Aradhya Extension
by Sky Space Developers Private Limited · Ansal Versalia, Sector-67A
- RERA registration
- Applied, not granted yet
- Applied on
- 15 Dec 2021
- Application status
- Rejected
- Project ID
- RERA-GRG-983-2021
- Land area
- 6.319 acres
- Apartments
- 84 in 21 towers
- Plots
- 21
- Completion (as filed)
- 30 Jun 2024
- Estimated cost
- ₹ 95.66 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Gurugram |
|---|---|
| Project ID | RERA-GRG-983-2021 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Aradhya Extension |
| Promoter | Sky Space Developers Private Limited |
| Promoter’s registered office | Plot No. D-17, Basement, South City-II, Sector-49 Gurgaon-122018 |
| CIN | U70100HR2019PTC081867 |
| Site address | Ansal Versalia, Sector-67A |
| Sector | Sector 67A |
| Tehsil / District | Badshahpur St / Gurugram |
| Construction start (as filed) | 1 Aug 2021 |
| Completion (as filed) | 30 Jun 2024 |
| Application submitted | 15 Dec 2021 |
Authority, hearings & orders
- Application submitted online
- Notice sent to the promoter 1st deficiency notice
-
Hearing
Examination By Authority
Proceedings
The matter is adjourned to 19.01.2022.
-
Hearing
Adjournment View order
Proceedings
Ms. Prachi Singh, Planning Executive briefed the facts about the project. No one is present on behalf of the promoter. The promoter has requested for adjournment of hearing vide letter dated 19.01.2022 requesting for some time for removing the deficiencies as the working of the office is affect by the covid-19 situation and is closed for 6-7 days. Therefore, the authority has decided to grant 10 days’ time to fulfill the deficiencies and matter to come up on 07.02.2022.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 07.02.2022 Ms. Prachi Singh, Planning Executive briefed about the facts of the case. None is present on behalf of the promoter and neither reply to the deficiencies already conveyed vide letter dated 05.01.2022 have been submitted. The promoter may be issued show cause notice as to why the application for registration should not be rejected for non-rectification of the deficiencies and non-submission of deficit documents already conveyed vide letter dated 05.01.2022.
-
Hearing
Adjournment View order
Proceedings
Ms. Prachi Singh Planning Executive briefed about the case.None is present on behalf of the promoterAn application regarding registration of residential floors projects namely “Aradhya Extension” situated at sector-67A,Gurugram, Haryana being developed by M/s Sky Space Developers Private Limited was submitted on 15.12.2021under section 4 of Real Estate (Regulation and Development), Act 2016. The applicant promoter M/s Sky SpaceDevelopers Private Limited has purchased the 21 plots from M/s New Look Builders and Developers Private Limited(formerly known as Ansal Phalak Infrastructure Private Limited) vide different sale deeds executed on different datesannexed as annexure A.The application submitted by the promoter for the said project contains 21 residential plots on which total of 84 unitsare to be constructed. On scrutiny of the application, some of the deficiencies and observations were observed whichwere conveyed to the promoter vide notice no. HARERA/GGM/RPIN/404 dated 05.01.2022. Neither the promoterappeared in the hearing nor submitted the reply. Further, the authority issued a show cause notice dated 08.04.2022for rejection of the project under section 5 (1)(b) of the Real Estate (Regulation and Development) Act, 2016 and Rule-5(2) of Haryana Real Estate (Regulation and Development) Rules, 2017. No reply has been received in the authority tilldate.One last opportunity is being granted to rectify the deficiencies and for submission of the response.The matter to come up on 06.06.2022.
-
Hearing
Adjournment View order
Proceedings
None is present on behalf of the promoter. It is understood that the sale of floors is being made without registration of the project and the promoter has failed to rectify the deficiencies even after giving four opportunities. One last opportunity for rectification of deficiencies be given to the applicant failing which public notice is to be issued that the project is not registered, and public is cautioned not to purchase any unit in this project till the registration is obtained from the authority. The matter to come up on 13.06.2022.
-
Hearing
Adjournment View order
Proceedings
Coram is incomplete. The matter is adjourned to 27.06.2022.
