Registration validHRERA Gurugram

ATS Grandstand Phase-2

by Homekraft Infra Private Limited · Sector 99A, Gurugram

RERA registration
GGM/1082/818/2026/54
Registered on
17 Aug 2026
Valid till
31 Mar 2031
Project ID
RERA-GRG-2297-2026
Land area
3.568 acres
Apartments
362 in 3 towers
Completion (as filed)
30 Jun 2031
Estimated cost
₹ 927.73 Cr

RERA registration

Registration certificateGGM/1082/818/2026/54, dated 17 Aug 2026
Registration valid till31 Mar 2031
Project IDRERA-GRG-2297-2026
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameATS Grandstand Phase-2
PromoterHomekraft Infra Private Limited
Promoter’s registered officeOcus Medley, 16TH Floor, ATS Homekraft Sector 99, Gurugram, Haryana 122001
CINU70200DL2017PTC314287
Site addressSector 99A, Gurugram
SectorSector 99A
Tehsil / DistrictGurgaon / Gurugram
Building plans approved10 Jul 2026
Construction start (as filed)1 Jul 2026
Completion (as filed)30 Jun 2031
Application submitted16 Jul 2026

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyFirst Hearing
Next hearingNot Required
  1. Application submitted online
  2. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Ms. Nikita Mittal, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Rajeev Kumar Gupta (Sr. V.P.), Sh. Yogesh Sharma (A.G.M), Sh. Ramniwas Saini (Architect), Sh. Bhavishya Mahajan (Manager) and Sh. Narendra Kumar (Manager) are present on behalf of the promoter. The Authorized Representative of the promoter submitted that DTCP Haryana had granted License No. 37 of 2013 dated 03.06.2013 for development of a Group Housing Colony over an area measuring 11.5875 acres. Subsequently, the phasing plan for the said project was approved vide Memo No. ZP-938-II/SD(RD)/2026/26027 dated 22.07.2026. Pursuant to the approval of the phasing plan, the promoter has applied for registration of Phase-2 under Section 4 of the Real Estate (Regulation and Development) Act, 2016, comprising an area measuring 3.5680 acres which consists of residential towers 4, 5, 6, 7 and 10. Further, the AR of the promoter states that no late fee be levied since although the license existed earlier, the project was never launched, and no construction activity had commenced. It was also submitted that no advertisement, booking, allotment, agreement for sale or creation of any third-party rights had taken place in respect of the project. Further states that the revised Environment clearance approval, revised approved Fire Scheme, revised approved service plans and estimates and mining permission are under process, and the said approvals have not yet been obtained as on date. Further, the Authorized Representative of the promoter undertakes to obtain and submit: i.         Revised Environment clearance approval within 6 months from the date of grant of registration; ii.       Revised Fire Scheme approval within 6 months from the date of grant of registration; iii.     Revised Approved Service Plans & Estimates within 6 months from the date of grant of registration; and iv.     Mining permission before commencement of construction activities at the project site.   Further, he undertakes to submit the three separate Demand Drafts amounting to Rs. 25 lakhs each, as a security deposit for timely compliance with the above requirements at point (i). It is also expressly undertaken that in the event of failure to obtain and submit the aforesaid approval within the stipulated time frames, the corresponding security amount shall be liable to be forfeited by the Authority. The Authority has taken note of the submissions made by the AR of the promoter regarding the non-availability of the aforesaid statutory approvals as on date. In view of the above, and in the interest of regulatory compliance, the Authority hereby directs that the promoter shall submit the two separate Demand Drafts amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only) each, in favour of the Authority as security amounts for timely submission of revised Environment clearance approval, revised approved Fire Scheme, revised approved service plans and estimates within 6 months from the date of grant of registration. In the event of non-submission of the above approvals within the prescribed time frames, the corresponding security amount shall stand forfeited by the Authority, and such failure may also attract additional regulatory action as permissible under the Act of 2016, rules and regulations made thereunder. Further, the promoter shall submit mining permission before commencement of construction activities at the project site. With respect to the concern regarding late fee, the opinion taken from Ld. AG, Haryana by the Authority in respect of Group Housing Colony namely “GH 63” located at Sector-63, Gurugram regarding the ongoing project and applicability of late fee wherein it is mentioned that it is not possible to say that as on 01.05.2017, promoter was in a position to start development of project because the building plans were not prepared what to talk of sanctioned. Equally speaking, even without requisite permissions as provided in section 4(2) of Act of 2016, the authority was not in a position to grant registration. However, in the present matter, since the building plans of the entire licensed colony had originally been approved on 26.05.2014 and revised building plans were subsequently approved vide Memo No. ZP-938-II/SD(RD)/2026/24449 dated 10.07.2026, and the promoter was in the position to commence the construction/development of the project on site, therefore, the project shall be considered as an ongoing project for the purpose of applicability of late fee. Regarding the levy of late fee in the said project, the Authority observes that the earlier building plans for the said phase were approved on 26.05.2014 which covers an area of 81,425.15 sq.m. Out of this area, Phase-I, admeasuring 28,923.29 sq. m., had already been registered with the Authority vide RC No. 06 of 2018 dated 02.01.2018. Accordingly, for the purpose of levy of late fee, the unregistered area covered under the earlier approved building plans is required to be taken into consideration. Thus, the late fee is liable to be calculated on the balance area of 52,501.86 sq.m as mentioned at S. No. 30. Approved as proposed subject to rectification of deficiencies mentioned above at S.no. 35. The Registration Certificate shall be issued after submission of the remaining deficiencies mentioned above at S.no. 35 including correction in Form A–H, online DPI, deficit fee and submission of three separate Demand Drafts of Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only) each for submission of revised Environment clearance approval, revised approved Fire Scheme, revised approved service plans and estimates within the time frame mentioned above, along with the deficiencies mentioned at S. No. 35.

