RERA applied, not grantedHRERA Gurugram

The Hibiscus

by SS Group Private Limited · Sector 50

RERA registration
Applied, not granted yet
Applied on
17 Jan 2024
Application status
Return
Project ID
RERA-GRG-1534-2024
Land area
0.502 acres
Estimated cost
₹ 5.56 Cr

This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.

RERA registration

Registration certificateNot issued yet: the application is being processed by HRERA Gurugram
Project IDRERA-GRG-1534-2024
AuthorityHRERA Gurugram
Project type (as filed)Ongoing
Project nameThe Hibiscus
PromoterSS Group Private Limited
Promoter’s registered officeSS House, Plot No. 77, Sector 44, Gurugram, Haryana - 122003
CINU70109HR2010PTC048739
Site addressSector 50
SectorSector 50
Tehsil / DistrictGurgaon / Gurugram
Application submitted17 Jan 2024

Authority, hearings & orders

Current statusReturn
Initial scrutinyFirst hearing
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Hearing Examination By Authority View order
    Proceedings

    Ms. Prachi Singh (Planning Executive) briefed about the facts of the case. The application submitted by the promoter has been scrutinized by the concerned official, but the deficiency notice has not been dispatched till date. Therefore, in view of the same the matter is adjourned, and the concerned official is directed to dispatch the notice. The next date of hearing will be conveyed after submission of reply of deficiencies.

  1. Notice sent to the promoter Deficiency Notice
  2. Hearing Adjournment View order
    Proceedings

    Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Manoj Shukla (AR) and Sh. Sunil Shekhawat (AR) are present on behalf of the promoter. The AR of the promoter seeks an adjournment to rectify the deficiencies pointed out. A final opportunity of one month is granted to the promoter to rectify the deficiencies pointed out. The director/CEO/Project-Incharge of the promoter company is directed to be present on the next date of hearing.   The matter to come up on 20.05.2024. 

  3. Hearing Adjournment View order
    Proceedings

    Ms. Prachi Singh, Planning Executive briefed about the facts of the project. S/Shri Ashok Singh Jaunapuria, Manoj Shukla and Sunil Shekhawat are present on behalf of the promoter. AR of the company requests for three weeks’ time for completing the deficiencies.       Matter to come up on 10.6.2024. 

  1. Hearing Adjournment
    Proceedings

    Mr. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh.  Ashok Jaunapuria (AR), Manoj Shukla (AR) and Sh. Sunil Shekhawat (AR) are present on behalf of the promoter. The AR of the promoter states that the OC in respect of 13.185 acres was obtained in 2014 much before the commencement of Act, 2016 and OC in respect of only 0.2856 acres comprising of three villas, convenient shopping and swimming pool was obtained in 2019 and hence registration in respect of this area has been applied and remaining area is not part of ongoing project and hence no registration of this part is required. A representation is being submitted for its exemption which will be examined and if need be, opinion of the AG Haryana shall also be obtained. Matter to come up on 12.08.2024.

  2. Hearing Adjournment
    Proceedings

    Mr. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Sunil Shekhawat (AR) is present on behalf of the promoter. The reply of the applicant promoter has been received in the Authority and is under examination. The matter to come up on 16.09.2024.

  3. Hearing Adjournment
    Proceedings

    The matter is adjourned and to come up on 14.10.2024.

  1. Hearing Adjournment
    Proceedings

    The matter is adjourned and to come up on 25.11.2024.

  2. Hearing Adjournment View order
    Proceedings

    The matter is adjourned and to come up on 06.01.2025.

  3. Hearing Adjournment
    Proceedings

    Due to gazetted holiday, the matter is adjourned and to come up on 10.02.2025.

  1. Hearing Adjournment
    Proceedings

    The matter is adjourned and to come up on 11.02.2025 at 03:00 PM.

  2. Hearing Adjournment
    Proceedings

    The matter is adjourned and to come up on 17.03.2025.

  3. Hearing Adjournment
    Proceedings

    Mr. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Manoj Shukla (AR), Sh. Lovekush Sharma (AR) are present on behalf of the promoter. A show cause notice be issued to the promoter for rejection of the application for registration on account of not applying for the complete project as per earlier directions of the Authority and consequent non-deposit of the requisite fee for the area licensed by DTCP and imposition of penalty under section 59 of the Act, 2016. The office to issue a reminder to AG, Haryana within three days. The matter to come up on 28.04.2025. 

  1. Hearing Adjournment View order
    Proceedings

    Proceedings dated: 28.04.2025. Mr. Shashank Sharma, Associate Engineer Executive and Mr. Ashish Dubey, CA briefed about the facts of the project. Sh. Sunil Shekhawat (AR), Sh. Manoj Shukla (AR), Sh. Lovekush Sharma (AR) are present on behalf of the promoter and states that reply to the show cause notice will be submitted in the Authority within 2 days. The Authority has passed a detailed order dated 09.01.2023 in the complaint case no 6030 of 2019 case titled as SS Hibiscus Apartment Owner’s Association Vs SS group Pvt. Ltd. and hibiscus Maintenance Pvt. Ltd. In the detailed order it was clearly mentioned that the project i.e., “SS Hibiscus” falls within the definition of “Ongoing project” and thus requires registration under the Act and the rules and regulations made thereunder. It is also noted that, Completion certificate (CC) of the said project has not yet been obtained. In view of the above, Authority decides that one last opportunity is being given to the promoter to amend this present application within one week from 0.2856 acres to the complete licensed area i.e., 13.48 acres and submit all documents accordingly for the whole licensed area i.e., 13.48 acres failing which penalty amounting to Rs. 10 lakhs will be imposed on the promoter and further no opportunity shall be given. The matter to come up on 12.05.2025. 