-
Hearing
Adjournment View order
Proceedings
Ms. Prachi Singh Planning Executive briefed about the case.Sh. Narayan Bhadana (Director) and Sh. Amit Sharma ( Legal) are present on behalf of thepromoter and the reply after compliance of the deficiencies conveyed vide letter dated 05.01.2022has been submitted today in the registry of the Authority and the same be checked by theconcerned Planning Executive. Further the promoter is required to submit the pending QPRs andannual audit report in respect of the existing registered project before the new project isconsidered for registration. Two weeks time is given for making compulsory compliance.
-
Hearing
Adjournment View order
Proceedings
Due to the administrative work of the authority, the matter is adjourned for 27.07.2022.
-
Hearing
Adjournment View order
Proceedings
Ms. Prachi Singh, Planning Executive briefed about the case.Sh. Narayan Bhadana (Director) and Sh. Amit Sharma (Legal) are present on behalf of the promoter.The AR requests for one week for rectification of the deficiencies and submission of deficit documents asper above.The matter to come up on 08.08.2022.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 08.08.2022Ar. Neeraj Gautam, Architectural Executive briefed about the facts of the project.Sh. Amit Sharma (Legal Manager) and Sh. Navin Kumar (GM) are present on behalf of the promoter.The AR submits that the deficit documents have been submitted today in the Authority except for the Bankundertaking and certificate of CA and seeks 2 weeks’ time for their submission as well as rectification ofother deficiencies. The CA of the Authority in the meanwhile to check the status of mortgage of project landand clause of the permissibility of sale subject to NOC of the financer. The AR further confirms that paymentto the financer shall be only from 30% account and not from 70% account which shall be spent only ondevelopment of the project as per RERA regulations. The condition to this effect be checked in the sanctionletter by the CA and concerned PE.The matter to come up on 22.08.2022.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 22.08.2022 Ms. Geeta Rathee Singh, Sr.L.O. briefed about the facts of the project. Sh. Amit Sharma (Legal Advisor - AR) is present on behalf of the promoter who seeks a short adjournment as the matter for Bank undertaking is still under consideration of the concerned Bank and CA certificate also could not be procured due to health limitations of the concerned CA. The matter regarding submission of approved lay out plan, demarcation and zoning plan is being taken up with main licensee promoter i.e. M/s Ansals and will be submitted in due course. The matter to come up on 12.09.2022.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 12.09.2022 Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts about the case. None is present on behalf of the promoter. One more opportunity is granted for rectifying the defects in the application for registration and submission of deficit documents. The matter to come up on 27.09.2022.
-
Hearing
Objection View order
Proceedings
Neeraj AAE (Associate Architectural Executive) briefed about the facts of the project and following major deficiencies have pointed out i.e. (1). Zoning Plan. (2). Demarcation Plan. (3). Layout Plan. (4). Bank undertaking. The matter is adjourned for 11.10.2022.
-
Hearing
Adjournment View order
Proceedings
The major deficiencies are Zoning Plan, Demarcation Plan, Layout Plan and Bank undertaking. The promoter is further advised to rectify the deficiencies and submit the deficient document apart from filing information in REP-I A to H format and detailed project information. Matter to come up on 26.10.2022.
-
Hearing
Objection
Proceedings
The coram is not complete. So the matter is adjourned for 27.10.2022.
-
Hearing
Adjournment View order
Proceedings
The promoter is directed to rectify the deficiencies and submit the deficit fee if any. The matter is adjourned for 21.11.2022.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 21.11.2022 Ms. Prachi Singh Planning Executive briefed the facts about the case. None is present on behalf of the promoter. The matter to come up on 26.12.2022. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Vijay Kumar Goyal) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram
-
Hearing
Objection View order
Proceedings
The AR of the promoter is directed to remove the deficiencies and the matter is adjourned to 09.01.2023.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 16.01.2023.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 30.01.2023.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 13.02.2023.
-
Hearing
Adjournment View order
Proceedings
Ms. Prachi Singh, Planning Executive briefed about the facts of the case. None is present on behalf of the promoter. No representative of the applicant appeared during the last three hearings and none is present today also. The deficiencies have not been rectified despite notice. In view of the above the Authority decided to issue a show cause notice as why the application for grant of registration should not be rejected on account of deficiencies as mentioned above as per provisions of section 5(2)(b) of the Act, 2016 read with rule 5(2) of Haryana Rules, 2017. If promoter has to say anything in the matter, he may represent before the authority on 13.03.2023 at 3.00 PM in the office of the authority or rectify deficiencies before that date.
