Layout plan approved
14 Mar 2018
Building plans approved
14 Mar 2018
Application submitted
2 Nov 2019
Authority, hearings & orders
Current statusExtension Certificate Uploaded
Next hearingNot Required
Registration granted28 OF 2017
Application submitted online
Application received by HRERA Gurugram
Registration valid till
Land, licence & cost
Land area of the project
2.893 acres
Total licensed area
2.893 acres
Licence
34 OF 2012 (15-04-2012)
FAR permissible / proposed
1.78 / 1.77
Estimated project cost
₹ 179 Cr
Cost of land
₹ 8.6 Cr
Cost of construction
₹ 90.65 Cr
Infrastructure and other structures
₹ 2.35 Cr
EDC, taxes, levies and other costs
₹ 77.4 Cr
How the land will be used
Use
Sq m
Share
Land Area To Be Used For Construction Of Apartments
2,892.5
24.7%
Construction Of Roads
1,945.351
16.6%
Pavements
459.214
3.9%
Grass
596.104
5.1%
Area
5,814.368
49.7%
External services
Service
Provided by
Approval taken
Roads
HUDA
Yes
Water Supply
HUDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
HUDA
Yes
Storm Water Drainage
HUDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 46.13 lakh
Submitted To HUDA
Water Supply System
₹ 85.76 lakh
Submitted To HUDA
Storm Water Drainage
₹ 16.45 lakh
Submitted To HUDA
Sewage Treatment & Garbage Disposal
₹ 22.92 lakh
Submitted To HUDA
Street Lighting
₹ 5.33 lakh
Submitted To HUDA
Any Other
₹ 58.41 lakh
Submitted To HUDA
Statutory approvals
Approval
Status
Date
Environment Clearance
Already Been Obtained
20 Aug 2018
Approved Zoning Plan Drawing
Already Been Obtained
25 Aug 2015
Approved Zoning Plan Letter
Already Been Obtained
25 Aug 2015
Bocw Registration Issued By The Assistant Director (Is& H) Gurugram -II, Registration Officer Cum Assessing Authority , Government Of Haryana
Already Been Obtained
10 Mar 2015
Br-III Approval Of Revised Building Plan
Already Been Obtained
14 Mar 2018
Certificate Of Registration Issued By The Labour Commissioner Haryana & Registering Officer, Labour Department Haryana
Already Been Obtained
14 Dec 2015
Noc From Pollution Board
Already Been Obtained
6 Feb 2017
Aravali Notification
Already Been Obtained
25 Apr 2014
Noc From Forest Dept.
Already Been Obtained
22 Apr 2014
Assurance Letter For Electricity Department
Already Been Obtained
11 Mar 2014
Noc From HUDA For Construction
Already Been Obtained
22 Apr 2013
Noc From Airports Authority
Already Been Obtained
17 Apr 2013
Licence No. 34 Of 2012
Already Been Obtained
15 Apr 2012
Approval Of Revised Building Plans
Already Been Obtained
14 Mar 2018
Specifications (as filed)
Flooring Details Of Various Parts Of House
Gf Central Plaza - Pavers/ Tiles, Common Toilets - Vitrified / Ceramic Tiles, Corridors / Passage - Vitrified / Ceramic Tiles,
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about 70 Grandwalk?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.