Affodable Group Housing Colony-Zara Rossa
by Deluris Buildtech India Pvt Lts · Sector 112, Bajghra, Gurugram
- RERA registration
- 82 OF 2017
- Registered on
- 23 Aug 2017
- Valid till
- 30 Jun 2024
- Project ID
- RERA-GRG-1077-2022
- Land area
- 5.006 acres
- Apartments
- 756
- Completion (as filed)
- 1 Apr 2023
- Estimated cost
- ₹ 165.61 Cr
RERA registration
| Registration certificate | 82 OF 2017, dated 23 Aug 2017 |
|---|---|
| Registration valid till | 30 Jun 2024 |
| Project ID | RERA-GRG-1077-2022 |
| Authority | HRERA Gurugram (Interim Rera) |
| Project type (as filed) | New |
| Project name | Affodable Group Housing Colony-Zara Rossa |
| Promoter | Deluris Buildtech India Private Limited |
| Promoter’s registered office | Sector-112, Gurgaon, Bajghera, Gurgaon, Haryana, 122017 |
| CIN | U70102DL2013PTC257689 |
| Site address | Sector-112, Gurgaon, Bajghera, Gurgaon, Haryana, 122017 |
| Sector | Sector 112 |
| Tehsil / District | Gurgaon / Gurugram |
| Layout plan approved | 3 May 2017 |
| Building plans approved | 16 Oct 2017 |
| Construction start (as filed) | 30 Nov 2017 |
| Completion (as filed) | 1 Apr 2023 |
| Application submitted | 14 Jun 2022 |
Authority, hearings & orders
- Registration granted 82 OF 2017
- Application submitted online
- Application received by HRERA Gurugram
- Registration valid till
Land, licence & cost
| Land area of the project | 5.006 acres |
|---|---|
| Total licensed area | 5.006 acres |
| Licence | 7 of 2016 (28-06-2016) |
| FAR permissible / proposed | 228 / 228 |
| Estimated project cost | ₹ 165.61 Cr |
| Cost of land | ₹ 35.62 Cr |
| Cost of construction | ₹ 85.25 Cr |
| Infrastructure and other structures | ₹ 38.17 Cr |
| EDC, taxes, levies and other costs | ₹ 6.57 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 3,468.762 | 17.1% |
| Construction Of Roads | 3,142.809 | 15.5% |
| Parks And Playgrounds | 3,645.711 | 18% |
| Vehicle Parkings | 10,002.26 | 49.4% |
Apartments 756 units
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 513.90 | 5,532 | 346 |
| Apartment/Shops/Other Buildings | 539.30 | 5,805 | 338 |
| Apartment/Shops/Other Buildings | 645.44 | 6,947 | 23 |
| Apartment/Shops/Other Buildings | 645.47 | 6,948 | 26 |
| Apartment/Shops/Other Buildings | 645.57 | 6,949 | 23 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | No | WATER SUPPLY |
| HUDA(Memo No-159240 Dated 25.08.2017) | Yes | ELECTRICITY |
| DHBVN(Memo No-99 Dated 21.09.2016) | Yes | SEWAGE DISPOSAL |
| HUDA(Memo No-159239 Dated 25.08.2017) | Yes | STORM WATER DRAINAGE |
| GMDA(Memo No-GMDA/Drainage/2021/129 Dated 24.02.2021) | Yes | FOREST NOC |
| Forest Department(No-2110-G Dated 07.10.2016) | Yes | HEIGHT CLEARANCE |
| Airport Authority Of India(Dated 29.07.2017) | Yes | ARAVALI NOC |
| Dc(NO.22 Dated 16.11.2016) | Yes | ENVIRONMENT CLEARANCE |
| Seiaa (No. Seiaa/Hr/2017/810 Dated 30.11.2017) | Yes | FIRE NOC |
| Fire Service(Memo No. Fs/2020/76 Dated 02.03.2020) | Yes | 4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report: |
| Sr. No. | Name of the facility | Estimated cost (In Lakhs)(Within the project area only) |
| Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C) | 1 | INTERNAL ROADS AND PAVEMENTS |
| 290 | AS PER PROJECT REPORT | 2 |
| Water Supply System | 56 | AS PER PROJECT REPORT |
| 3 | STORM WATER DRAINAGE | 280 |
| As Per Project Report | 4 | ELECTRICITY SUPPLY SYSTEM |
| 400 | AS PER PROJECT REPORT | 5 |
| Sewage Treatment & Garbage Disposal | 111 | AS PER PROJECT REPORT |
| 6 | STREET LIGHTING | 20 |
| As Per Project Report | 7 | SECURITY AND FIRE FIGHTING |
| 300 | AS PER PROJECT REPORT | 8 |
| Playgrounds And Parks | 30 | AS PER PROJECT REPORT |
| 9 | CLUB HOUSE/COMMUNITY CENTRE | 0 |
| As Per Project Report | 10 | SHOPPING AREA |
| 0 | AS PER PROJECT REPORT | 11 |
| Renewable Energy System | 28 | AS PER PROJECT REPORT |
| 12 | SCHOOL | 0 |
| As Per Project Report | 13 | HOSPITAL/DISPENSARY |
| 0 | AS PER PROJECT REPORT | 14 |
| Any Other | 445 | YET TO BE PREPARED |
| 5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed. | 03-05-2017 | (date) |
