Registration period overHRERA GurugramOC / CC on record

Emaar Business District (Ebd-89)

by Emaar India Limited · Village - Badha, Sector-89, Gurugram

RERA registration
GGM/507/239/2021/75
Registered on
9 Nov 2021
Valid till
17 Aug 2026
Project ID
RERA-GRG-901-2021
Land area
3.706 acres
Plots
52
Completion (as filed)
17 Aug 2026
Estimated cost
₹ 72.89 Cr

RERA registration

Registration certificateGGM/507/239/2021/75, dated 9 Nov 2021
Registration valid till17 Aug 2026
Project IDRERA-GRG-901-2021
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameEmaar Business District (Ebd-89)
PromoterEmaar India Limited
Promoter’s registered officeEmaar Business Park, Sikanderpur Sector-28, Gurugram, Haryana - 122001
CINU45201DL2005PLC133161
Site addressVillage - Badha, Sector-89, Gurugram
SectorSector 89
Tehsil / DistrictManesar / Gurugram
Construction start (as filed)1 Nov 2021
Completion (as filed)17 Aug 2026
Application submitted31 Aug 2021

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyThe hearing is fixed for 14.09.2021.
Next hearingNot Required
  1. Application submitted online
  2. Notice sent to the promoter By Hand
  3. Hearing Examination By Authority View order
    Proceedings

    Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Rohit Mehta (GM Govt. Affairs) and Sh. Anitesh Singh (Dy. Manager) are present on behalf of the promoter. The promoter M/s Emaar India Ltd. who is a Collaborator applied for the registration of real estate project namely “Emaar Business District- 89” located at Sector-89, Gurugram under section 4 of the Real Estate (Regulations and Development) Act, 2016 vide central receipt no. 11522/22744 dated 31.08.2021 and RPIN-368. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-901-2021. The project area for registration is same as that of the licensed area i.e. 3.70625 acres. License no – 52 of 2021 dated 18.08.2021. The application for registration was scrutinized and 1st deficiency notice vide notice no. HARERA/GGM/RPIN/368 dated 03.09.2021 was issued to the promoter with an opportunity of being heard on 14.09.2021. The promoter submitted a reply dated 09.09.2021, after scrutiny of the reply some of the deficiencies are remaining which are mentioned below: 1.    The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. 2.    Approved Service Plan and Estimates needs to be submitted. If applied than copy of applied needs to be submitted. 3.    Quarterly schedule physical progress of infrastructure and services needs to be filled in DPI. 4.    Demarcation plan, zoning plan and architectural control sheet needs to be submitted. 5.    Draft Allotment letter is not as per the prescribed format. 6.    Draft Builder Buyer Agreement is not as per the prescribed format. 7.    CA certificate for promoter equity and CA certificate for expenditure incurred upto the date of application needs to be revised.  The matter to come up on 21.09.2021.Samir Kumar (Member)Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman)

  1. Hearing Adjournment View order
    Proceedings

    Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Rohit Mehta (GM Govt. Affairs) and Sh. Anitesh Singh (Dy. Manager) are present on behalf of the promoter. The promoter M/s Emaar India Ltd. who is a Collaborator applied for the registration of real estate project namely “Emaar Business District- 89” located at Sector-89, Gurugram under section 4 of the Real Estate (Regulations and Development) Act, 2016 vide central receipt no. 11522/22744 dated 31.08.2021 and RPIN-368. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-901-2021. The project area for registration is same as that of the licensed area i.e. 3.70625 acres. License no – 52 of 2021 dated 18.08.2021. The application for registration was scrutinized and 1st deficiency notice vide notice no. HARERA/GGM/RPIN/368 dated 03.09.2021 was issued to the promoter with an opportunity of being heard on 14.09.2021. The promoter submitted a reply dated 09.09.2021, after scrutiny of the reply deficiencies were conveyed to the promoter. On 14.09.2021, On the request of the promoter the matter was adjourned for 21.09.2021. The promoter submitted a reply dated 20.09.2021, after scrutiny of the reply the remaining deficiencies are mentioned below: The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. Approved Service Plan and Estimates needs to be submitted. Quarterly schedule physical progress of infrastructure and services needs to be filled in DPI. Demarcation plan, zoning plan and architectural control sheet needs to be submitted. The promoter requested for one week time and the authority grants the same and matter is adjourned for 27.09.2021.Samir Kumar (Member)Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman)

