315, 3RD Floor, Time Tower, Mg Road, Gurugram, Haryana 122002
CIN
U70109DL2006PTC150938
Site address
Sector-68
Sector
Sector 68
Tehsil / District
Gurgaon / Gurugram
Layout plan approved
6 Nov 2024
Construction start (as filed)
1 Feb 2025
Completion (as filed)
30 Sep 2029
Application submitted
29 Jan 2025
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
Application submitted online
Notice sent to the promoterDispatched
HearingExamination By AuthorityView order Proceedings
The matter is adjourned and to come up on 03.03.2025.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ar. Neeraj Gautam, Associate Architectural Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Deepak Sethi (AR), Sh. Vivek Lohani (AR), Sh. Sharad Tiwari (AR) and Ms. Monica Chugh (AR) ae present on behalf of the promoter and states that the present application pertains to new license no. 138 of 2024 dated 05.11.2024 which is granted by DTCP after migration of area measuring 4.1125 acres from license no. 150 of 2022 dated 28.09.2022 and area measuring 0.1688 acres from license no. 17 of 2010 dated 13.02.2010 along with fresh area measuring 1.9688 acres. The promoter states that no building plan has been obtained till date with respect to respect to license no. 150 of 2022, and therefore the promoter neither applied for RERA registration and nor advertised, marketed, booked, sold or offered to sale in any manner any area proposed to be developed under the said license. It is further stated by the promoter that the license no. 17 of 2010 dated 13.02.2010, was granted for an area measuring 6.26 acres. The project under the said license was developed in two parts, one office complex and the other retail complex. The OC of the office area was issued by DTCP vide memo no. ZP-603/SD(BS)/2017/18007 dated 27.07.2017 which is prior to the commencement of Haryana Real Estate (Regulation and Development) Rules, 2017. Further, the OC of retail complex is issued by DTCP vide memo no. ZP-603-Vol-II/SD(DK)/2019/19762 dated 16.08.2019 which is after the commencement of Rules of 2017. The AR of the promoter further states that no third-party rights have been created in the retail area and the same is for self-occupancy and is on lease model. No sale is proposed in the retail area of the project area and hence no registration is required in terms of clarification issued by HRERA vide its memo no. HRERA/RD/2017/35/1049 dated 15.09.2017 wherein it is clarified that a promoter may register his licensed (unlaunched) projects any time in future before he intends to advertise, market, book, sell or offer to sale, or invite persons to purchase in any manner any plot, apartment or building, as the case may be, in any real estate project or part of it, in the planning area.. The promoter has submitted the consent of 22 allottees out of 33 unique allottees in the office complex falling in license no. 17 of 2010 dated 13.02.2010 in the Authority. A public notice inviting objections with respect to the consents submitted and the above claims made by the promoter were published in The Tribune (English), The Hindu (English) and Dainik Jagran (Hindi) and no objection is received in the Authority. The registration of the project namely “Reach The Bazaria” under section 4 of Real Estate (Regulation and Development), Act 2016 applied for registration vide application dated 29.01.2025 is approved as proposed subject to submission of approved service plans and compliance of the other minor deficiencies. The registration certificate shall be issued after rectifications in form REP-I, DPI and other deficiencies listed above at S. No. 21.
Registration grantedGGM/923/655/2025/26
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
6.25 acres
Total licensed area
6.25 acres
Licence
138 of 2024 Dated 05/11/2024
FAR permissible / proposed
1.5 / 1.4946
Estimated project cost
₹ 183.02 Cr
Cost of land
₹ 72.59 Cr
Infrastructure and other structures
₹ 33.18 Cr
EDC, taxes, levies and other costs
₹ 77.24 Cr
How the land will be used
Use
Sq m
Share
Plots To Be Sold
8,822.27
34.9%
Construction Of Roads
7,099.01
28.1%
Pavements
6,173.212
24.4%
Parks And Playgrounds
1,978.95
7.8%
Vehicle Parkings
725
2.9%
Electricity Sub-Station
300
1.2%
Sewage And Solid Waste Treatment Facility
194.37
0.8%
Plots 58 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
85.93
103
925
2
97.50
117
1,049
7
109.38
131
1,177
3
126.88
152
1,366
1
131.25
157
1,413
8
149.50
179
1,609
8
153.03
183
1,647
1
162.50
194
1,749
7
169.00
202
1,819
13
174.30
208
1,876
1
178.50
213
1,921
1
184.00
220
1,981
1
223.08
267
2,401
1
253.50
303
2,729
2
256.25
306
2,758
2
External services
Service
Provided by
Approval taken
Roads
ALREADY CONNECTED
Yes
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 4.43 Cr
As Per Project Report
Water Supply System
₹ 1.29 Cr
As Per Project Report
Storm Water Drainage
₹ 1.99 Cr
As Per Project Report
Electricity Supply System
₹ 5.58 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 1.05 Cr
As Per Project Report
Street Lighting
₹ 61.71 lakh
As Per Project Report
Security And Fire Fighting
₹ 50.3 lakh
As Per Project Report
Playgrounds And Parks
₹ 1.78 Cr
As Per Project Report
Cost Of Construction Boundary Wall And Front Entry Point
₹ 88.7 lakh
As Per Project Report
Parking Open
₹ 11.4 lakh
As Per Project Report
Stp
₹ 34.98 lakh
As Per Project Report
Underground Water Tank
₹ 34.98 lakh
As Per Project Report
Electrical Sub Station
₹ 3.36 Cr
As Per Project Report
Site Establishment And Infrastructure Cost
₹ 10.88 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
5 Nov 2024
Layout Plan
Already Been Obtained
6 Nov 2024
Assurance Of Storm Water
Already Been Obtained
19 Nov 2024
Assurance Of Water Supply For Construction Purpose
Already Been Obtained
18 Nov 2024
Assurance For Water Supply Of Drinking Water
Already Been Obtained
21 Nov 2024
Electrical Load
Already Been Obtained
22 Nov 2024
Assurance Of Sewerage Connection
Already Been Obtained
18 Nov 2024
Forest Noc
Already Been Obtained
9 Sep 2024
Architect Control Sheet
Already Been Obtained
28 Jan 2025
Service Estimates Plan
Already Been Obtained
3 Mar 2025
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Reach The Bazaria?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.