| 6. Date of approval of Building Plans | 16-10-2017 | (date) |
| 7. New projects: | i) Likely date of starting the construction work | 30-11-2017 |
| ii) Likely date of completing the project | 01-04-2023 | iii) Sizes of the plots to be offered in the project |
| Sr. No | Plot Area(In Square Meter) | Number of plots in the project |
| 1 | 0 | 0 |
| Total | 0 | iv. Type of apartments to be constructed in the project: |
| Type | Carpet area(In Square Meter) | Number of apartments |
| Number of towers | Apartment/Shops/Other Buildings | 513.90 |
| 346 | 0 | Apartment/Shops/Other Buildings |
| 539.30 | 338 | 0 |
| Apartment/Shops/Other Buildings | 645.44 | 23 |
| 0 | Apartment/Shops/Other Buildings | 645.47 |
| 26 | 0 | Apartment/Shops/Other Buildings |
| 645.57 | 23 | 0 |
| (vi) Quarterly schedule of development of whole/remaining part of the project: | (c) Apartments/Shops/Other Buildings | Expenditure incurred till the date of application (In Lakhs) |
| Particulars | Expenditure | Apartments |
| 6385.91 | Shops | 212.76 |
| Plots | 0 | Expenditure to be made in each quarter (In Lakhs) |
| Particulars | Expenditure to be made in each quarter ( | ) |
| Apr-June | July-Sep | Oct-Dec |
| Jan-Mar | (d) Infrastructure | Expenditure incurred till the date of application (In Lakhs) |
| Particulars | Expenditure | Roads & Pavements |
| 0 | Water Supply System | 0 |
| Sewerage treatment & garbage disposal | 55.32 | Electricity Supply System |
| 177.36 | Storm Water Drainage | 8.50 |
| Parks and Playgrounds | 0 | Clubhouse/community centres |
| 0 | Shopping area | 0 |
| Other | 167.00 | Expenditure to be made in each quarter (In Lakhs) |
| Particulars | Year-2022 | Jan-Mar |
| Apr-June | July-Sep | Oct-Dec |
| Roads & Pavements | 0 | 190.00 |
| 0 | Water Supply System | 2.89 |
| 13.11 | 0 | Sewerage treatment & garbage disposal |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 2.9 Cr | As Per Project Report |
| Water Supply System | ₹ 56 lakh | As Per Project Report |
| Storm Water Drainage | ₹ 2.8 Cr | As Per Project Report |
| Electricity Supply System | ₹ 4 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 1.11 Cr | As Per Project Report |
| Street Lighting | ₹ 20 lakh | As Per Project Report |
| Security And Fire Fighting | ₹ 3 Cr | As Per Project Report |
| Playgrounds And Parks | ₹ 30 lakh | As Per Project Report |
| Renewable Energy System | ₹ 28 lakh | As Per Project Report |
| Any Other | ₹ 4.45 Cr | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Airport Height Clearance Noc | Already Been Obtained | 29 Jul 2017 |
| HUDA Construction Water Noc | Already Been Obtained | 25 Aug 2017 |
| Electrical Load Availability | Already Been Obtained | 21 Sep 2016 |
| Environmental Clearance | Already Been Obtained | 30 Nov 2017 |
| Mining Permission | Already Been Obtained | 9 Feb 2018 |
| Fire Scheme Approval | Already Been Obtained | 31 Jul 2019 |
| Services Estimates And Plans | Applied For But Yet To Receive | 23 Jun 2021 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified Tile In Rooms, Ceramic Tile In Toilets |
|---|---|
| Wall Finishing Details | Oil Bound Distemper |
| Kitchen Details | Ceramic Tile Up To 2FEET Above Counter |
| Bathroom Fittings | Good Quality C.p. Fittings |
| Doors And Windos Frames | Aluminium/Upvc For External Windows. Wooden Frame In Internal Door |
| Glass Work | As Required |
| Electric Fittings | Isi Mark |
| Conducting And Wiring Details | Isi Mark |
| Water Storage | Under Ground & Over Head Tank |
| Lift Details | As Required |
| External Glazings | As Required |
| Windows/Glazings | As Required |
| Doors | Flush Door/Skin Moulded Hdf Panel Door |
| Main Doors | Flush Door/Skin Moulded Hdf Panel Door |
| Internal Doors | Flush Door/Skin Moulded Hdf Panel Door |
| Electrical Fittings | Isi Mark |
| External Finishing/Colour Scheme | Good Quality Exterior Paint |
| Internal Finishing | Oil Bound Distemper In Wall & Ceiling |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Affodable Group Housing Colony-Zara Rossa?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.