  2. Hearing Adjournment View order
    Proceedings

    Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Rohit Mehta (GM Govt. Affairs) and Sh. Anitesh Singh (Dy. Manager) are present on behalf of the promoter. The promoter M/s Emaar India Ltd. who is a Collaborator applied for the registration of real estate project namely “Emaar Business District- 89” located at Sector-89, Gurugram under section 4 of the Real Estate (Regulations and Development) Act, 2016 vide central receipt no. 11522/22744 dated 31.08.2021 and RPIN-368. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-901-2021. The project area for registration is same as that of the licensed area i.e. 3.70625 acres. License no – 52 of 2021 dated 18.08.2021. The application for registration was scrutinized and 1st deficiency notice vide notice no. HARERA/GGM/RPIN/368 dated 03.09.2021 was issued to the promoter with an opportunity of being heard on 14.09.2021. The promoter submitted a reply dated 09.09.2021, after scrutiny of the reply deficiencies were conveyed to the promoter. On 14.09.2021, On the request of the promoter the matter was adjourned for 21.09.2021. The promoter submitted a reply dated 20.09.2021, after scrutiny of the reply the remaining deficiencies were conveyed to the promoter. On 21.09.2021, the promoter requested for one week time and the authority grants the same and matter is adjourned for 27.09.2021. The promoter submitted a reply on 22.09.2021, after scrutiny of the reply the remaining deficiencies are mentioned below: The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. Approved Service Plan and Estimates needs to be submitted. Demarcation plan, zoning plan and architectural control sheet needs to be submitted. The authority directed the promoter to remove the above mentioned deficiencies. The matter to come up on 04.10.2021.Samir Kumar (Member)Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman)

  3. Hearing Adjournment View order
    Proceedings

    Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Rohit Mehta (GM Govt. Affairs) and Sh. Anitesh Singh (Dy. Manager) are present on behalf of the promoter. The promoter M/s Emaar India Ltd. who is a Collaborator applied for the registration of real estate project namely “Emaar Business District- 89” located at Sector-89, Gurugram under section 4 of the Real Estate (Regulations and Development) Act, 2016 vide central receipt no. 11522/22744 dated 31.08.2021 and RPIN-368. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-901-2021. The project area for registration is same as that of the licensed area i.e. 3.70625 acres. License no – 52 of 2021 dated 18.08.2021. The application for registration was scrutinized and 1st deficiency notice vide notice no. HARERA/GGM/RPIN/368 dated 03.09.2021 was issued to the promoter with an opportunity of being heard on 14.09.2021. The promoter submitted a reply dated 09.09.2021, after scrutiny of the reply deficiencies were conveyed to the promoter. On 14.09.2021, On the request of the promoter the matter was adjourned for 21.09.2021. The promoter submitted a reply dated 20.09.2021, after scrutiny of the reply the remaining deficiencies were conveyed to the promoter. On 21.09.2021, the promoter requested for one week time and the authority grants the same and matter is adjourned for 27.09.2021. The promoter submitted a reply on 22.09.2021, after scrutiny of the reply the remaining deficiencies are mentioned below: The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. Approved Service Plan and Estimates needs to be submitted. Demarcation plan, zoning plan and architectural control sheet needs to be submitted. On 27.09.2021, The authority directed the promoter to remove the above mentioned deficiencies. The matter to come up on 04.10.2021. The above deficiencies still have not been rectified. The matter to come up on 19.10.2021.Samir Kumar (Member)Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman)

  1. Hearing Adjournment View order
    Proceedings

    Sh. Ashish Kush, Planning Executive briefed about the facts of the project. Sh. Rohit Mehta (GM Govt. Affairs) and Sh. Naveen Naudiyal (DM Govt. Affairs) are present on behalf of the promoter. The hard copy of online DPI has not submitted by promoter. The AR is advised to submit an undertaking that the timelines of one month for submission of architectural control sheet and 3 months for submission of service plan and estimates from grant of RC shall be strictly followed failing which the Authority will be at liberty to forfeit the Bank Guarantee. The matter to come up on 09.11.2021.Samir Kumar (Member)Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman)

