Land Area To Be Used For Construction Of Apartments
5,588.492
32.9%
Construction Of Roads
3,513.33
20.7%
Parks And Playgrounds
770.372
4.5%
Vehicle Parkings
2,372.156
14%
Any Other
4,752.42
28%
Apartments 700 units · 1 tower
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
18,590.85
-
700
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
Service
Provided by
Approval taken
Roads
HSVP/GMDA
No
Water Supply
HSVP
Yes
Electricity
DHBVN
Yes
Sewage Disposal
HSVP/GMDA
Yes
Storm Water Drainage
HSVP/GMDA
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 1.73 Cr
Submitted To HUDA
Water Supply System
₹ 1.8 Cr
Submitted To HUDA
Storm Water Drainage
₹ 36.83 lakh
Submitted To HUDA
Electricity Supply System
₹ 13.65 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 71.95 lakh
Submitted To HUDA
Street Lighting
₹ 16.12 lakh
Submitted To HUDA
Security And Fire Fighting
₹ 6.2 Cr
Yet To Be Prepared
Renewable Energy System
₹ 90 lakh
Yet To Be Prepared
Horticulture
₹ 3.53 lakh
Submitted To HUDA
Hvac
₹ 9.92 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
26 Oct 2012
Building Plan Approval
Already Been Obtained
6 Apr 2018
Revised Building Plan Approval
Already Been Obtained
25 Oct 2019
Environment Clearance
Already Been Obtained
30 Jan 2018
Height Clearance
Already Been Obtained
21 Mar 2018
Mining Permission
Already Been Obtained
14 Mar 2018
Consent To Establish
Already Been Obtained
8 Mar 2018
Aravali Noc
Already Been Obtained
30 May 2013
Forest Noc
Already Been Obtained
18 Apr 2013
Assurance Of Fresh Water Supply
Already Been Obtained
12 Oct 2017
Assurance For Stp Water For Construction
Already Been Obtained
16 Oct 2017
Assurance Of Ultimate Power Load
Already Been Obtained
5 Dec 2014
Assurance For Sewerage Connection
Already Been Obtained
16 Oct 2017
Specifications (as filed)
Flooring Details Of Various Parts Of House
Stone / Tile Flooring In Common Areas
Wall Finishing Details
Cement Plaster & Paint In Common Areas
Kitchen Details
N/A
Bathroom Fittings
White Chinaware With Cp Fittings
Wood Work Etc
N/A
Doors And Windos Frames
Aluminium Frames With Glass
Glass Work
Toughened Glass 6MM Thick And Above
Electric Fittings
Electrical Fittings & Fixtures Not Provided
Conducting And Wiring Details
Pvc Conducting With Copper Wiring
Cupboard Details
N/A
Water Storage
400KL Fire Tank, 150KL Domestic Tank, 150KL Raw Water Tank
Lift Details
10 Nos
External Glazings
Curtain / Structural Glazing
Windows/Glazings
Aluminium Frames With Glass
Doors
Commercial Flush Door Shutters / Glass Doors
Main Doors
Commercial Flush Door Shutters / Glass Doors
Internal Doors
Commercial Flush Door Shutters / Glass Doors
Air Conditioning
Chilled Water & Dx System
Electrical Fittings
Electrical Fittings & Fixtures Not Provided
Cng Pipe Line
N/A
Provision Of Wifi And Broadband Facility
Yes Provision Is There
External Finishing/Colour Scheme
Plaster & Paint, Glazing, Acp / Stone Cladding
Internal Finishing
Cement / Gypsum Plaster In Common Areas
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about 83 Metro Street?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.