  2. Hearing Adjournment
    Proceedings

    Mr. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Sunil Shekhawat (AR), Sh. Manoj Shukla (AR), Sh. Lovekush Sharma (AR) are present on behalf of the promoter and states that deficit documents with respect to the 0.2856 acres has been submitted and AG opinion regarding exemption for applying whole area is also pending, so the AR of the promoter requested to consider their application for applying whole area after AG reply. Keeping, in view of the above, the Authority decides that the promoter shall submit the remaining deficit documents including deficit fees within the period of 1 week. The matter to come up on 16.06.2025.

  3. Hearing Adjournment View order
    Proceedings

    The matter to come up on 23.06.2025

  1. Hearing Return View order
    Proceedings

    Mr. Shashank Sharma, Associate Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. The Authority passed a detailed order in the complaint case no 6030 of 2019, wherein it has been held that project requires registration for the whole area under the Act and the rules and regulations made thereunder as the CC for the said project had not been obtained so far. A Suo -motu proceedings were initiated against the promoter and a notice dated 12.04.2023 wherein the promoter was directed to apply for registration of the project and also to show cause as to why action u/s 59 of the Act, 2016 may not be initiated against the promoter for violation of the provisions of the Section 3 of the Act ibid. Consequently, hearings were held before the Authority from time to time as detailed in the proceedings above. Sh.  Ashok Jaunapuria (AR), Manoj Shukla (AR) & Sh. Sunil Shekhawat (AR) are present on behalf of the promoter and state that the OC in respect of 13.185 acres was obtained in 2014 much before the commencement of Act, 2016 and OC in respect of only 0.2856 acres comprising of three villas, convenient shopping and swimming pool was obtained in 2019. So, accordingly application for 0.2856 acres only was applied in the Authority for which OC has been obtained in 2019 which is after the enactment of RERA. Further, the order of the Authority is also under challenge before the Hon’ble HREAT in appeal no 261 of 2024. The AR further submits that now CC for the whole project has also been granted by DTCP vide memo no LC-452/JE(SK)/2025/22742 dated 17.06.2025 and the direction for applying registration of whole area may be exempted. A legal opinion was sought from AG, Haryana vide memo no PA/Secy/2024/254 dated 17.12.2024 along with a reminder vide memo no PA/Secy/HARERA/GGM/2025/35 dated 25.03.2025 against which reply is still awaited. The Authority observes that the application is pending for more than 1 year now and promoter has failed to apply for registration of the whole licensed area i.e., 13.48 acres despite of multiple opportunities granted. In view of the fact that the promoter has obtained the completion certificate for the entire project, the Authority considers it appropriate to finalize the proceedings. Since, the promoter has failed to abide by the directions of the Authority and apply for registration of entire ongoing project, it is held that the promoter is in violation of Section 3(1) of the Act of 2016 and is liable for penalty under the provisions of Section 59(1) of the Act ibid which provides for a penalty which may extend up to 10% of the cost of real estate project. However, under the peculiar circumstances of the case where the promoter has obtained the CC of the project, the Authority is of the view that a token penalty of Rs. 25 lakhs may be imposed upon the promoter under the said provision. The promoter is directed to deposit the said penalty amount in the Authority within a period of 60 days failing which further legal consequences would follow. Ordered accordingly. The present proceedings are closed, and application submitted by the promoter u/s 4 of the Act, 2016 is returned. The processing fee deposited by the promoter is forfeited.      

Land, licence & cost

Land area of the project0.502 acres
Total licensed area13.48 acres
Licence874 OF 2006 (24.06.2006), 875 OF 2006 (24.06.2006), 875 OF 2006 (24.06.2006), 875 OF 2006 (24.06.2006)
FAR permissible / proposed174.6 / 174.6
Estimated project cost₹ 5.56 Cr
Cost of land₹ 0.32 Cr
Cost of construction₹ 4.88 Cr
Infrastructure and other structures₹ 0.35 Cr
EDC, taxes, levies and other costs₹ 0.35 Cr

How the land will be used

UseArea (as filed)Share
Land Area To Be Used For Construction Of Apartments883.0276.4%
Any Other272.5623.6%

External services

ServiceProvided byApproval taken
RoadsGMDAYes
Water SupplyGMDAYes
ElectricityDHVNLYes
Sewage DisposalHSVPYes
Storm Water DrainageHSVPYes

Statutory approvals

ApprovalStatusDate
LicenceAlready Been Obtained

Specifications (as filed)

Flooring Details Of Various Parts Of HouseVitrified Tiles As Per Approved Make
Wall Finishing DetailsExternal- Texture Paint Internal- Oil Bound Distemper
Kitchen DetailsGlazed 600MM High Tiles Above Counterlevel & Balance Obd
Bathroom FittingsSingle Lever Cp Fittings Wash Basin, Wall Hanging Wc 9SUPER Quality)
Doors And Windos FramesSolid Hardwood / Upvc Frames
Electric FittingsModular Type
Conducting And Wiring DetailsPvc Conduiting With Copper Wiring
Water StorageCommon Rcc Over Head Water Tank
External GlazingsUpvc Frame With Plain Glass
Windows/GlazingsUpvc Frame With Plain Glass
DoorsSolid Flush Doors With Enamel Paint Shutters
Main DoorsSolid Decorative Flush Doors
Internal DoorsSolid Flush Doors With Enamel Paint Shutters
Air ConditioningSplit Air Conditioner
Electrical FittingsModuler Type
External Finishing/Colour SchemeTexture Paint
Internal FinishingAcrylic Emulsion Paint

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about The Hibiscus?

This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.