Initial scrutiny1st deficiency notice sent to the promoter
Next hearingNot Required
Application submitted online
HearingExamination By AuthorityProceedings
No one is present on behalf of the promoter. It has came to the notice of the Authority that approved building plans of 140 plots are deficit. The Authority decide to grant one week time. The matter is to be come up on 12.04.2021.
HearingApproved And Ready For Certificate Issuing ProcessProceedings
Mr. Akhil Aggarwal authorized representative of the promoter is present on behalf of the promoter. The promoter is directed to submit the affidavit regarding the revalidation of building plan (BR-III) submitted that there is no revision/changes at the applying for revalidation. The authority has decided to issue conditional registration certificate on submission of the above mentioned affidavit by the promoter.
Registration grantedGGM/449/181/2021/17
Certificate uploadedApproved and RC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
49.6 acres
Total licensed area
114.506 acres
Licence
59 of 2013 (17.07.2013)
FAR permissible / proposed
1.45 / 1.45
Estimated project cost
₹ 424.87 Cr
Cost of land
₹ 25.59 Cr
Cost of construction
₹ 279.18 Cr
Infrastructure and other structures
₹ 13.35 Cr
EDC, taxes, levies and other costs
₹ 106.75 Cr
How the land will be used
Use
Area (as filed)
Share
Land Area To Be Used For Construction Of Apartments
7.069
100%
External services
Service
Provided by
Approval taken
Roads
NOT APPLICABLE
No
Water Supply
GMDA/HSVP
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA/HSVP
Yes
Storm Water Drainage
GMDA/HSVP
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 2.87 Cr
Submitted To Town & Country Planning
Water Supply System
₹ 73 lakh
Submitted To Town & Country Planning
Storm Water Drainage
₹ 1.07 Cr
Submitted To Town & Country Planning
Electricity Supply System
₹ 60 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 30 lakh
Submitted To Town & Country Planning
Street Lighting
₹ 45 lakh
As Per Project Report
Security And Fire Fighting
₹ 2.86 Cr
As Per Project Report
Playgrounds And Parks
₹ 42 lakh
Submitted To Town & Country Planning
Any Other
₹ 1.24 Cr
Submitted To Town & Country Planning
Stp
₹ 75 lakh
Submitted To Town & Country Planning
Ug Tank
₹ 53 lakh
Submitted To Town & Country Planning
Rain Water Harvesting
₹ 27 lakh
Submitted To Town & Country Planning
Electrical Sub Station
₹ 60 lakh
Submitted To Town & Country Planning
Statutory approvals
Approval
Status
Date
Forest
Already Been Obtained
20 Jan 2014
Electrical Load Availability
Already Been Obtained
25 Jun 2020
Licence
Already Been Obtained
12 Sep 2019
Environment Clearance
Already Been Obtained
17 Oct 2014
Water Supply
Already Been Obtained
11 Jun 2020
Service Estimate Plan
Already Been Obtained
2 Aug 2019
Licence
Already Been Obtained
17 Jul 2013
Revised Environment Clearance
Applied For But Yet To Receive
19 Oct 2019
Building Plan
Applied For But Yet To Receive
24 Mar 2021
Sewage Disposal
Applied For But Yet To Receive
25 Aug 2020
Specifications (as filed)
Flooring Details Of Various Parts Of House
Stilt - Heavy Duty Anti Skid Tiles / Cobblestone In Parking Area
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Ace Palm Floors?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.