  3. Registration granted GGM/1082/818/2026/54
  1. Certificate uploaded Project Registration certificate uploaded
  2. Registration valid till

Land, licence & cost

Land area of the project3.568 acres
Total licensed area11.588 acres
Licence37 of 2013 Dated 03.06.2013
FAR permissible / proposed3.4 / 3.4
Estimated project cost₹ 927.73 Cr
Cost of land₹ 327.41 Cr
Cost of construction₹ 292.11 Cr
Infrastructure and other structures₹ 31.79 Cr
EDC, taxes, levies and other costs₹ 276.42 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments0.59516.7%
Construction Of Roads0.7621.3%
Parks And Playgrounds1.24234.8%
Vehicle Parkings0.174.8%
Rwh0.0270.8%
Ess0.143.9%
Openarea0.63417.8%

Apartments 362 units · 3 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings151.801,6344
Apartment/Shops/Other Buildings151.801,634142
Apartment/Shops/Other Buildings112.041,2066
Apartment/Shops/Other Buildings112.041,206210

Areas are as filed with HRERA.

External services

ServiceProvided byApproval taken
RoadsALREADY CONNECTEDYes
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 1.47 CrAs Per Project Report
Water Supply System₹ 6.5 CrAs Per Project Report
Storm Water Drainage₹ 1.95 CrAs Per Project Report
Electricity Supply System₹ 5.98 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 1.85 CrAs Per Project Report
Street Lighting₹ 25 lakhAs Per Project Report
Security And Fire Fighting₹ 6.12 CrAs Per Project Report
Playgrounds And Parks₹ 15.11 lakhAs Per Project Report
Renewable Energy System₹ 1.23 CrAs Per Project Report
Stp₹ 1.25 CrAs Per Project Report
Underground Water Tank₹ 2.86 CrAs Per Project Report
Rain Water Harvesting₹ 83.25 lakhAs Per Project Report
Electrical Sub Station₹ 1.35 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
Phasing Plan LetterAlready Been Obtained22 Jul 2026
CodAlready Been Obtained19 Jun 2026
Assurance For Water SupplyAlready Been Obtained7 Jan 2026
Assurance Of Sewerage ConnectionAlready Been Obtained9 Jan 2026
Assurance Of Storm WaterAlready Been Obtained8 Jan 2026
Br-IIIAlready Been Obtained10 Jul 2026
Forest NocAlready Been Obtained20 Dec 2013
HUDA ConstructionAlready Been Obtained12 Aug 2026
AaiAlready Been Obtained24 Jul 2019
LicenseAlready Been Obtained3 Jun 2013
EcApplied For But Yet To Receive19 May 2026
Fire Scheme ApprovalApplied For But Yet To Receive13 Jul 2026
Electrical LoadApplied For But Yet To Receive17 Jul 2026
Service Plan Estimate ApprovalApplied For But Yet To Receive14 Jul 2026

Specifications (as filed)

Flooring Details Of Various Parts Of HouseVitrified Tiles Flooring, Wooden Flooring, Ceramic Tiles, Anti-Skid Ceramic Flooring
Wall Finishing DetailsGlazed Tiles (450MM X 600MM)/ (300MM X 450MM)
Kitchen DetailsWall Tiles 600MM Height Above Kitchen Counter Slab In Appropriate Colour & Paint."Upvc Sections Profile-Openable ΤΥΡΕ 6ΜΜ ΤΗK. Clear Float Glass"
Bathroom FittingsCeramic Tiles, Glazed Tiles Upto 2400MM And Oil Bound Distemper Of Appropriate Colour Above IT Upto Ceiling, Flush/Skin Doors-Polished
Doors And Windos FramesUpvc Door/Window, Flush/Skin Doors-Polished, Engineered Door With Polished Wood Veneer
Electric FittingsHeavy Duty Conduit (2.0MM Thick) For Slab, Medium Duty Conduit For Wall - Isi Marked, Confirming To Is Codes, Modular Type Switch/Sockets For Flats
Conducting And Wiring DetailsAll Electrical Wiring In Concealed Conduits
Lift Details"(1) Flats:-04 Units/Floor (Bc-Type); 02 Units/Floor (A-Type) (2) Total No Of Lift: Towers-10"
External GlazingsAppropriate Finish Of Texture Paint Of Exterior Grade Water Proof Paint.
Windows/Glazings"Upvc Sections Profile-Three Track System 6MM Thk. Clear Float Glass Handle : Casement Type"
DoorsEngineered Door Eith Polished Wood Veneer, All Internal Doors Area Flush/Skin Doors-Laminated
Main DoorsEngineered Door With Polished Wood Veneer
Internal DoorsAll Internal Doors Are Flush/Skin Doors-Laminated
Electrical FittingsProvision For Adequate Light & Power Points. Telephone & T.v. Outlets In Drawing, Dining And All Bedroom: Moulded Modular Plastic Switches & Protective Mcb's
Provision Of Wifi And Broadband FacilityYes
External Finishing/Colour SchemeAppropriate Finish Of Texture Paint Of Exterior Grade Water Proof Paint
Internal FinishingOil Bound Distemper Of Appropriate Colour On Interior Walls

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about ATS Grandstand Phase-2?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.