  2. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Sh. Ashish Kush, Planning Executive, Planning Branch briefed the facts about the project. Sh. Rohit Mehta (General Manager) and Sh. Anitesh Singh (Dy. Manager) are present on behalf of the promoter. The promoter submitted the Bank guarantee of Rs 25 lac for Architectural Control Sheet and Rs 50 lac for the approved service plan and estimates on 13.10.2021. As per proceedings dated 19.10.2021, the promoter also submitted an undertaking that failing the timelines of one month for submission of architectural control sheet and 3 months for submission of service plan and estimates from grant of RC the authority may encash the bank guarantee. The authority decides to grant the registration certificate subject to the corrections in online DPI. Further, a condition shall be imposed that no withdrawal of any amount shall be allowed till submission of above documents. Any sale made on the basis of draft architectural control sheet and service plan estimates shall be subject to final approved architectural control sheet and service plans and estimates. In case of failure to submit the approved Demarcation plan, Architectural Control Sheet within one month from the date of issuance of registration certificate and Service estimates and plans within three months from the date of issuance of registration certificate, then the amount collected from the allottees is liable to be refunded with interest at the prescribed rate and the registration certificate shall be treated as deemed cancelled.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman)

  3. Registration granted GGM/507/239/2021/75
  1. Certificate uploaded RC Approved and Certificate Uploaded
  2. Registration valid till

Land, licence & cost

Land area of the project3.706 acres
Total licensed area3.706 acres
Licence52 of 2021 dated 18.08.2021
FAR permissible / proposed1.5 / 1.5
Estimated project cost₹ 72.89 Cr
Cost of land₹ 15.51 Cr
Infrastructure and other structures₹ 20.92 Cr
EDC, taxes, levies and other costs₹ 36.47 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments1.296735%
Construction Of Roads1.499740.5%
Parks And Playgrounds0.418811.3%
Vehicle Parkings0.401610.8%
Electricity Sub-Station0.06141.7%
Area To Be Left For Transferring To The Government For Community Services0.01880.5%
Toilet0.00930.3%

Plots 52 plots

Plot size (sq m)Sq ydSq ftPlots
86.521039311
106.871281,1501
168.002011,8081
169.822031,8281
175.002091,8841
179.992151,9371
420.005024,5215
588.007036,3297
648.007756,9756
672.008047,2338
840.001,0059,04210
1,180.201,41212,70410

External services

ServiceProvided byApproval taken
RoadsALREADY CONNECTEDYes
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 1.37 CrAs Per Project Report
Water Supply System₹ 59.67 lakhAs Per Project Report
Storm Water Drainage₹ 54.19 lakhAs Per Project Report
Electricity Supply System₹ 1.08 CrAs Per Project Report
Street Lighting₹ 22.77 lakhAs Per Project Report
Security And Fire Fighting₹ 3.5 lakhAs Per Project Report
Playgrounds And Parks₹ 2.63 CrAs Per Project Report
Stp₹ 88.88 lakhAs Per Project Report
Parking₹ 19.83 lakhAs Per Project Report
Sewerage₹ 30.63 lakhAs Per Project Report
Ugt₹ 68.82 lakhAs Per Project Report
Rain Water Harvesting₹ 6.55 lakhAs Per Project Report
Electrical Substation Ancillary Building₹ 50.11 lakhAs Per Project Report
Electrical Panels₹ 1.49 CrAs Per Project Report
Signages Plot Demarcation₹ 15.2 lakhAs Per Project Report
Miscellaneous Works₹ 31.31 lakhAs Per Project Report
Switching Station Works₹ 5.99 CrAs Per Project Report
Other Costs₹ 3.85 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
License ApprovalAlready Been Obtained18 Aug 2021
Layout Plan ApprovalAlready Been Obtained18 Aug 2021
Water Supply Sewerage Storm ApprovalAlready Been Obtained17 Aug 2021
Zoning Plan ApprovalApplied For But Yet To Receive7 Jul 2021

Specifications (as filed)

Flooring Details Of Various Parts Of HouseNot Applicable
Wall Finishing DetailsNot Applicable
Kitchen DetailsNot Applicable
Bathroom FittingsNot Applicable
Wood Work EtcNot Applicable
Doors And Windos FramesNot Applicable
Glass WorkNot Applicable
Electric FittingsNot Applicable
Conducting And Wiring DetailsNot Applicable
Cupboard DetailsNot Applicable
Water StorageNot Applicable
Lift DetailsNot Applicable
External GlazingsNot Applicable
Windows/GlazingsNot Applicable
DoorsNot Applicable
Main DoorsNot Applicable
Internal DoorsNot Applicable
Air ConditioningNot Applicable
Electrical FittingsNot Applicable
Cng Pipe LineNot Applicable
Provision Of Wifi And Broadband FacilityNot Applicable
External Finishing/Colour SchemeNot Applicable
Internal FinishingNot Applicable

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Emaar Business District (Ebd-89)?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.