Height Clearance NocAlready Been Obtained29 Jul 2017
HUDA Construction Water NocAlready Been Obtained25 Aug 2017
Electrical Load AvailabilityAlready Been Obtained21 Sep 2016
Environmental ClearanceAlready Been Obtained30 Nov 2017
Mining PermissionAlready Been Obtained9 Feb 2018
Fire Scheme ApprovalAlready Been Obtained31 Jul 2019
Services Estimates And PlansApplied For But Yet To Receive23 Jun 2021

Specifications (as filed)

Flooring Details Of Various Parts Of HouseVitrified Tile In Rooms, Ceramic Tile In Toilets
Wall Finishing DetailsOil Bound Distemper
Kitchen DetailsCeramic Tile Up To 2FEET Above Counter
Bathroom FittingsGood Quality C.p. Fittings
Doors And Windos FramesAluminium/Upvc For External Windows. Wooden Frame In Internal Door
Glass WorkAs Required
Electric FittingsIsi Mark
Conducting And Wiring DetailsIsi Mark
Water StorageUnder Ground & Over Head Tank
Lift DetailsAs Required
External GlazingsAs Required
Windows/GlazingsAs Required
DoorsFlush Door/Skin Moulded Hdf Panel Door
Main DoorsFlush Door/Skin Moulded Hdf Panel Door
Internal DoorsFlush Door/Skin Moulded Hdf Panel Door
Electrical FittingsIsi Mark
External Finishing/Colour SchemeGood Quality Exterior Paint
Internal FinishingOil Bound Distemper In Wall & Ceiling

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Affodable Group Housing Colony-Zara Rossa?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.