-
Hearing
Adjournment View order
Proceedings
Ms. Prachi Singh, Planning Executive briefed about the facts of the case. None is present on behalf of the promoter. One last opportunity is being granted to the promoter to put in appearance failing which the applicant is liable to be rejected ex-parte. The matter to come up on 17.04.2023.
-
Hearing
Rejected View order
Proceedings
Ms. Prachi Singh, Planning Executive briefed about the facts of the case. None is present on behalf of the promoter. Even after giving more than 18 hearings the promoter is unable to rectify the deficiencies. The Authority decided to reject the application for registration of project as per section 5 of the Real Estate (Regulation and Development) Act, 2016 and rule 5 of the Haryana Real Estate (Regulation and Development) Rules, 2017. The processing fee is forfeited.
Land, licence & cost
| Land area of the project | 6.319 acres |
|---|---|
| Total licensed area | 6.319 acres |
| Licence | License no 60 of 2021 |
| FAR permissible / proposed | 1 / 1 |
| Estimated project cost | ₹ 95.66 Cr |
| Cost of land | ₹ 40.22 Cr |
| Cost of construction | ₹ 55.44 Cr |
How the land will be used
| Use | Area (as filed) | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 5,250 | 100% |
Apartments 84 units · 21 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 149.25 | 1,607 | 84 |
Areas are as filed with HRERA.
Plots 21 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 250.00 | 299 | 2,691 | 21 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | BY COLONISER | No |
| Water Supply | BY COLONISER | No |
| Electricity | BY COLONISER | No |
| Sewage Disposal | BY COLONISER | No |
| Storm Water Drainage | BY COLONISER | No |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Building Plan | Already Been Obtained | 1 Sep 2021 |
| Building Plan | Already Been Obtained | 12 Sep 2021 |
| Building Plan | Already Been Obtained | 23 Jul 2021 |
| Building Plan | Already Been Obtained | 23 Jul 2021 |
| Building Plan | Already Been Obtained | 23 Jul 2021 |
| Building Plan | Already Been Obtained | 23 Jul 2021 |
| Building Plan | Already Been Obtained | 23 Jul 2021 |
| Building Plan | Already Been Obtained | 23 Jul 2021 |
| Building Plan | Already Been Obtained | 23 Jul 2021 |
| Building Plan | Already Been Obtained | 23 Jul 2021 |
| Building Plan | Already Been Obtained | 23 Jul 2021 |
| Building Plan | Already Been Obtained | 10 Sep 2021 |
| Building Plan | Already Been Obtained | 10 Sep 2021 |
| Building Plan | Already Been Obtained | 13 Sep 2021 |
| Building Plan | Already Been Obtained | 13 Sep 2021 |
| Building Plan | Already Been Obtained | 19 Jul 2021 |
| Building Plan | Already Been Obtained | 12 Sep 2021 |
| Building Plan | Already Been Obtained | 12 Sep 2021 |
| Building Plan | Already Been Obtained | 11 Sep 2021 |
| Building Plan | Already Been Obtained | 11 Sep 2021 |
| Building Plan | Already Been Obtained | 11 Sep 2021 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified Tiles |
|---|---|
| Wall Finishing Details | Acrylic Emulsion |
| Kitchen Details | Modular Kitchen With Vitrified Tiles On Floor And Walls |
| Bathroom Fittings | Jaquar |
| Wood Work Etc | Wardrobes In All Bedrooms |
| Doors And Windos Frames | Flush Doors And Upvc Window |
| Glass Work | Tuffen Glass (6MM) |
| Electric Fittings | Panasonic Anchor |
| Conducting And Wiring Details | Plaza, Kei Or Equivalent |
| Cupboard Details | Modular Wardrobes |
| Water Storage | Pvc Water Tank Of 1000 Ltr. For Each Floor |
| Lift Details | Spire Elevators Or Equivalent |
| External Glazings | M.s Railing |
| Windows/Glazings | Upvc With 6MM Tuffen Glass |
| Doors | Flush Doors |
| Main Doors | Flush Doors |
| Internal Doors | Flush Doors |
| Air Conditioning | 2 A.c Are Provided In Each Floor |
| Electrical Fittings | Fan And Lights |
| Cng Pipe Line | N/A |
| Provision Of Wifi And Broadband Facility | N/A |
| External Finishing/Colour Scheme | Texture And Apex Paints |
| Internal Finishing | P.o.p With Pleasing Colour Of Acrylic Emulsion |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Aradhya Extension?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.