114 Avenue
by Vsr Infratech Private Limited · Sector-114, Gurgaon-Bajghera Road, Tehsil- Gurugram, District- Gurugram
- RERA registration
- GGM/359/91/2019/53 DATED-30.09.2019
- Valid till
- 31 Dec 2020
- Project ID
- RERA-GRG-231-2019
- Estimated cost
- ₹ 196.17 Cr
RERA registration
| Registration certificate | GGM/359/91/2019/53 DATED-30.09.2019 |
|---|---|
| Registration valid till | 31 Dec 2020 |
| Project ID | RERA-GRG-231-2019 |
| Authority | HRERA Gurugram |
| Project type (as filed) | Ongoing |
| Project name | 114 Avenue |
| Promoter | Vsr Infratech Private Limited |
| Promoter’s registered office | Plot No-14, Ground Floor, Sector-44, Gurgaon-122003 |
| CIN | U70100DL2010PTC209004 |
| Site address | Sector-114, Gurgaon-Bajghera Road, Tehsil- Gurugram, District- Gurugram |
| Sector | Sector 114 |
| Tehsil / District | Gurgaon / Gurugram |
| Layout plan approved | 22 Jul 2011 |
| Building plans approved | 20 Jul 2016 |
| Application submitted | 14 May 2019 |
Authority, hearings & orders
- Application submitted online
-
Hearing
Examination By Authority
Proceedings
Next date for hearing 07.08.2019
-
Hearing
Objection
Proceedings
Next date for hearing 29.08.2019
- Application received by HRERA Gurugram
-
Hearing
Objection
Proceedings
Next date for hearing 11.09.2019
-
Hearing
Approved And Ready For Certificate Issuing Process
Proceedings
RC approved
- Hearing Objection
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Licence | 72 OF 2011(20-07-2019) |
|---|---|
| FAR permissible / proposed | 21019.34 / 175 |
| Estimated project cost | ₹ 196.17 Cr |
| Cost of land | ₹ 21.97 Cr |
| Cost of construction | ₹ 80.64 Cr |
| Infrastructure and other structures | ₹ 10.8 Cr |
| EDC, taxes, levies and other costs | ₹ 82.76 Cr |
How the land will be used
| Use | Area (as filed) | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 4,691.42 | 39.1% |
| Construction Of Roads | 1,007.79 | 8.4% |
| Pavements | 3,435.3 | 28.6% |
| Parks And Playgrounds | 41.85 | 0.3% |
| Green Belts | 1,688.89 | 14.1% |
| Vehicle Parkings | 887.5 | 7.4% |
| Any Other | 258.3 | 2.2% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HSVP | No |
| Water Supply | HSVP | No |
| Electricity | DHBVN | No |
| Sewage Disposal | HSVP | No |
| Storm Water Drainage | HUDA | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 50 lakh | Yet To Be Prepared |
| Water Supply System | ₹ 2 Cr | Yet To Be Prepared |
| Storm Water Drainage | ₹ 50 lakh | Yet To Be Prepared |
| Electricity Supply System | ₹ 4 Cr | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 40 lakh | Yet To Be Prepared |
| Street Lighting | ₹ 40 lakh | Yet To Be Prepared |
| Security And Fire Fighting | ₹ 2.5 Cr | Yet To Be Prepared |
| Any Other | ₹ 50 lakh | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Zonning | Already Been Obtained | 22 Jul 2011 |
| Environmental Clearance | Already Been Obtained | 28 May 2013 |
| Aravali Clearance Through Dc | Already Been Obtained | 30 Jan 2013 |
| Forest Clreance | Already Been Obtained | 9 Aug 2011 |
| Electricity Assurance For Operational Phase | Already Been Obtained | 17 May 2013 |
| Consent To Establish For Pollution | Already Been Obtained | 24 Jul 2016 |
| Sanction Of Fire Plan | Already Been Obtained | 3 Sep 2012 |
| Clearance From Mining Departments | Already Been Obtained | 31 Jan 2012 |
| Height Clearance(N.o.c) From-Aai | Already Been Obtained | 12 Jan 2012 |
| Sanction Of Building Plan | Already Been Obtained | 12 Jan 2012 |
| Service Estimate | Applied For But Yet To Receive | 11 May 2012 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Yes |
|---|---|
| Wall Finishing Details | Yes |
| Kitchen Details | N/A |
| Bathroom Fittings | N/A |
| Wood Work Etc | N/A |
| Doors And Windos Frames | Yes |
| Glass Work | Yes |
| Electric Fittings | Yes |
| Conducting And Wiring Details | Yes |
| Cupboard Details | N/A |
| Water Storage | N/A |
| Lift Details | Yes |
| External Glazings | Yes |
| Windows/Glazings | Yes |
| Doors | N/A |
| Main Doors | N/A |
| Internal Doors | N/A |
| Air Conditioning | Yes |
| Electrical Fittings | Yes |
| Cng Pipe Line | N/A |
| Provision Of Wifi And Broadband Facility | N/A |
| External Finishing/Colour Scheme | Yes |
| Internal Finishing | N/A |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about 114 Avenue?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.